Possession date of NAKSHATRA APARTMENT: 31 July 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50500053384, and currently active. Its completion date is now July 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about NAKSHATRA APARTMENT?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NAKSHATRA APARTMENT has moved

  1. 31 March 2028

    Completion date given when the project was registered

  2. 31 July 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: NAKSHATRA APARTMENT’s extension records on MahaRERA (P50500053384), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NAKSHATRA APARTMENT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the July 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50500053384
Status
Registered and active
Builder
MAHARSHEE BUILDERS
Location
Beltarodi, Nagpur · 440034
Project type
Residential / Group Housing
Registered on
27 Oct 2023
Completion date at registration
March 2028
Latest completion date
July 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
128
Sold or booked
49%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of NAKSHATRA APARTMENT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NAKSHATRA APARTMENT100%70%80%0%

Commencement certificate (CC), as filed on MahaRERA

  • NAKSHATRA APARTMENT: covers 13 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NAKSHATRA APARTMENT every month.

NAKSHATRA APARTMENT: buildings, flats and land, as filed on MahaRERA

  • Buildings: NAKSHATRA APARTMENT (13 floors, 128 units)
  • Land: 4,000 sq m (about 1.0 acres) · sanctioned built-up 12,628 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of NAKSHATRA APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NAKSHATRA APARTMENT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NAKSHATRA APARTMENT

What is the possession date of NAKSHATRA APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NAKSHATRA APARTMENT in Beltarodi, Nagpur is 31 July 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for NAKSHATRA APARTMENT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NAKSHATRA APARTMENT's builder has filed on MahaRERA, the official one, is 31 July 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of NAKSHATRA APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NAKSHATRA APARTMENT in Beltarodi, Nagpur is P50500053384.

Is NAKSHATRA APARTMENT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA APARTMENT is registered as P50500053384 and its status is "Registered and active".

What is the construction status of NAKSHATRA APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA APARTMENT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NAKSHATRA APARTMENT is 70% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does NAKSHATRA APARTMENT have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is NAKSHATRA APARTMENT safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA APARTMENT is registered on MahaRERA as P50500053384, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NAKSHATRA APARTMENT's possession date changes?

The latest dates are on NAKSHATRA APARTMENT's MahaRERA page (P50500053384). GharKundli's Kundli Watch sends a free WhatsApp update on NAKSHATRA APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NAKSHATRA APARTMENT have?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA APARTMENT has one building filed: NAKSHATRA APARTMENT with 13 floors and 128 units.

How big is the land of NAKSHATRA APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA APARTMENT stands on 4,000 sq m of land (about 1.0 acres), with 12,628 sq m of sanctioned built-up area.

Where can I read reviews of NAKSHATRA APARTMENT?

Google Maps has reviews of NAKSHATRA APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NAKSHATRA APARTMENT?

NAKSHATRA APARTMENT by MAHARSHEE BUILDERS is in Beltarodi, Nagpur (pincode 440034), near Patwardhan Ground, Mahatma Fule Bazar, Ranapratap Nagar, Maharashtra, and is registered on MahaRERA as P50500053384, per GharKundli's check of MahaRERA records.

How many homes are in NAKSHATRA APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA APARTMENT has 128 homes in 1 tower registered on MahaRERA, and 49% of them are sold or booked.

When was NAKSHATRA APARTMENT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NAKSHATRA APARTMENT was registered on MahaRERA on 27 October 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on NAKSHATRA APARTMENT?

No court cases are listed for NAKSHATRA APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of NAKSHATRA APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAHARSHEE BUILDERS, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2028 in Nagpur →

Other projects in Beltarodi

All 104 projects in Mhalginagar (440034) →

Other projects by MAHARSHEE BUILDERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.