Garnet Paladium
by Garnet Construction Limited · Dindoshi malad east, Mumbai
Possession: Garnet Paladium is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800005369. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Garnet Paladium?
How the possession date of Garnet Paladium has moved
31 December 2018
Completion date given when the project was registered
30 May 2026
Extended at the builder's request (MahaRERA application EA15012619458)
Reason the builder gave MahaRERA:
“Dear Sir/Ma’am, We, Garnet Construction Limited, the Promoter of the real estate project “Garnet Paladium” bearing MahaRERA Registration No. P51800005369, hereby submit this explanatory note for your kind consideration. We respectfully stat…” Read the full reason
“Dear Sir/Ma’am, We, Garnet Construction Limited, the Promoter of the real estate project “Garnet Paladium” bearing MahaRERA Registration No. P51800005369, hereby submit this explanatory note for your kind consideration. We respectfully state that the above-mentioned project has been fully completed, and we have successfully obtained the Full Occupancy Certificate bearing No. CHE/9572/BP(WS)/AP/OCC/1/NEW of 22 September 2025, dated 22nd September 2025, from the competent authority. We further confirm that possession has been handed over to 100% of the allottees/buyers in the project, and the…”
Source: Garnet Paladium’s extension records on MahaRERA (P51800005369), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Garnet Paladium
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints and 1 court case, and how it ended
- Construction pace against the May 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800005369
- Status
- Completed
- Builder
- Garnet Construction Limited
- Location
- Dindoshi malad east, Mumbai · 400053
- Project type
- Commercial
- Registered on
- 11 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- May 2026
- Delay so far
- 89 months
- Homes
- 0
- Sold or booked
- 98%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Garnet Paladium, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Garnet Paladium | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Garnet Paladium: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Garnet Paladium every month.
Garnet Paladium: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 122 – 1,950 | 55 |
- Buildings: Garnet Paladium (9 floors, 55 units)
- Car parking: 32 covered
- Land: 1,678 sq m (about 0.4 acres) · sanctioned built-up 3,180 sq m
The builder’s record and reviews
Garnet Construction (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 87 months); 5 still being built, 1 past the promised date (typically 30 months late). 21 complaints on MahaRERA across 3 projects.
Read Google reviews of Garnet Paladium →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Garnet Paladium: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Garnet Paladium
What is the possession date of Garnet Paladium?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Garnet Paladium in Dindoshi malad east, Mumbai is 30 May 2026 — 89 months later than 31 December 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Garnet Paladium?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Garnet Paladium's builder has filed on MahaRERA, the official one, is 30 May 2026, already 89 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Garnet Paladium extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Garnet Paladium's builder applied to MahaRERA to extend the completion date once: to 30 May 2026, giving the reason "Dear Sir/Ma’am, We, Garnet Construction Limited, the Promoter of the real estate project “Garnet Paladium” bearing MahaRERA Registration No. P51800005369, hereby submit this explanatory note for your kind consideration. We respectfully state that the above-mentioned project has been fully completed, and we have successfully obtained the Full Occupancy Certificate bearing No. CHE/9572/BP(WS)/AP/OCC/1/NEW of 22 September 2025, dated 22nd September 2025, from the competent authority. We further confirm that possession has been handed over to 100% of the allottees/buyers in the project, and the…".
What is the RERA number of Garnet Paladium?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Garnet Paladium in Dindoshi malad east, Mumbai is P51800005369.
Is Garnet Paladium registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Garnet Paladium is registered as P51800005369 and its status is "Completed".
What is the construction status of Garnet Paladium?
According to GharKundli's check of MahaRERA records (updated October 2026), Garnet Paladium's status on MahaRERA is "Completed". As filed by the builder, slab work on Garnet Paladium is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Garnet Paladium have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Garnet Paladium safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Garnet Paladium is registered on MahaRERA as P51800005369, its MahaRERA status is "Completed", its completion date has moved 89 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Garnet Paladium's possession date changes?
The latest dates are on Garnet Paladium's MahaRERA page (P51800005369). GharKundli's Kundli Watch sends a free WhatsApp update on Garnet Paladium every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Garnet Paladium have?
According to GharKundli's check of MahaRERA records (updated October 2026), Garnet Paladium has one building filed: Garnet Paladium with 9 floors and 55 units.
How much parking does Garnet Paladium have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 32 covered car parking spaces for Garnet Paladium.
How big is the land of Garnet Paladium?
According to GharKundli's check of MahaRERA records (updated October 2026), Garnet Paladium stands on 1,678 sq m of land (about 0.4 acres), with 3,180 sq m of sanctioned built-up area.
What is the track record of Garnet Paladium's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Garnet Construction (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 87 months); 5 still being built, 1 past the promised date (typically 30 months late). 21 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Garnet Paladium?
Google Maps has reviews of Garnet Paladium written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Garnet Paladium?
Garnet Paladium by Garnet Construction Limited is in Dindoshi malad east, Mumbai (pincode 400053), Maharashtra, and is registered on MahaRERA as P51800005369, per GharKundli's check of MahaRERA records.
How many homes are in Garnet Paladium?
According to GharKundli's check of MahaRERA records (updated October 2026), Garnet Paladium has 0 homes in 1 tower registered on MahaRERA, and 98% of them are sold or booked.
When was Garnet Paladium registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Garnet Paladium was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Garnet Paladium?
1 court case is listed for Garnet Paladium on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Garnet Paladium?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Garnet Construction Limited, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Garnet Paladium
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Borivali
- SAFFRONWOODS CHSL
- L&T Realty Ahana Tower B
- PARSHURAM HEIGHTS
- L&T Realty Ahana Tower A
- AVIRAHI ELEGANCE
- RASHMI ICON
- MARU MANSION
- SHRADDHA SKYLINE
Other projects by Garnet Construction Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.