Ambika Darshan
by THE KANDIVALI METAL WORKS · Near Swami Narayan Mandir, Mumbai 400101Also near Kandivali West, Kandivali East, Malad West
What’s in the report? →Possession date of Ambika Darshan (MahaRERA P51800006350): 31 December 2025, moved from 30 June 2021 (54 months later), and it has already passed. It has 76 homes (1 BHK and 2 BHK, 215–915 sq ft carpet), 100% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800006350. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800006350, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Ambika Darshan?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Ambika Darshan has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT51800009634)
Reason the builder gave MahaRERA:
“Due to ongoing Covid — 19 Pandemic the work on site has slowed down. We also intent to club this project with another project but to these present pandemic things have stalled and we are not able to move things ahead in respect to the clubb…” Read the full reason
“Due to ongoing Covid — 19 Pandemic the work on site has slowed down. We also intent to club this project with another project but to these present pandemic things have stalled and we are not able to move things ahead in respect to the clubbing of scheme and due to which the project was not able to get completed in time. We would like to request you to further grant us extension for 12 months.”31 December 2024
Extended at the builder's request (MahaRERA application EXT51800013690)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2024”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800025727)
Reason the builder gave MahaRERA:
“We are writing regarding Ambika Darshan's project registration number P51800006350. This project is being developed under Regulation 33(14)(D) in conjunction with Regulation 14(F) of DCR 1991. As part of this project, we must hand over 0.75…” Read the full reason
“We are writing regarding Ambika Darshan's project registration number P51800006350. This project is being developed under Regulation 33(14)(D) in conjunction with Regulation 14(F) of DCR 1991. As part of this project, we must hand over 0.75 FSI of the plot to MCGM/SRA in the form of housing units known as PTC units. In return, we will receive an equivalent FSI for sale. We would like to clarify that, according to the regulations outlined in DCR 1991, we must provide the PTC units on a different plot (let's refer to it as Plot B). The handover of the PTC units on Plot B must occur before we…”
Source: Ambika Darshan’s extension records on MahaRERA (P51800006350), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ambika Darshan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800006350
- Status
- Lapsed (registration period ended)
- Builder
- THE KANDIVALI METAL WORKS
- Location
- Near Swami Narayan Mandir, Mumbai · 400101
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- December 2025
- Delay so far
- 54 months
- Homes
- 76
- Sold or booked
- 100%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Ambika Darshan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING C | 100% | 100% | 99% | 0% |
| WING D | 100% | 100% | 88% | 0% |
| WING E | 100% | 100% | 99% | 97% |
Commencement certificate (CC), as filed on MahaRERA
- WING C: covers PLINTH LEVEL
- WING D: covers PLINTH LEVEL
- WING E: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ambika Darshan every 1–2 months.
Ambika Darshan: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 432 – 915 | 39 |
| 1 BHK | 215 – 915 | 36 |
| Shops | 90 – 2,717 | 15 |
| Office Space | 174 – 1,324 | 6 |
| Other | 911 | 1 |
- Buildings: WING C (9 floors, 39 units) · WING D (9 floors, 5 units) · WING E (21 floors, 53 units)
- Land: 4,778 sq m (about 1.2 acres) · sanctioned built-up 5,002 sq m · recreational space 360 sq m
- Land, as filed: 17A 17B 89
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Ambika Darshan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ambika Darshan: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Ambika Darshan
What is the possession date of Ambika Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ambika Darshan in Near Swami Narayan Mandir, Mumbai is 31 December 2025 — 54 months later than 30 June 2021, the date given at registration. That date has already passed.
The date has already moved 54 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Ambika Darshan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ambika Darshan's builder has filed on MahaRERA, the official one, is 31 December 2025, already 54 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Ambika Darshan extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Ambika Darshan's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "Due to ongoing Covid — 19 Pandemic the work on site has slowed down. We also intent to club this project with another project but to these present pandemic things have stalled and we are not able to move things ahead in respect to the clubbing of scheme and due to which the project was not able to get completed in time. We would like to request you to further grant us extension for 12 months."; to 31 December 2024, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2024"; to 31 December 2025, giving the reason "We are writing regarding Ambika Darshan's project registration number P51800006350. This project is being developed under Regulation 33(14)(D) in conjunction with Regulation 14(F) of DCR 1991. As part of this project, we must hand over 0.75 FSI of the plot to MCGM/SRA in the form of housing units known as PTC units. In return, we will receive an equivalent FSI for sale. We would like to clarify that, according to the regulations outlined in DCR 1991, we must provide the PTC units on a different plot (let's refer to it as Plot B). The handover of the PTC units on Plot B must occur before we…".
What is the RERA number of Ambika Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ambika Darshan in Near Swami Narayan Mandir, Mumbai is P51800006350.
Is Ambika Darshan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ambika Darshan is registered as P51800006350 and its status is "Lapsed (registration period ended)".
What is the current construction status of Ambika Darshan? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Ambika Darshan's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Ambika Darshan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Ambika Darshan safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Ambika Darshan is registered on MahaRERA as P51800006350, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Ambika Darshan?
Ambika Darshan isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Ambika Darshan are 215 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Ambika Darshan?
For a flat in Ambika Darshan (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Ambika Darshan received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ambika Darshan isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Ambika Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), Ambika Darshan's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Ambika Darshan uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ambika Darshan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Ambika Darshan's possession date changes?
The latest dates are on Ambika Darshan's MahaRERA page (P51800006350). GharKundli's Kundli Watch sends a free WhatsApp update on Ambika Darshan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ambika Darshan have?
According to GharKundli's check of MahaRERA records (updated October 2026), Ambika Darshan has 3 buildings filed: WING C with 9 floors and 39 units; WING D with 9 floors and 5 units; WING E with 21 floors and 53 units.
What are the flat sizes (carpet area) in Ambika Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ambika Darshan: 2 BHK: 432 to 915 sq ft carpet (39 homes); 1 BHK: 215 to 915 sq ft carpet (36 homes); Other: 911 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Ambika Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), Ambika Darshan stands on 4,778 sq m of land (about 1.2 acres), with 5,002 sq m of sanctioned built-up area and 360 sq m of recreational open space.
What are the reviews of Ambika Darshan?
Google Maps has reviews of Ambika Darshan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Ambika Darshan?
Ambika Darshan by THE KANDIVALI METAL WORKS is in Near Swami Narayan Mandir, Mumbai, pincode 400101 (near Kandivali West, Kandivali East, Malad West), Maharashtra, and is registered on MahaRERA as P51800006350, per GharKundli's check of MahaRERA records. Its land is filed as 17A 17B 89. GharKundli lists all 113 MahaRERA projects in Kandivali East (400101).
How many flats are in Ambika Darshan, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Ambika Darshan has 76 homes in 3 towers registered on MahaRERA, and 100% of them are sold or booked.
When was Ambika Darshan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ambika Darshan was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Does Ambika Darshan have any legal issues or court cases?
No court cases are listed for Ambika Darshan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Ambika Darshan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is THE KANDIVALI METAL WORKS.
Check it yourself on MahaRERA
- How to check the possession date of Ambika Darshan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Borivali
- Saffronwoods CHSL
- L&T Realty Ahana Tower A
- Avirahi Elegance
- L&T Realty Ahana Tower B
- Parshuram Heights
- Maru Mansion
- LA SERENA Tower 5, Tower 6 and Tower 7
- Shraddha Skyline
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.