NALINI KRISHNA RENAISSANCE

by SHRI KRISHNA PROMOTERS · Yavatmal

Possession: NALINI KRISHNA RENAISSANCE is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51000027090. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about NALINI KRISHNA RENAISSANCE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NALINI KRISHNA RENAISSANCE has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51000011907)

    Reason the builder gave MahaRERA:
    “As per new Development Control Act i.e. UDCPR 2020 made applicable from 2nd Dec 2020 for sanctioning of Buildings, in our case because of UDCPR 2020 our Commercial as well as Residential sanction area was increasing. We applied for revised…” Read the full reason“As per new Development Control Act i.e. UDCPR 2020 made applicable from 2nd Dec 2020 for sanctioning of Buildings, in our case because of UDCPR 2020 our Commercial as well as Residential sanction area was increasing. We applied for revised sanction on 18/03/2021 and on 21/03/2022 we got revised sanction with additional One Floor of Commercial area in Wing D and Two Floors i.e. 8nos of Apartment in Wing A. We need additional time of 1 year to complete the construction of additional area which was sanctioned on 21/03/2022. We have attached Commencement Certificate received with revised sancti…”

Source: NALINI KRISHNA RENAISSANCE’s extension records on MahaRERA (P51000027090), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NALINI KRISHNA RENAISSANCE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51000027090
Status
Completed
Builder
SHRI KRISHNA PROMOTERS
Location
Yavatmal · 445001
Project type
Others
Registered on
13 Nov 2020
Completion date at registration
June 2022
Latest completion date
June 2023
Delay so far
12 months
Homes
42
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of NALINI KRISHNA RENAISSANCE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%65%40%35%
WING B100%100%100%100%
WING C AND D100%100%50%35%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NALINI KRISHNA RENAISSANCE every month.

NALINI KRISHNA RENAISSANCE: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of NALINI KRISHNA RENAISSANCE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NALINI KRISHNA RENAISSANCE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NALINI KRISHNA RENAISSANCE

What is the possession date of NALINI KRISHNA RENAISSANCE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NALINI KRISHNA RENAISSANCE in Yavatmal is 30 June 2023 — 12 months later than 30 June 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for NALINI KRISHNA RENAISSANCE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NALINI KRISHNA RENAISSANCE's builder has filed on MahaRERA, the official one, is 30 June 2023, already 12 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NALINI KRISHNA RENAISSANCE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), NALINI KRISHNA RENAISSANCE's builder applied to MahaRERA to extend the completion date once: to 30 June 2023, giving the reason "As per new Development Control Act i.e. UDCPR 2020 made applicable from 2nd Dec 2020 for sanctioning of Buildings, in our case because of UDCPR 2020 our Commercial as well as Residential sanction area was increasing. We applied for revised sanction on 18/03/2021 and on 21/03/2022 we got revised sanction with additional One Floor of Commercial area in Wing D and Two Floors i.e. 8nos of Apartment in Wing A. We need additional time of 1 year to complete the construction of additional area which was sanctioned on 21/03/2022. We have attached Commencement Certificate received with revised sancti…".

What is the RERA number of NALINI KRISHNA RENAISSANCE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NALINI KRISHNA RENAISSANCE in Yavatmal is P51000027090.

Is NALINI KRISHNA RENAISSANCE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NALINI KRISHNA RENAISSANCE is registered as P51000027090 and its status is "Completed".

What is the construction status of NALINI KRISHNA RENAISSANCE?

According to GharKundli's check of MahaRERA records (updated November 2026), NALINI KRISHNA RENAISSANCE's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 65% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does NALINI KRISHNA RENAISSANCE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is NALINI KRISHNA RENAISSANCE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), NALINI KRISHNA RENAISSANCE is registered on MahaRERA as P51000027090, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NALINI KRISHNA RENAISSANCE's possession date changes?

The latest dates are on NALINI KRISHNA RENAISSANCE's MahaRERA page (P51000027090). GharKundli's Kundli Watch sends a free WhatsApp update on NALINI KRISHNA RENAISSANCE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NALINI KRISHNA RENAISSANCE have?

According to GharKundli's check of MahaRERA records (updated November 2026), NALINI KRISHNA RENAISSANCE has 3 buildings filed: WING A with 5 floors; WING B with 5 floors; WING C AND D with 5 floors.

How big is the land of NALINI KRISHNA RENAISSANCE?

According to GharKundli's check of MahaRERA records (updated November 2026), NALINI KRISHNA RENAISSANCE stands on 2,354 sq m of land (about 0.6 acres), with 2,540 sq m of sanctioned built-up area.

Where can I read reviews of NALINI KRISHNA RENAISSANCE?

Google Maps has reviews of NALINI KRISHNA RENAISSANCE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NALINI KRISHNA RENAISSANCE?

NALINI KRISHNA RENAISSANCE by SHRI KRISHNA PROMOTERS is in Yavatmal (pincode 445001), Maharashtra, and is registered on MahaRERA as P51000027090, per GharKundli's check of MahaRERA records.

How many homes are in NALINI KRISHNA RENAISSANCE?

According to GharKundli's check of MahaRERA records (updated November 2026), NALINI KRISHNA RENAISSANCE has 42 homes in 3 towers registered on MahaRERA.

When was NALINI KRISHNA RENAISSANCE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NALINI KRISHNA RENAISSANCE was registered on MahaRERA on 13 November 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on NALINI KRISHNA RENAISSANCE?

No court cases are listed for NALINI KRISHNA RENAISSANCE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of NALINI KRISHNA RENAISSANCE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHRI KRISHNA PROMOTERS.

Other projects in Yavatmal

All 12 projects in Yavatmal (445001) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.