by OZEN DEVELOPERS · Wela Hari, Nagpur 441108Registered on MahaRERA as “INSIGHT”

What’s in the report? →

Possession date of Ozen Insight (MahaRERA P50500030523): 31 December 2023, and it has already passed. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500030523. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P50500030523, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about Ozen Insight?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Ozen Insight

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500030523
Status
Lapsed (registration period ended)
Builder
OZEN DEVELOPERS
Location
Wela Hari, Nagpur · 441108
Project type
Plotted
Registered on
30 Aug 2021
Completion date at registration
December 2023
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Ozen Insight: buildings, flats and land, as filed on MahaRERA

  • Land: 12,000 sq m (about 3.0 acres) · recreational space 1,070 sq m
  • Land, as filed: KH NO 195 MOUZA WELA HARI TAH NAGPUR RURAL DIST NAGPUR
  • Map: Get directions

The builder’s record and reviews

Ozen Developers has 5 projects on MahaRERA since 2021, this one included. Of the 5 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 11 months); 1 still being built, 1 past the promised date (typically 34 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Ozen Insight →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ozen Insight: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Ozen Insight

What is the possession date of Ozen Insight?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Ozen Insight in Wela Hari, Nagpur is 31 December 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Ozen Insight?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ozen Insight's builder has filed on MahaRERA, the official one, is 31 December 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Ozen Insight?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Ozen Insight in Wela Hari, Nagpur is P50500030523.

Is Ozen Insight registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ozen Insight is registered as P50500030523 and its status is "Lapsed (registration period ended)".

What is the current construction status of Ozen Insight? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Ozen Insight's status on MahaRERA is "Lapsed (registration period ended)". GharKundli's full report compares construction progress with the deadline.

Does Ozen Insight have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Ozen Insight safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Ozen Insight is registered on MahaRERA as P50500030523, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Ozen Insight?

Ozen Insight isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Ozen Insight?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Ozen Insight: gharkundli.com/tools/property-cost-calculator

Has Ozen Insight received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Ozen Insight isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Ozen Insight?

According to GharKundli's check of MahaRERA records (updated November 2026), Ozen Insight's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Ozen Insight uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Ozen Insight was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Ozen Insight's possession date changes?

The latest dates are on Ozen Insight's MahaRERA page (P50500030523). GharKundli's Kundli Watch sends a free WhatsApp update on Ozen Insight every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Ozen Insight?

According to GharKundli's check of MahaRERA records (updated November 2026), Ozen Insight stands on 12,000 sq m of land (about 3.0 acres) and 1,070 sq m of recreational open space.

What is the track record of Ozen Insight's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Ozen Developers has 5 projects on MahaRERA since 2021, this one included. Of the 5 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 11 months); 1 still being built, 1 past the promised date (typically 34 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Ozen Insight?

Google Maps has reviews of Ozen Insight written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Ozen Insight?

Ozen Insight by OZEN DEVELOPERS is in Wela Hari, Nagpur, pincode 441108, Maharashtra, and is registered on MahaRERA as P50500030523, per GharKundli's check of MahaRERA records. Its land is filed as KH NO 195 MOUZA WELA HARI TAH NAGPUR RURAL DIST NAGPUR. GharKundli lists all 430 MahaRERA projects in Bori (441108).

When was Ozen Insight registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ozen Insight was registered on MahaRERA on 30 August 2021. GharKundli did not find a title report on the land on file there.

Does Ozen Insight have any legal issues or court cases?

No court cases are listed for Ozen Insight on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Ozen Insight?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is OZEN DEVELOPERS, which has 4 other projects registered on MahaRERA.

Other projects in Bori (441108)

All 430 projects in Bori (441108) →

Other projects by OZEN DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.