SHANKARAA SRUSHTI

by VYANKATESH ABK INFRAA · Harsul, Aurangabad

Possession date of SHANKARAA SRUSHTI: 30 December 2026, moved from 30 June 2021 (66 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51500004524, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHANKARAA SRUSHTI?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHANKARAA SRUSHTI has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 October 2023

    Extended at the builder's request (MahaRERA application EXT51500009677)

    Reason the builder gave MahaRERA: “Due to COVID Situation and unavailability of Labour, Material and others issues the project is getting delayed for which purchser given consent for extension till 30/10/2023,”
  3. 30 December 2026

    Extended at the builder's request (MahaRERA application EA20062621464)

    Reason the builder gave MahaRERA:
    “Fluctuations and Escalations in rates of key components like Cement, Steel, Ready Mix Concrete, Skilled Labourers has made rework of Funds Management and thus resulted in revised Budget along with delay in completion activities. The promote…” Read the full reason“Fluctuations and Escalations in rates of key components like Cement, Steel, Ready Mix Concrete, Skilled Labourers has made rework of Funds Management and thus resulted in revised Budget along with delay in completion activities. The promoter already received part completion and also handed over possession of 37 units. All pending QPR also uploaded.... the promoter already applied in old portal but the same has been not updated in new portal... We also have to update all QPR since registration which also done....”

Source: SHANKARAA SRUSHTI’s extension records on MahaRERA (P51500004524), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHANKARAA SRUSHTI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500004524
Status
Registered and active
Builder
VYANKATESH ABK INFRAA
Location
Harsul, Aurangabad · 431001
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
June 2021
Latest completion date
December 2026
Delay so far
66 months
Homes
100
Sold or booked
37%
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SHANKARAA SRUSHTI, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AB100%100%100%100%
CD100%100%100%100%
EF100%100%100%100%
COMMERCIAL BUILDING100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • AB: covers 5 floors
  • CD: covers 5 floors
  • EF: covers 5 floors
  • COMMERCIAL BUILDING: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHANKARAA SRUSHTI every month.

SHANKARAA SRUSHTI: buildings, flats and land, as filed on MahaRERA

  • Buildings: AB (10 floors, 33 units) · CD (10 floors, 34 units) · EF (10 floors, 32 units) · COMMERCIAL BUILDING (4 floors, 11 units)
  • Car parking: 12 covered
  • Land: 3,950 sq m (about 1.0 acres) · sanctioned built-up 4,110 sq m · recreational space 400 sq m
  • Boundaries filed include: HARSOOL PISADEVI ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHANKARAA SRUSHTI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHANKARAA SRUSHTI: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHANKARAA SRUSHTI

What is the possession date of SHANKARAA SRUSHTI?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHANKARAA SRUSHTI in Harsul, Aurangabad is 30 December 2026 — 66 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SHANKARAA SRUSHTI?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHANKARAA SRUSHTI's builder has filed on MahaRERA, the official one, is 30 December 2026, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHANKARAA SRUSHTI extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHANKARAA SRUSHTI's builder applied to MahaRERA to extend the completion date 2 times: to 30 October 2023, giving the reason "Due to COVID Situation and unavailability of Labour, Material and others issues the project is getting delayed for which purchser given consent for extension till 30/10/2023,"; to 30 December 2026, giving the reason "Fluctuations and Escalations in rates of key components like Cement, Steel, Ready Mix Concrete, Skilled Labourers has made rework of Funds Management and thus resulted in revised Budget along with delay in completion activities. The promoter already received part completion and also handed over possession of 37 units. All pending QPR also uploaded.... the promoter already applied in old portal but the same has been not updated in new portal... We also have to update all QPR since registration which also done....".

What is the RERA number of SHANKARAA SRUSHTI?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHANKARAA SRUSHTI in Harsul, Aurangabad is P51500004524.

Is SHANKARAA SRUSHTI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHANKARAA SRUSHTI is registered as P51500004524 and its status is "Registered and active".

What is the construction status of SHANKARAA SRUSHTI?

According to GharKundli's check of MahaRERA records (updated October 2026), SHANKARAA SRUSHTI's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does SHANKARAA SRUSHTI have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SHANKARAA SRUSHTI safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHANKARAA SRUSHTI is registered on MahaRERA as P51500004524, its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHANKARAA SRUSHTI's possession date changes?

The latest dates are on SHANKARAA SRUSHTI's MahaRERA page (P51500004524). GharKundli's Kundli Watch sends a free WhatsApp update on SHANKARAA SRUSHTI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHANKARAA SRUSHTI have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHANKARAA SRUSHTI has 4 buildings filed: AB with 10 floors and 33 units; CD with 10 floors and 34 units; EF with 10 floors and 32 units; COMMERCIAL BUILDING with 4 floors and 11 units.

How much parking does SHANKARAA SRUSHTI have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 covered car parking spaces for SHANKARAA SRUSHTI.

How big is the land of SHANKARAA SRUSHTI?

According to GharKundli's check of MahaRERA records (updated October 2026), SHANKARAA SRUSHTI stands on 3,950 sq m of land (about 1.0 acres), with 4,110 sq m of sanctioned built-up area and 400 sq m of recreational open space.

Where can I read reviews of SHANKARAA SRUSHTI?

Google Maps has reviews of SHANKARAA SRUSHTI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHANKARAA SRUSHTI?

SHANKARAA SRUSHTI by VYANKATESH ABK INFRAA is in Harsul, Aurangabad (pincode 431001), Maharashtra, and is registered on MahaRERA as P51500004524, per GharKundli's check of MahaRERA records. Its boundaries filed there include HARSOOL PISADEVI ROAD.

How many homes are in SHANKARAA SRUSHTI?

According to GharKundli's check of MahaRERA records (updated October 2026), SHANKARAA SRUSHTI has 100 homes in 4 towers registered on MahaRERA, and 37% of them are sold or booked.

When was SHANKARAA SRUSHTI registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHANKARAA SRUSHTI was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHANKARAA SRUSHTI?

No court cases are listed for SHANKARAA SRUSHTI on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SHANKARAA SRUSHTI?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VYANKATESH ABK INFRAA.

All projects with possession due in 2026 in Aurangabad →

Other projects in Aurangabad

All 189 projects in Chhatrapati Sambhajinagar (431001) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.