R M Dhariwal Greens Yavatmal Phase - 3

by Dhariwal And Chhoriya Developers LLP · Yavatmal

Possession date of R M Dhariwal Greens Yavatmal Phase - 3: 31 December 2023, moved from 30 June 2021 (30 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51000015553. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about R M Dhariwal Greens Yavatmal Phase - 3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of R M Dhariwal Greens Yavatmal Phase - 3 has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51000010300)

    Reason the builder gave MahaRERA:
    “Note for State of development work – a) Proposed infrastructure in this proposed Phase-2 like Concrete Road, Drainage, STP, water line, Transformer and street light, Entrance gate, Compound wall, Security cabin, Garden and landscaping, Chil…” Read the full reason“Note for State of development work – a) Proposed infrastructure in this proposed Phase-2 like Concrete Road, Drainage, STP, water line, Transformer and street light, Entrance gate, Compound wall, Security cabin, Garden and landscaping, Children Play Park, Vermiculture Pit, Rainwater harvesting, Solid Waste Management System etc are completed and amenities like Yoga hall, Garden are completed. Only amenities like CCTV surveillance system, EPbex telephone system, Cricket Pitch, Skating Ring, Basket Ball Court are in progress and shall be completed soon. b) Total proposed units of 21 No Smart…”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51000017532)

    Reason the builder gave MahaRERA:
    “We request an extension for our project registered as R.M. Dhariwal Greens yavatmal Phase 2 in MAHARERA. We inadvertently selected the wrong project type as Residential instead of the correct category, which is a Mix category (Building + Pl…” Read the full reason“We request an extension for our project registered as R.M. Dhariwal Greens yavatmal Phase 2 in MAHARERA. We inadvertently selected the wrong project type as Residential instead of the correct category, which is a Mix category (Building + Plotting). We have completed the entire project as per the original timeline and applied for the Occupancy Certificate before 30.12.2022. However, we have not yet received the Occupancy Certificate. To rectify the project type selection and ensure accurate representation, we kindly seek an extension to modify the project type to Mix category. We have attach…”

Source: R M Dhariwal Greens Yavatmal Phase - 3’s extension records on MahaRERA (P51000015553), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on R M Dhariwal Greens Yavatmal Phase - 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51000015553
Status
Lapsed (registration period ended)
Builder
Dhariwal And Chhoriya Developers LLP
Location
Yavatmal · 445001
Project type
Residential / Group Housing
Registered on
8 Mar 2018
Completion date at registration
June 2021
Latest completion date
December 2023
Delay so far
30 months
Homes
21
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
8

Construction progress of R M Dhariwal Greens Yavatmal Phase - 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Smart Row House - 32 to 380%0%0%0%
Smart Row House - 39 to 42 And 87 to 890%0%0%0%
Smart Row House - 60 to 64 , 90 And 910%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on R M Dhariwal Greens Yavatmal Phase - 3 every month.

R M Dhariwal Greens Yavatmal Phase - 3: buildings, flats and land, as filed on MahaRERA

  • Buildings: Smart Row House - 32 to 38 (2 floors) · Smart Row House - 39 to 42 And 87 to 89 (2 floors) · Smart Row House - 60 to 64 , 90 And 91 (2 floors)
  • Land: 2,650 sq m (about 0.7 acres) · sanctioned built-up 1,720 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Dhariwal And Chhoriya Developers has 9 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. No complaints on MahaRERA.

Read Google reviews of R M Dhariwal Greens Yavatmal Phase - 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

R M Dhariwal Greens Yavatmal Phase - 3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about R M Dhariwal Greens Yavatmal Phase - 3

What is the possession date of R M Dhariwal Greens Yavatmal Phase - 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for R M Dhariwal Greens Yavatmal Phase - 3 in Yavatmal is 31 December 2023 — 30 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for R M Dhariwal Greens Yavatmal Phase - 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date R M Dhariwal Greens Yavatmal Phase - 3's builder has filed on MahaRERA, the official one, is 31 December 2023, already 30 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of R M Dhariwal Greens Yavatmal Phase - 3 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), R M Dhariwal Greens Yavatmal Phase - 3's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2022, giving the reason "Note for State of development work – a) Proposed infrastructure in this proposed Phase-2 like Concrete Road, Drainage, STP, water line, Transformer and street light, Entrance gate, Compound wall, Security cabin, Garden and landscaping, Children Play Park, Vermiculture Pit, Rainwater harvesting, Solid Waste Management System etc are completed and amenities like Yoga hall, Garden are completed. Only amenities like CCTV surveillance system, EPbex telephone system, Cricket Pitch, Skating Ring, Basket Ball Court are in progress and shall be completed soon. b) Total proposed units of 21 No Smart…"; to 31 December 2023, giving the reason "We request an extension for our project registered as R.M. Dhariwal Greens yavatmal Phase 2 in MAHARERA. We inadvertently selected the wrong project type as Residential instead of the correct category, which is a Mix category (Building + Plotting). We have completed the entire project as per the original timeline and applied for the Occupancy Certificate before 30.12.2022. However, we have not yet received the Occupancy Certificate. To rectify the project type selection and ensure accurate representation, we kindly seek an extension to modify the project type to Mix category. We have attach…".

