SHEWALKAR LAKE-VIEW

by SHEWALKAR DEVELOPERS LIMITED · Dharampeth, NagpurAlso near Parsodi, A.D. Project, Jaitala

Possession date of SHEWALKAR LAKE-VIEW: 30 September 2024, moved from 31 December 2018 (69 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P50500008244. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (September 2024) has passed.

What do you want to know about SHEWALKAR LAKE-VIEW?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHEWALKAR LAKE-VIEW has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT50500000196)

    Reason the builder gave MahaRERA: “The Project came under Metro Corridor regulation and hence needs revised sanction before applying for Occupation Permit.”
  3. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT50500002345)

    Reason the builder gave MahaRERA: “We wish to start the second phase of our project “SHEWALKAR LAKE-VIEW” situated at Subhash Nagar T-Point, Hingna Road, Nagpur, for which we have applied for revised sanction of plan. We have not yet received the revised sanction.”
  4. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT50500008485)

    Reason the builder gave MahaRERA: “70% construction is done want extension to complete the project.”
  5. 30 September 2024

    Revised completion date on MahaRERA

Source: SHEWALKAR LAKE-VIEW’s extension records on MahaRERA (P50500008244), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHEWALKAR LAKE-VIEW

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500008244
Status
Lapsed (registration period ended)
Builder
SHEWALKAR DEVELOPERS LIMITED
Location
Dharampeth, Nagpur · 440022
Project type
Others
Registered on
18 Aug 2017
Completion date at registration
December 2018
Latest completion date
September 2024
Delay so far
69 months
Homes
38
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of SHEWALKAR LAKE-VIEW, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHEWALKAR LAKE-VIEW100%100%100%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHEWALKAR LAKE-VIEW every month.

SHEWALKAR LAKE-VIEW: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Shewalkar Developers has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 91 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of SHEWALKAR LAKE-VIEW →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHEWALKAR LAKE-VIEW: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHEWALKAR LAKE-VIEW

What is the possession date of SHEWALKAR LAKE-VIEW?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHEWALKAR LAKE-VIEW in Dharampeth, Nagpur is 30 September 2024 — 69 months later than 31 December 2018, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SHEWALKAR LAKE-VIEW?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHEWALKAR LAKE-VIEW's builder has filed on MahaRERA, the official one, is 30 September 2024, already 69 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHEWALKAR LAKE-VIEW extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHEWALKAR LAKE-VIEW's builder applied to MahaRERA to extend the completion date 3 times: to 30 April 2020, giving the reason "The Project came under Metro Corridor regulation and hence needs revised sanction before applying for Occupation Permit."; to 30 April 2020, giving the reason "We wish to start the second phase of our project “SHEWALKAR LAKE-VIEW” situated at Subhash Nagar T-Point, Hingna Road, Nagpur, for which we have applied for revised sanction of plan. We have not yet received the revised sanction."; to 31 March 2024, giving the reason "70% construction is done want extension to complete the project.".

What is the RERA number of SHEWALKAR LAKE-VIEW?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHEWALKAR LAKE-VIEW in Dharampeth, Nagpur is P50500008244.

Is SHEWALKAR LAKE-VIEW registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHEWALKAR LAKE-VIEW is registered as P50500008244 and its status is "Lapsed (registration period ended)".

What is the construction status of SHEWALKAR LAKE-VIEW?

According to GharKundli's check of MahaRERA records (updated November 2026), SHEWALKAR LAKE-VIEW's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHEWALKAR LAKE-VIEW is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SHEWALKAR LAKE-VIEW have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SHEWALKAR LAKE-VIEW safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHEWALKAR LAKE-VIEW is registered on MahaRERA as P50500008244, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 69 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHEWALKAR LAKE-VIEW's possession date changes?

The latest dates are on SHEWALKAR LAKE-VIEW's MahaRERA page (P50500008244). GharKundli's Kundli Watch sends a free WhatsApp update on SHEWALKAR LAKE-VIEW every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHEWALKAR LAKE-VIEW have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHEWALKAR LAKE-VIEW has one building filed: SHEWALKAR LAKE-VIEW with 7 floors.

How big is the land of SHEWALKAR LAKE-VIEW?

According to GharKundli's check of MahaRERA records (updated November 2026), SHEWALKAR LAKE-VIEW stands on 1,491 sq m of land (about 0.4 acres), with 1,863 sq m of sanctioned built-up area.

What is the track record of SHEWALKAR LAKE-VIEW's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Shewalkar Developers has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 91 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SHEWALKAR LAKE-VIEW?

Google Maps has reviews of SHEWALKAR LAKE-VIEW written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHEWALKAR LAKE-VIEW?

SHEWALKAR LAKE-VIEW by SHEWALKAR DEVELOPERS LIMITED is in Dharampeth, Nagpur (pincode 440022), near Parsodi, A.D. Project, Jaitala, Maharashtra, and is registered on MahaRERA as P50500008244, per GharKundli's check of MahaRERA records. Its boundaries filed there include HINGNA ROAD.

How many homes are in SHEWALKAR LAKE-VIEW?

According to GharKundli's check of MahaRERA records (updated November 2026), SHEWALKAR LAKE-VIEW has 38 homes in 1 tower registered on MahaRERA.

When was SHEWALKAR LAKE-VIEW registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHEWALKAR LAKE-VIEW was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHEWALKAR LAKE-VIEW?

No court cases are listed for SHEWALKAR LAKE-VIEW on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHEWALKAR LAKE-VIEW?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHEWALKAR DEVELOPERS LIMITED, which has 3 other projects registered on MahaRERA.

Other projects in Dharampeth

All 55 projects in Ranapratap Nagar (440022) →

Other projects by SHEWALKAR DEVELOPERS LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.