by CLASSIC ENTERPRISES VAKOLA · Vakola, MumbaiAlso near Santacruz East, Andheri, Kalina

Possession date of EKTA SRA CHS: 28 June 2026, moved from 1 August 2023 (30 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800004680. Status: Lapsed (registration period ended). Its completion date has moved from August 2023 to June 2026: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (June 2026) has passed.

What do you want to know about EKTA SRA CHS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of EKTA SRA CHS has moved

  1. 1 August 2023

    Completion date given when the project was registered

  2. 1 July 2024

    Extended at the builder's request (MahaRERA application EXT51800017236)

    Reason the builder gave MahaRERA:
    “COURT CASE IN HIGH COURT MUMBAI regarding ownership of the property and existing commercial tenants (shops) in road setback are not ready to shift in the permanent rehab commercial premises (SHOPS) after obtaining part occupation of the Gro…” Read the full reason“COURT CASE IN HIGH COURT MUMBAI regarding ownership of the property and existing commercial tenants (shops) in road setback are not ready to shift in the permanent rehab commercial premises (SHOPS) after obtaining part occupation of the Ground Floor of the building.”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800024646)

    Reason the builder gave MahaRERA:
    “1) Writ petition No. 10551 of 2018 verses Shri Dattaram Mahadev Mahadik (Petitioner) and Slum Rehabilitation Authority (Respondent) petitioner was instructed to withdraw the petition and file and appeal before AGR on 21st September 2018. 2)…” Read the full reason“1) Writ petition No. 10551 of 2018 verses Shri Dattaram Mahadev Mahadik (Petitioner) and Slum Rehabilitation Authority (Respondent) petitioner was instructed to withdraw the petition and file and appeal before AGR on 21st September 2018. 2) Before the Apex Grievance Redressal Committee Government of Maharashtra Application (L) No. 205 of 2018 and Application (L) No. 206 of 2018 Applicant. 3) Order of Dy. Collector SRA vide No. OW/2019/11427 जा. क्र. झोपुप्रा / अजि / मुद्रा / कार्या - 09/2019 dated 6th March 2018 4) Lock down period 1 year work effected 5) Now extension for project is being…”
  4. 28 February 2026

    Extended at the builder's request (MahaRERA application EA17092502618)

    Reason the builder gave MahaRERA:
    “1) Writ petition No. 10551 of 2018 verses Shri Dattaram Mahadev Mahadik (Petitioner) and Slum Rehabilitation Authority (Respondent) petitioner was instructed to withdraw the petition and file and appeal before AGR on 21st September 2018. 2)…” Read the full reason“1) Writ petition No. 10551 of 2018 verses Shri Dattaram Mahadev Mahadik (Petitioner) and Slum Rehabilitation Authority (Respondent) petitioner was instructed to withdraw the petition and file and appeal before AGR on 21st September 2018. 2) Before the Apex Grievance Redressal Committee Government of Maharashtra Application (L) No. 205 of 2018 and Application (L) No. 206 of 2018 Applicant. 3) Order of Dy. Collector SRA vide No. OW/2019/11427 जा. क्र. झोपुप्रा / अजि / मुद्रा / कार्या - 09/2019 dated 6th March 2018 4) Lock down period 1 year work effected 5) Now extension for project is being…”
  5. 28 June 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: EKTA SRA CHS’s extension records on MahaRERA (P51800004680), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on EKTA SRA CHS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 court cases, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800004680
Status
Lapsed (registration period ended)
Builder
CLASSIC ENTERPRISES VAKOLA
Location
Vakola, Mumbai · 400055
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
August 2023
Latest completion date
June 2026
Delay so far
30 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
61
Sold or booked
85%
Towers
1
Complaints on MahaRERA
0
Court cases listed
4
Title report on file
Not found

Construction progress of EKTA SRA CHS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
EKTA CHS100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • EKTA CHS: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on EKTA SRA CHS every month.

