Metrocity Kanyakapuram
by Metrocity Homes · Dharampeth, Nagpur 440001Registered on MahaRERA as “Kanyakapuram”
What’s in the report? →Possession date of Metrocity Kanyakapuram (MahaRERA P50500009990): 30 December 2021, moved from 31 March 2018 (45 months later), and it has already passed. It has 86 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500009990. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P50500009990, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2021) has passed.
What do you want to know about Metrocity Kanyakapuram?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Metrocity Kanyakapuram has moved
31 March 2018
Completion date given when the project was registered
31 December 2020
Extended at the builder's request (MahaRERA application EXT50500002561)
Reason the builder gave MahaRERA: “Occupancy Certificate not received as there is change in Competent Authority”
30 December 2021
Revised completion date on MahaRERA
Source: Metrocity Kanyakapuram’s extension records on MahaRERA (P50500009990), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Metrocity Kanyakapuram
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500009990
- Status
- Lapsed (registration period ended)
- Builder
- Metrocity Homes
- Location
- Dharampeth, Nagpur · 440001
- Project type
- Residential / Group Housing
- Registered on
- 23 Aug 2017
- Completion date at registration
- March 2018
- Latest completion date
- December 2021
- Delay so far
- 45 months
- Homes
- 86
- Towers
- 10
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Metrocity Kanyakapuram, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 100% | 100% |
| WING B | 100% | 100% | 100% | 100% |
| WING C | 100% | 100% | 100% | 100% |
| ROW HOUSE 1 | 100% | 100% | 100% | 100% |
| ROW HOUSE 2 | 100% | 100% | 100% | 100% |
| ROW HOUSE 3 | 100% | 100% | 100% | 100% |
| ROW HOUSE 4 | 100% | 100% | 100% | 100% |
| ROW HOUSE 5 | 100% | 100% | 100% | 100% |
| ROW HOUSE 6 | 100% | 100% | 100% | 100% |
| ROW HOUSE 7 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Metrocity Kanyakapuram every 1–2 months.
Metrocity Kanyakapuram: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (9 floors) · WING B (9 floors) · WING C (6 floors) · ROW HOUSE 1 (2 floors) · ROW HOUSE 2 (2 floors) · ROW HOUSE 3 (2 floors) · ROW HOUSE 4 (2 floors) · ROW HOUSE 5 (2 floors) · and 2 more
- Land: 3,994 sq m (about 1.0 acres) · sanctioned built-up 4,993 sq m · recreational space 1,331 sq m
- Land, as filed: kh no 171/2
- Map: Get directions
The builder’s record and reviews
Metrocity Projects (a group of 3 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 18 months); 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Metrocity Kanyakapuram →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Metrocity Kanyakapuram: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Metrocity Kanyakapuram
What is the possession date of Metrocity Kanyakapuram?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Metrocity Kanyakapuram in Dharampeth, Nagpur is 30 December 2021 — 45 months later than 31 March 2018, the date given at registration. That date has already passed.
The date has already moved 45 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Metrocity Kanyakapuram?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Metrocity Kanyakapuram's builder has filed on MahaRERA, the official one, is 30 December 2021, already 45 months later than the 31 March 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Metrocity Kanyakapuram extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Metrocity Kanyakapuram's builder applied to MahaRERA to extend the completion date once: to 31 December 2020, giving the reason "Occupancy Certificate not received as there is change in Competent Authority".
What is the RERA number of Metrocity Kanyakapuram?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Metrocity Kanyakapuram in Dharampeth, Nagpur is P50500009990.
Is Metrocity Kanyakapuram registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Metrocity Kanyakapuram is registered as P50500009990 and its status is "Lapsed (registration period ended)".
What is the current construction status of Metrocity Kanyakapuram? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Metrocity Kanyakapuram's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 10 towers. GharKundli's full report compares construction progress with the deadline.
Does Metrocity Kanyakapuram have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Metrocity Kanyakapuram safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Metrocity Kanyakapuram is registered on MahaRERA as P50500009990, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 45 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Metrocity Kanyakapuram?
Metrocity Kanyakapuram isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Metrocity Kanyakapuram?
For a flat in Metrocity Kanyakapuram (Nagpur), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Transport Surcharge + 1% LBT. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Metrocity Kanyakapuram received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Metrocity Kanyakapuram isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Metrocity Kanyakapuram?
According to GharKundli's check of MahaRERA records (updated November 2026), Metrocity Kanyakapuram's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Metrocity Kanyakapuram uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Metrocity Kanyakapuram was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Metrocity Kanyakapuram's possession date changes?
The latest dates are on Metrocity Kanyakapuram's MahaRERA page (P50500009990). GharKundli's Kundli Watch sends a free WhatsApp update on Metrocity Kanyakapuram every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Metrocity Kanyakapuram have?
According to GharKundli's check of MahaRERA records (updated November 2026), Metrocity Kanyakapuram has 10 buildings filed: WING A with 9 floors; WING B with 9 floors; WING C with 6 floors; ROW HOUSE 1 with 2 floors; ROW HOUSE 2 with 2 floors; ROW HOUSE 3 with 2 floors; and 4 more.
How big is the land of Metrocity Kanyakapuram?
According to GharKundli's check of MahaRERA records (updated November 2026), Metrocity Kanyakapuram stands on 3,994 sq m of land (about 1.0 acres), with 4,993 sq m of sanctioned built-up area and 1,331 sq m of recreational open space.
What is the track record of Metrocity Kanyakapuram's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Metrocity Projects (a group of 3 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 18 months); 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Metrocity Kanyakapuram?
Google Maps has reviews of Metrocity Kanyakapuram written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Metrocity Kanyakapuram?
Metrocity Kanyakapuram by Metrocity Homes is in Dharampeth, Nagpur, pincode 440001, Maharashtra, and is registered on MahaRERA as P50500009990, per GharKundli's check of MahaRERA records. Its land is filed as kh no 171/2. GharKundli lists all 26 MahaRERA projects in Nagpur (440001).
How many flats are in Metrocity Kanyakapuram?
According to GharKundli's check of MahaRERA records (updated November 2026), Metrocity Kanyakapuram has 86 homes in 10 towers registered on MahaRERA.
When was Metrocity Kanyakapuram registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Metrocity Kanyakapuram was registered on MahaRERA on 23 August 2017. GharKundli did not find a title report on the land on file there.
Does Metrocity Kanyakapuram have any legal issues or court cases?
No court cases are listed for Metrocity Kanyakapuram on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Metrocity Kanyakapuram?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Metrocity Homes.
Check it yourself on MahaRERA
- How to check the possession date of Metrocity Kanyakapuram
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nagpur (440001)
All 26 projects in Nagpur (440001) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.