by Chourangi Builders and Developers Private Limited · Bandra Kurla Complex, Nagpur

Possession date of Classic Akshay: 31 December 2032, moved from 30 December 2022 (120 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500005480, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Classic Akshay?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Classic Akshay has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 31 December 2032

    Extended at the builder's request (MahaRERA application EA12022619808)

    Reason the builder gave MahaRERA:
    “Pursuant to a competitive bidding process conducted by MADC, the Applicant was selected and awarded the contract for construction of houses and social infrastructure for Project Affected People (“PAPs”). In consideration thereof, MADC grant…” Read the full reason“Pursuant to a competitive bidding process conducted by MADC, the Applicant was selected and awarded the contract for construction of houses and social infrastructure for Project Affected People (“PAPs”). In consideration thereof, MADC granted compensatory land to the CBDPL and executed a registered Lease Deed dated 8th October 2010, thereby transferring and assigning development rights in favour of the CBDPL. In furtherance of the said Lease Deed, CBDPL commenced development of the Project after obtaining Commencement Certificates and other statutory approvals. ***Development Agreement 18.0…”

Source: Classic Akshay’s extension records on MahaRERA (P50500005480), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Classic Akshay

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 court cases, and how it ended
  • Construction pace against the December 2032 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500005480
Status
Registered and active
Builder
Chourangi Builders and Developers Private Limited
Location
Bandra Kurla Complex, Nagpur · 441108
Project type
Others
Registered on
11 Aug 2017
Completion date at registration
December 2022
Latest completion date
December 2032
Delay so far
120 months
Homes
91
Sold or booked
15%
Towers
3
Complaints on MahaRERA
0
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Classic Akshay, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Akshay A Wing0%0%0%0%
Akshay B Wing0%0%0%0%
Akshay C Wing0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Akshay A Wing: covers 11 floors
  • Akshay B Wing: covers 11 floors
  • Akshay C Wing: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Classic Akshay every month.

Classic Akshay: buildings, flats and land, as filed on MahaRERA

  • Buildings: Akshay A Wing (12 floors, 47 units) · Akshay B Wing (11 floors, 56 units) · Akshay C Wing (11 floors, 47 units)
  • Land: 6,184 sq m (about 1.5 acres) · sanctioned built-up 61,650 sq m · recreational space 1,546 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Classic Akshay →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Classic Akshay: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Classic Akshay

What is the possession date of Classic Akshay?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Classic Akshay in Bandra Kurla Complex, Nagpur is 31 December 2032 — 120 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Classic Akshay?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Classic Akshay's builder has filed on MahaRERA, the official one, is 31 December 2032, already 120 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Classic Akshay extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Classic Akshay's builder applied to MahaRERA to extend the completion date once: to 31 December 2032, giving the reason "Pursuant to a competitive bidding process conducted by MADC, the Applicant was selected and awarded the contract for construction of houses and social infrastructure for Project Affected People (“PAPs”). In consideration thereof, MADC granted compensatory land to the CBDPL and executed a registered Lease Deed dated 8th October 2010, thereby transferring and assigning development rights in favour of the CBDPL. In furtherance of the said Lease Deed, CBDPL commenced development of the Project after obtaining Commencement Certificates and other statutory approvals. ***Development Agreement 18.0…".

What is the RERA number of Classic Akshay?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Classic Akshay in Bandra Kurla Complex, Nagpur is P50500005480.

Is Classic Akshay registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Classic Akshay is registered as P50500005480 and its status is "Registered and active".

What is the construction status of Classic Akshay?

According to GharKundli's check of MahaRERA records (updated October 2026), Classic Akshay's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Classic Akshay have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Classic Akshay safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Classic Akshay is registered on MahaRERA as P50500005480, its completion date has moved 120 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Classic Akshay's possession date changes?

The latest dates are on Classic Akshay's MahaRERA page (P50500005480). GharKundli's Kundli Watch sends a free WhatsApp update on Classic Akshay every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Classic Akshay have?

According to GharKundli's check of MahaRERA records (updated October 2026), Classic Akshay has 3 buildings filed: Akshay A Wing with 12 floors and 47 units; Akshay B Wing with 11 floors and 56 units; Akshay C Wing with 11 floors and 47 units.

How big is the land of Classic Akshay?

According to GharKundli's check of MahaRERA records (updated October 2026), Classic Akshay stands on 6,184 sq m of land (about 1.5 acres), with 61,650 sq m of sanctioned built-up area and 1,546 sq m of recreational open space.

Where can I read reviews of Classic Akshay?

Google Maps has reviews of Classic Akshay written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Classic Akshay?

Classic Akshay by Chourangi Builders and Developers Private Limited is in Bandra Kurla Complex, Nagpur (pincode 441108), Maharashtra, and is registered on MahaRERA as P50500005480, per GharKundli's check of MahaRERA records.

How many homes are in Classic Akshay?

According to GharKundli's check of MahaRERA records (updated October 2026), Classic Akshay has 91 homes in 3 towers registered on MahaRERA, and 15% of them are sold or booked.

When was Classic Akshay registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Classic Akshay was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Classic Akshay?

2 court cases are listed for Classic Akshay on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Classic Akshay?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Chourangi Builders and Developers Private Limited, which has 2 other projects registered on MahaRERA.

Other projects in Bandra Kurla Complex

All 303 projects in Bori (441108) →

Other projects by Chourangi Builders and Developers Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.