Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.

by MHADA (Nagpur board) · Tiger saoji, NagpurAlso near Parsodi, Jaitala

Possession date of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.: 31 December 2026, moved from 14 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500053887, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. has moved

  1. 14 December 2024

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA06102518046)

    Reason the builder gave MahaRERA:
    “सदर योजनेचे काम जवळपास पूर्ण झालेले असून या योजनेची विकास कामे करण्यासाठी व अंतिम भोगवटा प्रमाणपत्र प्राप्त करण्यासाठी या योजनेस मुदतवाढ हवी असून सदर योजनेस दिनांक ३१/१२/२०२६ पर्यंत मुदतवाढ देण्यात यावी. सदर Resolution / Consent tab मध्ये म…” Read the full reason“सदर योजनेचे काम जवळपास पूर्ण झालेले असून या योजनेची विकास कामे करण्यासाठी व अंतिम भोगवटा प्रमाणपत्र प्राप्त करण्यासाठी या योजनेस मुदतवाढ हवी असून सदर योजनेस दिनांक ३१/१२/२०२६ पर्यंत मुदतवाढ देण्यात यावी. सदर Resolution / Consent tab मध्ये माहिती चेंज होत नाही तो tab Fix असल्यामुळे माहिती त्या tab मध्ये चेंज करता येत नाही त्यामुळे सदरील format – B मध्ये दिलेली माहिती गृहीत धरण्यात यावी. सदरील योजनेस लवकरात लवकर मुदतवाढ देण्यात यावी.”

Source: Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.’s extension records on MahaRERA (P50500053887), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500053887
Status
Registered and active
Builder
MHADA (Nagpur board)
Location
Tiger saoji, Nagpur · 440022
Project type
Residential / Group Housing
Registered on
8 Dec 2023
Completion date at registration
December 2024
Latest completion date
December 2026
Delay so far
24 months
Homes
2
Sold or booked
0%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
9

Construction progress of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur., as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Block A25%0%0%0%
Block B25%0%0%0%
Block C25%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. every month.

Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.

What is the possession date of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. in Tiger saoji, Nagpur is 31 December 2026 — 24 months later than 14 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.'s builder has filed on MahaRERA, the official one, is 31 December 2026, already 24 months later than the 14 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.'s builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "सदर योजनेचे काम जवळपास पूर्ण झालेले असून या योजनेची विकास कामे करण्यासाठी व अंतिम भोगवटा प्रमाणपत्र प्राप्त करण्यासाठी या योजनेस मुदतवाढ हवी असून सदर योजनेस दिनांक ३१/१२/२०२६ पर्यंत मुदतवाढ देण्यात यावी. सदर Resolution / Consent tab मध्ये माहिती चेंज होत नाही तो tab Fix असल्यामुळे माहिती त्या tab मध्ये चेंज करता येत नाही त्यामुळे सदरील format – B मध्ये दिलेली माहिती गृहीत धरण्यात यावी. सदरील योजनेस लवकरात लवकर मुदतवाढ देण्यात यावी.".

What is the RERA number of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. in Tiger saoji, Nagpur is P50500053887.

Is Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. is registered as P50500053887 and its status is "Registered and active".

What is the construction status of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.?

According to GharKundli's check of MahaRERA records (updated October 2026), Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.'s status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. is registered on MahaRERA as P50500053887, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.'s possession date changes?

The latest dates are on Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.'s MahaRERA page (P50500053887). GharKundli's Kundli Watch sends a free WhatsApp update on Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. have?

According to GharKundli's check of MahaRERA records (updated October 2026), Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. has 3 buildings filed: Block A with 3 floors; Block B with 3 floors; Block C with 3 floors.

How big is the land of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.?

According to GharKundli's check of MahaRERA records (updated October 2026), Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. stands on 2,828 sq m of land (about 0.7 acres), with 1,687 sq m of sanctioned built-up area.

Where can I read reviews of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.?

Google Maps has reviews of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.?

Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. by MHADA (Nagpur board) is in Tiger saoji, Nagpur (pincode 440022), near Parsodi, Jaitala, Maharashtra, and is registered on MahaRERA as P50500053887, per GharKundli's check of MahaRERA records.

How many homes are in Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.?

According to GharKundli's check of MahaRERA records (updated October 2026), Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. has 2 homes in 3 towers registered on MahaRERA, and 0% of them are sold or booked.

When was Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. was registered on MahaRERA on 8 December 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.?

No court cases are listed for Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur. on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MHADA (Nagpur board), which has 9 other projects registered on MahaRERA.

All projects with possession due in 2026 in Nagpur →

Other projects in Nagpur (Rural)

All 55 projects in Ranapratap Nagar (440022) →

Other projects by MHADA (Nagpur board)

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.