by A.M.PATEL INFRA PVT LTD · Satara Aurangabad, Aurangabad

Possession date of 180 and 51 Greens: 31 January 2024, moved from 31 July 2023 (6 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51500004770. Status: Lapsed (registration period ended). 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (January 2024) has passed.

What do you want to know about 180 and 51 Greens?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of 180 and 51 Greens has moved

  1. 31 July 2023

    Completion date given when the project was registered

  2. 31 January 2024

    Extended at the builder's request (MahaRERA application EXT51500017218)

    Reason the builder gave MahaRERA:
    “We do Have four towers consisting 46 units in each towers . Out of four towers our three towers are 98% completed. Fourth tower we have completed entire RCC work, drainage line is completed, exterior final paint is in progress. Lift is orde…” Read the full reason“We do Have four towers consisting 46 units in each towers . Out of four towers our three towers are 98% completed. Fourth tower we have completed entire RCC work, drainage line is completed, exterior final paint is in progress. Lift is ordered . within 45 days lift will be installed . 50 percent apartments Glass aluminium work is completed and rest is in progress. All common area like all floors staircase lift lobbies , parking, entrance lobby , parking light is completed. All basic services like water , drainage line, electricity services are operational through out the project. Further we…”

Source: 180 and 51 Greens’s extension records on MahaRERA (P51500004770), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on 180 and 51 Greens

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints, and how it ended
  • Construction pace against the January 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500004770
Status
Lapsed (registration period ended)
Builder
A.M.PATEL INFRA PVT LTD
Location
Satara Aurangabad, Aurangabad · 431005
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
July 2023
Latest completion date
January 2024
Delay so far
6 months
Homes
236
Sold or booked
52%
Towers
8
Complaints on MahaRERA
7
Court cases listed
0
Appeals at the tribunal
2
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of 180 and 51 Greens, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A OF 180 GREENS100%100%100%90%
WING B OF 180 GREENS100%100%100%95%
WING C OF 180 GREENS100%100%100%90%
WING D OF 180 GREENS100%100%100%80%
WING E OF 51 GREENS100%100%100%100%
CLUBHOUSE II0%0%0%0%
CLUBHOUSE I0%0%0%0%
AMENITY BUILDING0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • WING A OF 180 GREENS: covers 14 floors
  • WING B OF 180 GREENS: covers 14 floors
  • WING C OF 180 GREENS: covers 14 floors
  • WING D OF 180 GREENS: covers 14 floors
  • WING E OF 51 GREENS: covers 153 floors
  • CLUBHOUSE II: covers 0 floors
  • CLUBHOUSE I: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 180 and 51 Greens every month.

180 and 51 Greens: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING A OF 180 GREENS (14 floors, 46 units) · WING B OF 180 GREENS (14 floors, 46 units) · WING C OF 180 GREENS (14 floors, 46 units) · WING D OF 180 GREENS (14 floors, 46 units) · WING E OF 51 GREENS (153 floors, 50 units) · CLUBHOUSE II (2 floors, 1 units) · CLUBHOUSE I (2 floors, 1 units) · AMENITY BUILDING (8 floors, 1 units)
  • Car parking: 40 open
  • Land: 29,050 sq m (about 7.2 acres) · sanctioned built-up 41,449 sq m · recreational space 4,358 sq m

The builder’s record and reviews

A M Patel Infra has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. 7 complaints on MahaRERA across 1 project.

Read Google reviews of 180 and 51 Greens →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

180 and 51 Greens: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 180 and 51 Greens

What is the possession date of 180 and 51 Greens?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 180 and 51 Greens in Satara Aurangabad, Aurangabad is 31 January 2024 — 6 months later than 31 July 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for 180 and 51 Greens?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 180 and 51 Greens's builder has filed on MahaRERA, the official one, is 31 January 2024, already 6 months later than the 31 July 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of 180 and 51 Greens extended?

According to GharKundli's check of MahaRERA records (updated November 2026), 180 and 51 Greens's builder applied to MahaRERA to extend the completion date once: to 31 January 2024, giving the reason "We do Have four towers consisting 46 units in each towers . Out of four towers our three towers are 98% completed. Fourth tower we have completed entire RCC work, drainage line is completed, exterior final paint is in progress. Lift is ordered . within 45 days lift will be installed . 50 percent apartments Glass aluminium work is completed and rest is in progress. All common area like all floors staircase lift lobbies , parking, entrance lobby , parking light is completed. All basic services like water , drainage line, electricity services are operational through out the project. Further we…".

What is the RERA number of 180 and 51 Greens?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 180 and 51 Greens in Satara Aurangabad, Aurangabad is P51500004770.

Is 180 and 51 Greens registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 180 and 51 Greens is registered as P51500004770 and its status is "Lapsed (registration period ended)".

What is the construction status of 180 and 51 Greens?

According to GharKundli's check of MahaRERA records (updated November 2026), 180 and 51 Greens's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 8 towers. GharKundli's full report compares construction progress with the deadline.

Does 180 and 51 Greens have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is 180 and 51 Greens safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), 180 and 51 Greens is registered on MahaRERA as P51500004770, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 180 and 51 Greens's possession date changes?

The latest dates are on 180 and 51 Greens's MahaRERA page (P51500004770). GharKundli's Kundli Watch sends a free WhatsApp update on 180 and 51 Greens every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 180 and 51 Greens have?

According to GharKundli's check of MahaRERA records (updated November 2026), 180 and 51 Greens has 8 buildings filed: WING A OF 180 GREENS with 14 floors and 46 units; WING B OF 180 GREENS with 14 floors and 46 units; WING C OF 180 GREENS with 14 floors and 46 units; WING D OF 180 GREENS with 14 floors and 46 units; WING E OF 51 GREENS with 153 floors and 50 units; CLUBHOUSE II with 2 floors and 1 units; and 2 more.

How much parking does 180 and 51 Greens have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 40 open car parking spaces for 180 and 51 Greens.

How big is the land of 180 and 51 Greens?

According to GharKundli's check of MahaRERA records (updated November 2026), 180 and 51 Greens stands on 29,050 sq m of land (about 7.2 acres), with 41,449 sq m of sanctioned built-up area and 4,358 sq m of recreational open space.

What is the track record of 180 and 51 Greens's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), A M Patel Infra has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. 7 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of 180 and 51 Greens?

Google Maps has reviews of 180 and 51 Greens written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 180 and 51 Greens?

180 and 51 Greens by A.M.PATEL INFRA PVT LTD is in Satara Aurangabad, Aurangabad (pincode 431005), Maharashtra, and is registered on MahaRERA as P51500004770, per GharKundli's check of MahaRERA records.

How many homes are in 180 and 51 Greens?

According to GharKundli's check of MahaRERA records (updated November 2026), 180 and 51 Greens has 236 homes in 8 towers registered on MahaRERA, and 52% of them are sold or booked.

When was 180 and 51 Greens registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 180 and 51 Greens was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on 180 and 51 Greens?

No court cases are listed for 180 and 51 Greens on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of 180 and 51 Greens?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is A.M.PATEL INFRA PVT LTD, which has 1 other project registered on MahaRERA.

Other projects in Aurangabad

All 93 projects in Kranti Chowk (431005) →

Other projects by A.M.PATEL INFRA PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.