Arista
by Jitendra Shankerlal Brahmbhatt · Goregaon West, MumbaiAlso near Kalanagar, Oshiwara, Goregaon East
Possession date of Arista: 31 March 2028, moved from 30 December 2022 (63 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800003375, and currently active. MahaRERA has issued a regulatory order on this project. 43 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Arista?
How the possession date of Arista has moved
30 December 2022
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800017067)
Reason the builder gave MahaRERA:
“The main reason for stalling of project was the health of the promoter. He has faced multiple operations and therapy before resuming in office. The allottees of the ongoing project putting forward their various demands in terms of the posse…” Read the full reason
“The main reason for stalling of project was the health of the promoter. He has faced multiple operations and therapy before resuming in office. The allottees of the ongoing project putting forward their various demands in terms of the possession of the Flat.”31 March 2028
Extended at the builder's request (MahaRERA application EA12032620195)
Reason the builder gave MahaRERA:
“C wing construction upto 29th floor is started as per the revised CC approved on 25th July 2024. The total provision of C wing is 42 floors & it's construction will finish as per approval received from Mhada. due to this we applied extensio…” Read the full reason
“C wing construction upto 29th floor is started as per the revised CC approved on 25th July 2024. The total provision of C wing is 42 floors & it's construction will finish as per approval received from Mhada. due to this we applied extension till 31/03/2028. In the mean time the Proprietor of the firm is demised due to sever illness of last 3 years that is reason of delayed of the construction work.”
Source: Arista’s extension records on MahaRERA (P51800003375), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Arista
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 43 complaints, and how it ended
- Construction pace against the March 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800003375
- Status
- Registered and active
- Builder
- Jitendra Shankerlal Brahmbhatt
- Location
- Goregaon West, Mumbai · 400104
- Project type
- Residential / Group Housing
- Registered on
- 5 Aug 2017
- Completion date at registration
- December 2022
- Latest completion date
- March 2028
- Delay so far
- 63 months
- Homes
- 327
- Sold or booked
- 77%
- Towers
- 3
- Complaints on MahaRERA
- 43
- Court cases listed
- 0
- Appeals at the tribunal
- 14
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Arista, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A | 100% | 100% | 100% | 100% |
| Wing B | 100% | 100% | 100% | 100% |
| Wing C | 100% | 72.54% | 38% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Wing A: covers 17 floors
- Wing B: covers 17 floors
- Wing C: covers 29 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Arista every month.
Arista: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 695 – 980 | 185 |
| 3 BHK | 699 – 1,128 | 142 |
- Buildings: Wing A (27 floors, 66 units) · Wing B (27 floors, 66 units) · Wing C (56 floors, 195 units)
- Car parking: 461 covered
- Land: 8,659 sq m (about 2.1 acres) · sanctioned built-up 31,448 sq m · recreational space 3,953 sq m
- Boundaries filed include: Prabhodhankar Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Jitendra Shankerlal Brahmbhatt has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 40 months); 1 still being built, 1 past the promised date (typically 34 months late). 53 complaints on MahaRERA across 3 projects.
Read Google reviews of Arista →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Arista: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Arista
What is the possession date of Arista?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Arista in Goregaon West, Mumbai is 31 March 2028 — 63 months later than 30 December 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Arista?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Arista's builder has filed on MahaRERA, the official one, is 31 March 2028, already 63 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Arista extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Arista's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "The main reason for stalling of project was the health of the promoter. He has faced multiple operations and therapy before resuming in office. The allottees of the ongoing project putting forward their various demands in terms of the possession of the Flat."; to 31 March 2028, giving the reason "C wing construction upto 29th floor is started as per the revised CC approved on 25th July 2024. The total provision of C wing is 42 floors & it's construction will finish as per approval received from Mhada. due to this we applied extension till 31/03/2028. In the mean time the Proprietor of the firm is demised due to sever illness of last 3 years that is reason of delayed of the construction work.".
What is the RERA number of Arista?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Arista in Goregaon West, Mumbai is P51800003375.
Is Arista registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Arista is registered as P51800003375 and its status is "Registered and active".
What is the construction status of Arista?
According to GharKundli's check of MahaRERA records (updated October 2026), Arista's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 72.54% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Arista have complaints on MahaRERA?
43 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Arista safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Arista is registered on MahaRERA as P51800003375, its completion date has moved 63 months since registration and 43 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Arista's possession date changes?
The latest dates are on Arista's MahaRERA page (P51800003375). GharKundli's Kundli Watch sends a free WhatsApp update on Arista every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Arista have?
According to GharKundli's check of MahaRERA records (updated October 2026), Arista has 3 buildings filed: Wing A with 27 floors and 66 units; Wing B with 27 floors and 66 units; Wing C with 56 floors and 195 units.
What are the flat sizes (carpet area) in Arista?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Arista: 2 BHK: 695 to 980 sq ft carpet (185 homes); 3 BHK: 699 to 1128 sq ft carpet (142 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Arista have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 461 covered car parking spaces for Arista.
How big is the land of Arista?
According to GharKundli's check of MahaRERA records (updated October 2026), Arista stands on 8,659 sq m of land (about 2.1 acres), with 31,448 sq m of sanctioned built-up area and 3,953 sq m of recreational open space.
What is the track record of Arista's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Jitendra Shankerlal Brahmbhatt has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 40 months); 1 still being built, 1 past the promised date (typically 34 months late). 53 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Arista?
Google Maps has reviews of Arista written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 43 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Arista?
Arista by Jitendra Shankerlal Brahmbhatt is in Goregaon West, Mumbai (pincode 400104), near Kalanagar, Oshiwara, Goregaon East, Maharashtra, and is registered on MahaRERA as P51800003375, per GharKundli's check of MahaRERA records. Its boundaries filed there include Prabhodhankar Road.
How many homes are in Arista?
According to GharKundli's check of MahaRERA records (updated October 2026), Arista has 327 homes in 3 towers registered on MahaRERA, and 77% of them are sold or booked.
When was Arista registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Arista was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Arista?
No court cases are listed for Arista on MahaRERA, and 14 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Arista?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Jitendra Shankerlal Brahmbhatt, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Arista
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400104
- EKTA TRIPOLIS PHASE II
- Sunteck Pinnacle 1
- Paras Residency
- DRM Sheetal Landmark
- io Residences by PCPL
- io Tower by PCPL
- Apricus
- Bali Ananda
Other projects by Jitendra Shankerlal Brahmbhatt
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.