What is the RERA number of R M Dhariwal Greens Yavatmal Phase - 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of R M Dhariwal Greens Yavatmal Phase - 3 in Yavatmal is P51000015553.

Is R M Dhariwal Greens Yavatmal Phase - 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), R M Dhariwal Greens Yavatmal Phase - 3 is registered as P51000015553 and its status is "Lapsed (registration period ended)".

What is the construction status of R M Dhariwal Greens Yavatmal Phase - 3?

According to GharKundli's check of MahaRERA records (updated November 2026), R M Dhariwal Greens Yavatmal Phase - 3's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does R M Dhariwal Greens Yavatmal Phase - 3 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is R M Dhariwal Greens Yavatmal Phase - 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), R M Dhariwal Greens Yavatmal Phase - 3 is registered on MahaRERA as P51000015553, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does R M Dhariwal Greens Yavatmal Phase - 3 have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: R M Dhariwal Greens Yavatmal Phase 1 (P51000009219); R M Dhariwal Greens Yavatmal Phase - 2 (P51000012173, possession 31 Dec 2023). Check that your agreement names the registration of your own wing.

How can I get updates if R M Dhariwal Greens Yavatmal Phase - 3's possession date changes?

The latest dates are on R M Dhariwal Greens Yavatmal Phase - 3's MahaRERA page (P51000015553). GharKundli's Kundli Watch sends a free WhatsApp update on R M Dhariwal Greens Yavatmal Phase - 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does R M Dhariwal Greens Yavatmal Phase - 3 have?

According to GharKundli's check of MahaRERA records (updated November 2026), R M Dhariwal Greens Yavatmal Phase - 3 has 3 buildings filed: Smart Row House - 32 to 38 with 2 floors; Smart Row House - 39 to 42 And 87 to 89 with 2 floors; Smart Row House - 60 to 64 , 90 And 91 with 2 floors.

How big is the land of R M Dhariwal Greens Yavatmal Phase - 3?

According to GharKundli's check of MahaRERA records (updated November 2026), R M Dhariwal Greens Yavatmal Phase - 3 stands on 2,650 sq m of land (about 0.7 acres), with 1,720 sq m of sanctioned built-up area.

What is the track record of R M Dhariwal Greens Yavatmal Phase - 3's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Dhariwal And Chhoriya Developers has 9 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of R M Dhariwal Greens Yavatmal Phase - 3?

Google Maps has reviews of R M Dhariwal Greens Yavatmal Phase - 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is R M Dhariwal Greens Yavatmal Phase - 3?

R M Dhariwal Greens Yavatmal Phase - 3 by Dhariwal And Chhoriya Developers LLP is in Yavatmal (pincode 445001), Maharashtra, and is registered on MahaRERA as P51000015553, per GharKundli's check of MahaRERA records.

How many homes are in R M Dhariwal Greens Yavatmal Phase - 3?

According to GharKundli's check of MahaRERA records (updated November 2026), R M Dhariwal Greens Yavatmal Phase - 3 has 21 homes in 3 towers registered on MahaRERA.

When was R M Dhariwal Greens Yavatmal Phase - 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), R M Dhariwal Greens Yavatmal Phase - 3 was registered on MahaRERA on 8 March 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on R M Dhariwal Greens Yavatmal Phase - 3?

No court cases are listed for R M Dhariwal Greens Yavatmal Phase - 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of R M Dhariwal Greens Yavatmal Phase - 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Dhariwal And Chhoriya Developers LLP, which has 8 other projects registered on MahaRERA.

Other projects in Yavatmal

All 12 projects in Yavatmal (445001) →

Other projects by Dhariwal And Chhoriya Developers LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.