JAIS INDUSTRIAL PARKK

by SUBHASHCHANDRA DAYARAM JAIS · Mouza Powari (Rithi), NagpurAlso near Mhalginagar, Ayodhya Nagar

Possession date of JAIS INDUSTRIAL PARKK: 31 July 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under PP1190002501989, and currently active. Its completion date is now July 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about JAIS INDUSTRIAL PARKK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of JAIS INDUSTRIAL PARKK has moved

  1. 31 March 2028

    Completion date given when the project was registered

  2. 31 July 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: JAIS INDUSTRIAL PARKK’s extension records on MahaRERA (PP1190002501989), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on JAIS INDUSTRIAL PARKK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PP1190002501989
Status
Registered and active
Builder
SUBHASHCHANDRA DAYARAM JAIS
Location
Mouza Powari (Rithi), Nagpur · 440009
Project type
Plotted
Registered on
6 Jan 2026
Completion date at registration
March 2028
Latest completion date
July 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of JAIS INDUSTRIAL PARKK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Commencement certificate (CC), as filed on MahaRERA

Latest CC order on MahaRERA: dated 06/11/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on JAIS INDUSTRIAL PARKK every month.

JAIS INDUSTRIAL PARKK: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of JAIS INDUSTRIAL PARKK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

JAIS INDUSTRIAL PARKK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about JAIS INDUSTRIAL PARKK

What is the possession date of JAIS INDUSTRIAL PARKK?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for JAIS INDUSTRIAL PARKK in Mouza Powari (Rithi), Nagpur is 31 July 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for JAIS INDUSTRIAL PARKK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date JAIS INDUSTRIAL PARKK's builder has filed on MahaRERA, the official one, is 31 July 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of JAIS INDUSTRIAL PARKK?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of JAIS INDUSTRIAL PARKK in Mouza Powari (Rithi), Nagpur is PP1190002501989.

Is JAIS INDUSTRIAL PARKK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), JAIS INDUSTRIAL PARKK is registered as PP1190002501989 and its status is "Registered and active".

What is the construction status of JAIS INDUSTRIAL PARKK?

According to GharKundli's check of MahaRERA records (updated October 2026), JAIS INDUSTRIAL PARKK's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.

Does JAIS INDUSTRIAL PARKK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is JAIS INDUSTRIAL PARKK safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), JAIS INDUSTRIAL PARKK is registered on MahaRERA as PP1190002501989, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if JAIS INDUSTRIAL PARKK's possession date changes?

The latest dates are on JAIS INDUSTRIAL PARKK's MahaRERA page (PP1190002501989). GharKundli's Kundli Watch sends a free WhatsApp update on JAIS INDUSTRIAL PARKK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of JAIS INDUSTRIAL PARKK?

According to GharKundli's check of MahaRERA records (updated October 2026), JAIS INDUSTRIAL PARKK stands on 13,800 sq m of land (about 3.4 acres) and 1,381 sq m of recreational open space.

Where can I read reviews of JAIS INDUSTRIAL PARKK?

Google Maps has reviews of JAIS INDUSTRIAL PARKK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is JAIS INDUSTRIAL PARKK?

JAIS INDUSTRIAL PARKK by SUBHASHCHANDRA DAYARAM JAIS is in Mouza Powari (Rithi), Nagpur (pincode 440009), near Mhalginagar, Ayodhya Nagar, Maharashtra, and is registered on MahaRERA as PP1190002501989, per GharKundli's check of MahaRERA records.

When was JAIS INDUSTRIAL PARKK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), JAIS INDUSTRIAL PARKK was registered on MahaRERA on 6 January 2026. GharKundli did not find a title report on the land on file there.

Are there court cases on JAIS INDUSTRIAL PARKK?

No court cases are listed for JAIS INDUSTRIAL PARKK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of JAIS INDUSTRIAL PARKK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUBHASHCHANDRA DAYARAM JAIS.

Other projects in Kamptee

All Nagpur projects with no pincode on MahaRERA →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.