Skip to content
GharKundli

SIDDHI SAMARPAN

by Neha Hemant Agrawal · Elphistone West, MumbaiAlso near Dahisar East, Borivali West

Possession date of SIDDHI SAMARPAN: 30 October 2020, moved from 31 December 2018 (22 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800008947. Status: Lapsed (registration period ended). 13 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (October 2020) has passed.

What do you want to know about SIDDHI SAMARPAN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SIDDHI SAMARPAN has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51800001170)

    Reason the builder gave MahaRERA:
    “A) Sir, our Revised amended CFO was cleared on 05/12/2017. (CFO No. FB/HRC/RIV/25 dated 05/12/2017). Sir we had to supply additional / alternate supply of power, as per CFO requirement for the fire equipment’s and fire lift. Reliance Infras…” Read the full reason“A) Sir, our Revised amended CFO was cleared on 05/12/2017. (CFO No. FB/HRC/RIV/25 dated 05/12/2017). Sir we had to supply additional / alternate supply of power, as per CFO requirement for the fire equipment’s and fire lift. Reliance Infrastructure Ltd. has approved the same on 16/02/2018., with conditions as mentioned in their, BILL OF SUPPLY, ELECTRICITY SERVICES CHARGES, (5 different contracts), dated 16/02/2018. Hence we are awaiting supply of additional / alternate line by Adani Electricity Ltd., (formerly Reliance Infrastructure Ltd.) and then approvals / occupation certification. B)…”
  3. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51800005088)

    Reason the builder gave MahaRERA:
    “B) Sir, as per our revised amended CFO, cleared on 05/12/2017.(CFO No.FB/HRC/RIV/25 dated 05/12/2017), I had to supply additional /alternate supply of power , as per CFO requirement for fire equipment’s and fire lift. Adani Electricity Ltd…” Read the full reason“B) Sir, as per our revised amended CFO, cleared on 05/12/2017.(CFO No.FB/HRC/RIV/25 dated 05/12/2017), I had to supply additional /alternate supply of power , as per CFO requirement for fire equipment’s and fire lift. Adani Electricity Ltd (formely Reliance Infrastructure Ltd) has approved the same on 16/02/2018. Sir, as, I have already paid the amount to Adani Electricity Ltd about 15 months ago but still we have not received any supply from them. Sir, I have also written and send and delivered letters to Adani Electricity from time to time, and send many reminders for the same. Sir, I am…”
  4. 30 October 2020

    Revised completion date on MahaRERA

Source: SIDDHI SAMARPAN’s extension records on MahaRERA (P51800008947), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SIDDHI SAMARPAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 13 complaints and 3 court cases, and how it ended
  • Construction pace against the October 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800008947
Status
Lapsed (registration period ended)
Builder
Neha Hemant Agrawal
Location
Elphistone West, Mumbai · 400068
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
December 2018
Latest completion date
October 2020
Delay so far
22 months
Homes
64
Towers
1
Complaints on MahaRERA
13
Court cases listed
3
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of SIDDHI SAMARPAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Siddhi Samarpan100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SIDDHI SAMARPAN every month.

SIDDHI SAMARPAN: buildings, flats and land, as filed on MahaRERA

  • Buildings: Siddhi Samarpan (46 floors)
  • Land: 2,510 sq m (about 0.6 acres) · sanctioned built-up 3,546 sq m · recreational space 100 sq m
  • Boundaries filed include: Shivam Complex
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SIDDHI SAMARPAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SIDDHI SAMARPAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SIDDHI SAMARPAN

What is the possession date of SIDDHI SAMARPAN?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SIDDHI SAMARPAN in Elphistone West, Mumbai is 30 October 2020 — 22 months later than 31 December 2018, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SIDDHI SAMARPAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SIDDHI SAMARPAN's builder has filed on MahaRERA, the official one, is 30 October 2020, already 22 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SIDDHI SAMARPAN extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHI SAMARPAN's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2020, giving the reason "A) Sir, our Revised amended CFO was cleared on 05/12/2017. (CFO No. FB/HRC/RIV/25 dated 05/12/2017). Sir we had to supply additional / alternate supply of power, as per CFO requirement for the fire equipment’s and fire lift. Reliance Infrastructure Ltd. has approved the same on 16/02/2018., with conditions as mentioned in their, BILL OF SUPPLY, ELECTRICITY SERVICES CHARGES, (5 different contracts), dated 16/02/2018. Hence we are awaiting supply of additional / alternate line by Adani Electricity Ltd., (formerly Reliance Infrastructure Ltd.) and then approvals / occupation certification. B)…"; to 30 April 2020, giving the reason "B) Sir, as per our revised amended CFO, cleared on 05/12/2017.(CFO No.FB/HRC/RIV/25 dated 05/12/2017), I had to supply additional /alternate supply of power , as per CFO requirement for fire equipment’s and fire lift. Adani Electricity Ltd (formely Reliance Infrastructure Ltd) has approved the same on 16/02/2018. Sir, as, I have already paid the amount to Adani Electricity Ltd about 15 months ago but still we have not received any supply from them. Sir, I have also written and send and delivered letters to Adani Electricity from time to time, and send many reminders for the same. Sir, I am…".

What is the RERA number of SIDDHI SAMARPAN?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SIDDHI SAMARPAN in Elphistone West, Mumbai is P51800008947.

Is SIDDHI SAMARPAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHI SAMARPAN is registered as P51800008947 and its status is "Lapsed (registration period ended)".

What is the construction status of SIDDHI SAMARPAN?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHI SAMARPAN's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Siddhi Samarpan is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SIDDHI SAMARPAN have complaints on MahaRERA?

13 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SIDDHI SAMARPAN safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHI SAMARPAN is registered on MahaRERA as P51800008947, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 22 months since registration and 13 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SIDDHI SAMARPAN's possession date changes?

The latest dates are on SIDDHI SAMARPAN's MahaRERA page (P51800008947). GharKundli's Kundli Watch sends a free WhatsApp update on SIDDHI SAMARPAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SIDDHI SAMARPAN have?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHI SAMARPAN has one building filed: Siddhi Samarpan with 46 floors.

How big is the land of SIDDHI SAMARPAN?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHI SAMARPAN stands on 2,510 sq m of land (about 0.6 acres), with 3,546 sq m of sanctioned built-up area and 100 sq m of recreational open space.

Where can I read reviews of SIDDHI SAMARPAN?

Google Maps has reviews of SIDDHI SAMARPAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 13 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SIDDHI SAMARPAN?

SIDDHI SAMARPAN by Neha Hemant Agrawal is in Elphistone West, Mumbai (pincode 400068), near Dahisar East, Borivali West, Maharashtra, and is registered on MahaRERA as P51800008947, per GharKundli's check of MahaRERA records. Its boundaries filed there include Shivam Complex.

How many homes are in SIDDHI SAMARPAN?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHI SAMARPAN has 64 homes in 1 tower registered on MahaRERA.

When was SIDDHI SAMARPAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SIDDHI SAMARPAN was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SIDDHI SAMARPAN?

3 court cases are listed for SIDDHI SAMARPAN on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SIDDHI SAMARPAN?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Neha Hemant Agrawal.

Other projects in Borivali

All 180 projects in Dahisar East (400068) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.