Sunrise Park
by Sirsikar Developers & Builders Pvt. Ltd. · Mouza Turakmari, Nagpur
Possession date of Sunrise Park: 31 December 2031, moved from 30 March 2026 (69 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50500023546, and currently active. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Sunrise Park?
How the possession date of Sunrise Park has moved
30 March 2026
Completion date given when the project was registered
31 December 2031
Extended at the builder's request (MahaRERA application EA30032620465)
Reason the builder gave MahaRERA:
“To, The Chairperson / Secretary, Real Estate Regulatory Authority (RERA), Maharashtra Subject: Request for extension of RERA Registration for Project SUNRISE PARK (Registration No: P50500023546) regarding pending phases. Respected Sir/Madam…” Read the full reason
“To, The Chairperson / Secretary, Real Estate Regulatory Authority (RERA), Maharashtra Subject: Request for extension of RERA Registration for Project SUNRISE PARK (Registration No: P50500023546) regarding pending phases. Respected Sir/Madam, We are writing to request an extension of the registration for our project, SUNRISE PARK, which consists of a total of 8 Buildings. The current registration is valid until 30-03-2026, and we request an extension until 31-12-2031. We would like to bring to your notice the current ground reality and the reasons for this request: • Current Progress: Out of…”
Source: Sunrise Park’s extension records on MahaRERA (P50500023546), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sunrise Park
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the December 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500023546
- Status
- Registered and active
- Builder
- Sirsikar Developers & Builders Pvt. Ltd.
- Location
- Mouza Turakmari, Nagpur · 440016
- Project type
- Others
- Registered on
- 18 Dec 2019
- Completion date at registration
- March 2026
- Latest completion date
- December 2031
- Delay so far
- 69 months
- Homes
- 441
- Sold or booked
- 13%
- Towers
- 8
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sunrise Park, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 1 | 80% | 80% | 60% | 10% |
| 2 | 100% | 100% | 100% | 50% |
| 3 | 0% | 0% | 0% | 0% |
| 4 | 0% | 0% | 0% | 0% |
| 5 | 0% | 0% | 0% | 0% |
| 6 | 0% | 0% | 0% | 0% |
| 7 | 0% | 0% | 0% | 0% |
| 8 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- 1: covers 8 floors
- 2: covers 7 floors
- 3: covers 6 floors
- 4: covers 6 floors
- 5: covers 7 floors
- 6: covers 7 floors
- 7: covers 7 floors
- 8: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sunrise Park every month.
Sunrise Park: buildings, flats and land, as filed on MahaRERA
- Buildings: 1 (9 floors, 64 units) · 2 (8 floors, 52 units) · 3 (8 floors, 54 units) · 4 (8 floors, 56 units) · 5 (9 floors, 60 units) · 6 (9 floors, 60 units) · 7 (8 floors, 60 units) · 8 (9 floors, 64 units)
- Land: 17,036 sq m (about 4.2 acres) · sanctioned built-up 21,364 sq m · recreational space 3,544 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Sunrise Park →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sunrise Park: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sunrise Park
What is the possession date of Sunrise Park?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sunrise Park in Mouza Turakmari, Nagpur is 31 December 2031 — 69 months later than 30 March 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Sunrise Park?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sunrise Park's builder has filed on MahaRERA, the official one, is 31 December 2031, already 69 months later than the 30 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sunrise Park extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Park's builder applied to MahaRERA to extend the completion date once: to 31 December 2031, giving the reason "To, The Chairperson / Secretary, Real Estate Regulatory Authority (RERA), Maharashtra Subject: Request for extension of RERA Registration for Project SUNRISE PARK (Registration No: P50500023546) regarding pending phases. Respected Sir/Madam, We are writing to request an extension of the registration for our project, SUNRISE PARK, which consists of a total of 8 Buildings. The current registration is valid until 30-03-2026, and we request an extension until 31-12-2031. We would like to bring to your notice the current ground reality and the reasons for this request: • Current Progress: Out of…".
What is the RERA number of Sunrise Park?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sunrise Park in Mouza Turakmari, Nagpur is P50500023546.
Is Sunrise Park registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Park is registered as P50500023546 and its status is "Registered and active".
What is the construction status of Sunrise Park?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Park's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 8 towers. GharKundli's full report compares construction progress with the deadline.
Does Sunrise Park have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Sunrise Park safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Park is registered on MahaRERA as P50500023546, its completion date has moved 69 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Sunrise Park's possession date changes?
The latest dates are on Sunrise Park's MahaRERA page (P50500023546). GharKundli's Kundli Watch sends a free WhatsApp update on Sunrise Park every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sunrise Park have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Park has 8 buildings filed: 1 with 9 floors and 64 units; 2 with 8 floors and 52 units; 3 with 8 floors and 54 units; 4 with 8 floors and 56 units; 5 with 9 floors and 60 units; 6 with 9 floors and 60 units; and 2 more.
How big is the land of Sunrise Park?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Park stands on 17,036 sq m of land (about 4.2 acres), with 21,364 sq m of sanctioned built-up area and 3,544 sq m of recreational open space.
Where can I read reviews of Sunrise Park?
Google Maps has reviews of Sunrise Park written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sunrise Park?
Sunrise Park by Sirsikar Developers & Builders Pvt. Ltd. is in Mouza Turakmari, Nagpur (pincode 440016), Maharashtra, and is registered on MahaRERA as P50500023546, per GharKundli's check of MahaRERA records.
How many homes are in Sunrise Park?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Park has 441 homes in 8 towers registered on MahaRERA, and 13% of them are sold or booked.
When was Sunrise Park registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Park was registered on MahaRERA on 18 December 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Sunrise Park?
No court cases are listed for Sunrise Park on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Sunrise Park?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sirsikar Developers & Builders Pvt. Ltd..
Check it yourself on MahaRERA
- How to check the possession date of Sunrise Park
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Nagpur →
Other projects in Hingna
- Vrindavan Park-18
- Elite Homes
- SWAMI NAGARI-2
- GREEN GOLD
- DIVYANJALI APARTMENTS
- ARTHAM ONE
- MAULI INFINITY SQUARE 39
- Samarth Nagar
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.