MADHAV-1 COMPLEX
by VIJAY MADHAVRAO CHIKTE · Wathoda, Nagpur
Possession date of MADHAV-1 COMPLEX: 28 November 2024, moved from 28 November 2022 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P50500024665. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (November 2024) has passed.
What do you want to know about MADHAV-1 COMPLEX?
How the possession date of MADHAV-1 COMPLEX has moved
28 November 2022
Completion date given when the project was registered
28 November 2024
Extended at the builder's request (MahaRERA application EXT50500012922)
Reason the builder gave MahaRERA:
“As we all have faced many issues because of pandemic in our life like financial, health, workers, team and etc.my project Madhav-1 complex is also got delay in its construction due to financial issues still lots of work are left in the proj…” Read the full reason
“As we all have faced many issues because of pandemic in our life like financial, health, workers, team and etc.my project Madhav-1 complex is also got delay in its construction due to financial issues still lots of work are left in the project completion now I have recover the amount to complete my project, so I Vijay Madhav Rao Chikte request MahaRERA to plz give extension so that I can complete my project in the requested time limit.”
Source: MADHAV-1 COMPLEX’s extension records on MahaRERA (P50500024665), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MADHAV-1 COMPLEX
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50500024665
- Status
- Lapsed (registration period ended)
- Builder
- VIJAY MADHAVRAO CHIKTE
- Location
- Wathoda, Nagpur · 440034
- Project type
- Residential / Group Housing
- Registered on
- 28 Feb 2020
- Completion date at registration
- November 2022
- Latest completion date
- November 2024
- Delay so far
- 24 months
- Homes
- 13
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of MADHAV-1 COMPLEX, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MADHAV-1 COMPLEX | 100% | 100% | 80% | 65% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MADHAV-1 COMPLEX every month.
MADHAV-1 COMPLEX: buildings, flats and land, as filed on MahaRERA
- Buildings: MADHAV-1 COMPLEX (17 floors)
- Land: 385 sq m (about 0.1 acres) · sanctioned built-up 499 sq m · recreational space 68 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Vijay Madhavrao Chikte has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 16 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of MADHAV-1 COMPLEX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MADHAV-1 COMPLEX: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MADHAV-1 COMPLEX
What is the possession date of MADHAV-1 COMPLEX?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MADHAV-1 COMPLEX in Wathoda, Nagpur is 28 November 2024 — 24 months later than 28 November 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for MADHAV-1 COMPLEX?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MADHAV-1 COMPLEX's builder has filed on MahaRERA, the official one, is 28 November 2024, already 24 months later than the 28 November 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MADHAV-1 COMPLEX extended?
According to GharKundli's check of MahaRERA records (updated November 2026), MADHAV-1 COMPLEX's builder applied to MahaRERA to extend the completion date once: to 28 November 2024, giving the reason "As we all have faced many issues because of pandemic in our life like financial, health, workers, team and etc.my project Madhav-1 complex is also got delay in its construction due to financial issues still lots of work are left in the project completion now I have recover the amount to complete my project, so I Vijay Madhav Rao Chikte request MahaRERA to plz give extension so that I can complete my project in the requested time limit.".
What is the RERA number of MADHAV-1 COMPLEX?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MADHAV-1 COMPLEX in Wathoda, Nagpur is P50500024665.
Is MADHAV-1 COMPLEX registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MADHAV-1 COMPLEX is registered as P50500024665 and its status is "Lapsed (registration period ended)".
What is the construction status of MADHAV-1 COMPLEX?
According to GharKundli's check of MahaRERA records (updated November 2026), MADHAV-1 COMPLEX's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MADHAV-1 COMPLEX is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does MADHAV-1 COMPLEX have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is MADHAV-1 COMPLEX safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), MADHAV-1 COMPLEX is registered on MahaRERA as P50500024665, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MADHAV-1 COMPLEX's possession date changes?
The latest dates are on MADHAV-1 COMPLEX's MahaRERA page (P50500024665). GharKundli's Kundli Watch sends a free WhatsApp update on MADHAV-1 COMPLEX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MADHAV-1 COMPLEX have?
According to GharKundli's check of MahaRERA records (updated November 2026), MADHAV-1 COMPLEX has one building filed: MADHAV-1 COMPLEX with 17 floors.
How big is the land of MADHAV-1 COMPLEX?
According to GharKundli's check of MahaRERA records (updated November 2026), MADHAV-1 COMPLEX stands on 385 sq m of land (about 0.1 acres), with 499 sq m of sanctioned built-up area and 68 sq m of recreational open space.
What is the track record of MADHAV-1 COMPLEX's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Vijay Madhavrao Chikte has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 16 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MADHAV-1 COMPLEX?
Google Maps has reviews of MADHAV-1 COMPLEX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MADHAV-1 COMPLEX?
MADHAV-1 COMPLEX by VIJAY MADHAVRAO CHIKTE is in Wathoda, Nagpur (pincode 440034), Maharashtra, and is registered on MahaRERA as P50500024665, per GharKundli's check of MahaRERA records.
How many homes are in MADHAV-1 COMPLEX?
According to GharKundli's check of MahaRERA records (updated November 2026), MADHAV-1 COMPLEX has 13 homes in 1 tower registered on MahaRERA.
When was MADHAV-1 COMPLEX registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MADHAV-1 COMPLEX was registered on MahaRERA on 28 February 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on MADHAV-1 COMPLEX?
No court cases are listed for MADHAV-1 COMPLEX on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of MADHAV-1 COMPLEX?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VIJAY MADHAVRAO CHIKTE, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MADHAV-1 COMPLEX
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Wathoda
All 120 projects in Mhalginagar (440034) →Other projects by VIJAY MADHAVRAO CHIKTE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.