EKTA SRA CHS: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK269 – 46853
Shops27 – 2248
2 BHK520 – 5376
Other216 – 2253
  • Buildings: EKTA CHS (9 floors, 70 units)
  • Car parking: 11 covered
  • Land: 605 sq m (about 0.1 acres) · sanctioned built-up 1,770 sq m
  • Boundaries filed include: ROAD MAINTAINED BY WARD, YASHWANT NAGAR ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of EKTA SRA CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

EKTA SRA CHS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about EKTA SRA CHS

What is the possession date of EKTA SRA CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for EKTA SRA CHS in Vakola, Mumbai is 28 June 2026 — 30 months later than 1 August 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for EKTA SRA CHS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date EKTA SRA CHS's builder has filed on MahaRERA, the official one, is 28 June 2026, already 30 months later than the 1 August 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of EKTA SRA CHS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA SRA CHS's builder applied to MahaRERA to extend the completion date 3 times: to 1 July 2024, giving the reason "COURT CASE IN HIGH COURT MUMBAI regarding ownership of the property and existing commercial tenants (shops) in road setback are not ready to shift in the permanent rehab commercial premises (SHOPS) after obtaining part occupation of the Ground Floor of the building."; to 30 June 2025, giving the reason "1) Writ petition No. 10551 of 2018 verses Shri Dattaram Mahadev Mahadik (Petitioner) and Slum Rehabilitation Authority (Respondent) petitioner was instructed to withdraw the petition and file and appeal before AGR on 21st September 2018. 2) Before the Apex Grievance Redressal Committee Government of Maharashtra Application (L) No. 205 of 2018 and Application (L) No. 206 of 2018 Applicant. 3) Order of Dy. Collector SRA vide No. OW/2019/11427 जा. क्र. झोपुप्रा / अजि / मुद्रा / कार्या - 09/2019 dated 6th March 2018 4) Lock down period 1 year work effected 5) Now extension for project is being…"; to 28 February 2026, giving the reason "1) Writ petition No. 10551 of 2018 verses Shri Dattaram Mahadev Mahadik (Petitioner) and Slum Rehabilitation Authority (Respondent) petitioner was instructed to withdraw the petition and file and appeal before AGR on 21st September 2018. 2) Before the Apex Grievance Redressal Committee Government of Maharashtra Application (L) No. 205 of 2018 and Application (L) No. 206 of 2018 Applicant. 3) Order of Dy. Collector SRA vide No. OW/2019/11427 जा. क्र. झोपुप्रा / अजि / मुद्रा / कार्या - 09/2019 dated 6th March 2018 4) Lock down period 1 year work effected 5) Now extension for project is being…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of EKTA SRA CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of EKTA SRA CHS in Vakola, Mumbai is P51800004680.

Is EKTA SRA CHS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA SRA CHS is registered as P51800004680 and its status is "Lapsed (registration period ended)".

What is the construction status of EKTA SRA CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA SRA CHS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on EKTA CHS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does EKTA SRA CHS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is EKTA SRA CHS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA SRA CHS is registered on MahaRERA as P51800004680, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if EKTA SRA CHS's possession date changes?

The latest dates are on EKTA SRA CHS's MahaRERA page (P51800004680). GharKundli's Kundli Watch sends a free WhatsApp update on EKTA SRA CHS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does EKTA SRA CHS have?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA SRA CHS has one building filed: EKTA CHS with 9 floors and 70 units.

What are the flat sizes (carpet area) in EKTA SRA CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for EKTA SRA CHS: 1 BHK: 269 to 468 sq ft carpet (53 homes); 2 BHK: 520 to 537 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does EKTA SRA CHS have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 11 covered car parking spaces for EKTA SRA CHS.

How big is the land of EKTA SRA CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA SRA CHS stands on 605 sq m of land (about 0.1 acres), with 1,770 sq m of sanctioned built-up area.

Where can I read reviews of EKTA SRA CHS?

Google Maps has reviews of EKTA SRA CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is EKTA SRA CHS?

EKTA SRA CHS by CLASSIC ENTERPRISES VAKOLA is in Vakola, Mumbai (pincode 400055), near Santacruz East, Andheri, Kalina, Maharashtra, and is registered on MahaRERA as P51800004680, per GharKundli's check of MahaRERA records. Its boundaries filed there include ROAD MAINTAINED BY WARD, YASHWANT NAGAR ROAD.

How many homes are in EKTA SRA CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA SRA CHS has 61 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.

When was EKTA SRA CHS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), EKTA SRA CHS was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on EKTA SRA CHS?

4 court cases are listed for EKTA SRA CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of EKTA SRA CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CLASSIC ENTERPRISES VAKOLA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Andheri

All 112 projects in Santacruz East (400055) →