Skip to content
GharKundli

SHRINATH PARK

by SHRI NATH VIHAR CONSTRUCTIONS · Town Centre, Aurangabad

Possession: SHRINATH PARK is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51500006059. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SHRINATH PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHRINATH PARK has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 29 June 2022

    Extended at the builder's request (MahaRERA application EXT51500011276)

    Reason the builder gave MahaRERA: “CONSTRUCTION IS DELAYED DUE TO NON AVAILABILITY OF MATERIAL AND LABOUR DURING CORONA PANDEMIC”

Source: SHRINATH PARK’s extension records on MahaRERA (P51500006059), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHRINATH PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500006059
Status
Completed
Builder
SHRI NATH VIHAR CONSTRUCTIONS
Location
Town Centre, Aurangabad · 431001
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
December 2021
Latest completion date
June 2022
Delay so far
6 months
Homes
49
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SHRINATH PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING D100%100%100%100%
WING C100%100%100%100%
WING B100%100%100%100%
WING A100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRINATH PARK every month.

SHRINATH PARK: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING D (7 floors) · WING C (3 floors) · WING B (3 floors) · WING A (3 floors)
  • Land: 5,300 sq m (about 1.3 acres) · sanctioned built-up 2,815 sq m · recreational space 527 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHRINATH PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHRINATH PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHRINATH PARK

What is the possession date of SHRINATH PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHRINATH PARK in Town Centre, Aurangabad is 29 June 2022 — 6 months later than 30 December 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SHRINATH PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRINATH PARK's builder has filed on MahaRERA, the official one, is 29 June 2022, already 6 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHRINATH PARK extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRINATH PARK's builder applied to MahaRERA to extend the completion date once: to 29 June 2022, giving the reason "CONSTRUCTION IS DELAYED DUE TO NON AVAILABILITY OF MATERIAL AND LABOUR DURING CORONA PANDEMIC".

What is the RERA number of SHRINATH PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHRINATH PARK in Town Centre, Aurangabad is P51500006059.

Is SHRINATH PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRINATH PARK is registered as P51500006059 and its status is "Completed".

What is the construction status of SHRINATH PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRINATH PARK's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does SHRINATH PARK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SHRINATH PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRINATH PARK is registered on MahaRERA as P51500006059, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHRINATH PARK's possession date changes?

The latest dates are on SHRINATH PARK's MahaRERA page (P51500006059). GharKundli's Kundli Watch sends a free WhatsApp update on SHRINATH PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHRINATH PARK have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRINATH PARK has 4 buildings filed: WING D with 7 floors; WING C with 3 floors; WING B with 3 floors; WING A with 3 floors.

How big is the land of SHRINATH PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRINATH PARK stands on 5,300 sq m of land (about 1.3 acres), with 2,815 sq m of sanctioned built-up area and 527 sq m of recreational open space.

Where can I read reviews of SHRINATH PARK?

Google Maps has reviews of SHRINATH PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHRINATH PARK?

SHRINATH PARK by SHRI NATH VIHAR CONSTRUCTIONS is in Town Centre, Aurangabad (pincode 431001), Maharashtra, and is registered on MahaRERA as P51500006059, per GharKundli's check of MahaRERA records.

How many homes are in SHRINATH PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRINATH PARK has 49 homes in 4 towers registered on MahaRERA.

When was SHRINATH PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHRINATH PARK was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHRINATH PARK?

No court cases are listed for SHRINATH PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHRINATH PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHRI NATH VIHAR CONSTRUCTIONS.

Other projects in Aurangabad

All 177 projects in Chhatrapati Sambhajinagar (431001) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.