New Jagdamba
by SiroyaFM Constructions Pvt Ltd · Andheri E, MumbaiAlso near Andheri West, Chakala, Fort
Possession date of New Jagdamba: 30 November 2026, moved from 31 December 2019 (83 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800008985, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about New Jagdamba?
How the possession date of New Jagdamba has moved
31 December 2019
Completion date given when the project was registered
31 December 2020
Extended at the builder's request (MahaRERA application EXT51800005235)
Reason the builder gave MahaRERA:
“The project has been delayed due to multiple reasons as enumerated as below: i) Financial Difficulty due to bad market conditions ii)Non availability of Directors due to Judicial Reasons iii)Change in DCR Policy wherein we have been advised…” Read the full reason
“The project has been delayed due to multiple reasons as enumerated as below: i) Financial Difficulty due to bad market conditions ii)Non availability of Directors due to Judicial Reasons iii)Change in DCR Policy wherein we have been advised to make modifications in planning as per the new DCR 2034”31 December 2021
Extended at the builder's request (MahaRERA application EXT51800009593)
Reason the builder gave MahaRERA:
“Due to the ongoing Covid Pandemic, it has been extremely difficult for us to coordinate various activities in terms of getting permissions from BMC, in organizing labour for the site, in getting materials such as oxygen cylinders required f…” Read the full reason
“Due to the ongoing Covid Pandemic, it has been extremely difficult for us to coordinate various activities in terms of getting permissions from BMC, in organizing labour for the site, in getting materials such as oxygen cylinders required for fabrication purposes, in getting loans from banks,etc. Hence, we require revised timelines of 6 months to complete the project.”30 November 2026
Extended at the builder's request (MahaRERA application EA20082622265)
Reason the builder gave MahaRERA: “POST FACTO EXTENSION”
Source: New Jagdamba’s extension records on MahaRERA (P51800008985), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on New Jagdamba
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800008985
- Status
- Registered and active
- Builder
- SiroyaFM Constructions Pvt Ltd
- Location
- Andheri E, Mumbai · 400093
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- November 2026
- Delay so far
- 83 months
- Homes
- 43
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of New Jagdamba, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| New Jagdamba | 95% | 95% | 40% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- New Jagdamba: covers GROUND + 11 UPPER FLOOR
Want to know when this changes? Kundli Watch sends a free WhatsApp update on New Jagdamba every month.
New Jagdamba: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 591 – 699 | 42 |
| 3 BHK | 943 | 1 |
- Buildings: New Jagdamba (13 floors, 43 units)
- Car parking: 32 covered, 2 open
- Land: 1,080 sq m (about 0.3 acres) · sanctioned built-up 2,247 sq m · recreational space 158 sq m
- Boundaries filed include: Dr Charat Singh Colony Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Siroyafm Constructions (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 still being built, 1 past the promised date (typically 82 months late); 2 lapsed. 4 complaints on MahaRERA across 2 projects.
Read Google reviews of New Jagdamba →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
New Jagdamba: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about New Jagdamba
What is the possession date of New Jagdamba?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for New Jagdamba in Andheri E, Mumbai is 30 November 2026 — 83 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for New Jagdamba?
Builders and listing sites often quote an earlier "target" date for handover. The completion date New Jagdamba's builder has filed on MahaRERA, the official one, is 30 November 2026, already 83 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of New Jagdamba extended?
According to GharKundli's check of MahaRERA records (updated October 2026), New Jagdamba's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2020, giving the reason "The project has been delayed due to multiple reasons as enumerated as below: i) Financial Difficulty due to bad market conditions ii)Non availability of Directors due to Judicial Reasons iii)Change in DCR Policy wherein we have been advised to make modifications in planning as per the new DCR 2034"; to 31 December 2021, giving the reason "Due to the ongoing Covid Pandemic, it has been extremely difficult for us to coordinate various activities in terms of getting permissions from BMC, in organizing labour for the site, in getting materials such as oxygen cylinders required for fabrication purposes, in getting loans from banks,etc. Hence, we require revised timelines of 6 months to complete the project."; to 30 November 2026, giving the reason "POST FACTO EXTENSION".
What is the RERA number of New Jagdamba?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of New Jagdamba in Andheri E, Mumbai is P51800008985.
Is New Jagdamba registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), New Jagdamba is registered as P51800008985 and its status is "Registered and active".
What is the construction status of New Jagdamba?
According to GharKundli's check of MahaRERA records (updated October 2026), New Jagdamba's status on MahaRERA is "Registered and active". As filed by the builder, slab work on New Jagdamba is 95% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.
Does New Jagdamba have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is New Jagdamba safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), New Jagdamba is registered on MahaRERA as P51800008985, its completion date has moved 83 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if New Jagdamba's possession date changes?
The latest dates are on New Jagdamba's MahaRERA page (P51800008985). GharKundli's Kundli Watch sends a free WhatsApp update on New Jagdamba every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does New Jagdamba have?
According to GharKundli's check of MahaRERA records (updated October 2026), New Jagdamba has one building filed: New Jagdamba with 13 floors and 43 units.
What are the flat sizes (carpet area) in New Jagdamba?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for New Jagdamba: 2 BHK: 591 to 699 sq ft carpet (42 homes); 3 BHK: 943 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does New Jagdamba have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 32 covered and 2 open car parking spaces for New Jagdamba.
How big is the land of New Jagdamba?
According to GharKundli's check of MahaRERA records (updated October 2026), New Jagdamba stands on 1,080 sq m of land (about 0.3 acres), with 2,247 sq m of sanctioned built-up area and 158 sq m of recreational open space.
What is the track record of New Jagdamba's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Siroyafm Constructions (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 still being built, 1 past the promised date (typically 82 months late); 2 lapsed. 4 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of New Jagdamba?
Google Maps has reviews of New Jagdamba written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is New Jagdamba?
New Jagdamba by SiroyaFM Constructions Pvt Ltd is in Andheri E, Mumbai (pincode 400093), near Andheri West, Chakala, Fort, Maharashtra, and is registered on MahaRERA as P51800008985, per GharKundli's check of MahaRERA records. Its boundaries filed there include Dr Charat Singh Colony Road.
How many homes are in New Jagdamba?
According to GharKundli's check of MahaRERA records (updated October 2026), New Jagdamba has 43 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was New Jagdamba registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), New Jagdamba was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on New Jagdamba?
No court cases are listed for New Jagdamba on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of New Jagdamba?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SiroyaFM Constructions Pvt Ltd, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of New Jagdamba
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Andheri
- SHRADDHA WEST RESIDENCY
- Green Bay
- SHIVSAI SRA CHS
- Live Well Chs Ltd
- VENUS CHS
- KK 415 WEST
- FIONA GARDEN
- DLH One
Other projects by SiroyaFM Constructions Pvt Ltd
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.