Anandam Park

by Pankaj Chandrakant Waghmare · Panjari FArm, Nagpur

Possession: Anandam Park is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500027394. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Anandam Park?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Anandam Park has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT50500017336)

    Reason the builder gave MahaRERA:
    “With respect our residential plotted project named and styled as “ANANDAM PARK”, Kh. No. 91, PH No. 42, Village & Mouza – Panjari (Farm), Taluka – Nagpur (Rural), Distt. – Nagpur., vide Project Registration Number as - P50500027394; due to…” Read the full reason“With respect our residential plotted project named and styled as “ANANDAM PARK”, Kh. No. 91, PH No. 42, Village & Mouza – Panjari (Farm), Taluka – Nagpur (Rural), Distt. – Nagpur., vide Project Registration Number as - P50500027394; due to the slowdown in the real estate market in the region, we could not complete the few development works related to the completion of the project. We would require some more time to complete the development of the project. Hence, we hereby request your authority to kindly grant the requisite extension of the permission to complete the project.”

Source: Anandam Park’s extension records on MahaRERA (P50500027394), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Anandam Park

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500027394
Status
Completed
Builder
Pankaj Chandrakant Waghmare
Location
Panjari FArm, Nagpur · 441108
Project type
Plotted
Registered on
8 Dec 2020
Completion date at registration
June 2023
Latest completion date
December 2026
Delay so far
42 months
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
11

Anandam Park: buildings, flats and land, as filed on MahaRERA

  • Land: 5,592 sq m (about 1.4 acres) · recreational space 1,546 sq m

The builder’s record and reviews

Pankaj Chandrakant Waghmare has 12 projects on MahaRERA since 2019, this one included. Of the 9 GharKundli has checked: 6 finished, 5 within the promised date and 1 needed more time (typically 10 months); 3 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA.

Read Google reviews of Anandam Park →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Anandam Park: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Anandam Park

What is the possession date of Anandam Park?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Anandam Park in Panjari FArm, Nagpur is 31 December 2026 — 42 months later than 30 June 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Anandam Park?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Anandam Park's builder has filed on MahaRERA, the official one, is 31 December 2026, already 42 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Anandam Park extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Park's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "With respect our residential plotted project named and styled as “ANANDAM PARK”, Kh. No. 91, PH No. 42, Village & Mouza – Panjari (Farm), Taluka – Nagpur (Rural), Distt. – Nagpur., vide Project Registration Number as - P50500027394; due to the slowdown in the real estate market in the region, we could not complete the few development works related to the completion of the project. We would require some more time to complete the development of the project. Hence, we hereby request your authority to kindly grant the requisite extension of the permission to complete the project.".

What is the RERA number of Anandam Park?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Anandam Park in Panjari FArm, Nagpur is P50500027394.

Is Anandam Park registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Park is registered as P50500027394 and its status is "Completed".

What is the construction status of Anandam Park?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Park's status on MahaRERA is "Completed". GharKundli's full report compares construction progress with the deadline.

Does Anandam Park have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Anandam Park safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Park is registered on MahaRERA as P50500027394, its MahaRERA status is "Completed", its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Anandam Park's possession date changes?

The latest dates are on Anandam Park's MahaRERA page (P50500027394). GharKundli's Kundli Watch sends a free WhatsApp update on Anandam Park every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Anandam Park?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Park stands on 5,592 sq m of land (about 1.4 acres) and 1,546 sq m of recreational open space.

What is the track record of Anandam Park's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Pankaj Chandrakant Waghmare has 12 projects on MahaRERA since 2019, this one included. Of the 9 GharKundli has checked: 6 finished, 5 within the promised date and 1 needed more time (typically 10 months); 3 still being built, 1 past the promised date (typically 22 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Anandam Park?

Google Maps has reviews of Anandam Park written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Anandam Park?

Anandam Park by Pankaj Chandrakant Waghmare is in Panjari FArm, Nagpur (pincode 441108), Maharashtra, and is registered on MahaRERA as P50500027394, per GharKundli's check of MahaRERA records.

When was Anandam Park registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandam Park was registered on MahaRERA on 8 December 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on Anandam Park?

No court cases are listed for Anandam Park on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Anandam Park?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Pankaj Chandrakant Waghmare, which has 11 other projects registered on MahaRERA.

Other projects in Nagpur (Rural)

All 303 projects in Bori (441108) →

Other projects by Pankaj Chandrakant Waghmare

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.