KALYANI SAI VISHWA
by RAJASHREE UDYOG · Sawangi, Aurangabad
Possession date of KALYANI SAI VISHWA: 31 July 2028, moved from 30 March 2023 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500006121, and currently active. Its completion date has moved from March 2023 to July 2028: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about KALYANI SAI VISHWA?
How the possession date of KALYANI SAI VISHWA has moved
30 March 2023
Completion date given when the project was registered
31 March 2028
Extended at the builder's request (MahaRERA application EXT51500016580)
Reason the builder gave MahaRERA: “Lack of Demand from Customers and Shortage of Fund”
31 July 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: KALYANI SAI VISHWA’s extension records on MahaRERA (P51500006121), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KALYANI SAI VISHWA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500006121
- Status
- Registered and active
- Builder
- RAJASHREE UDYOG
- Location
- Sawangi, Aurangabad · 431001
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- March 2023
- Latest completion date
- July 2028
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 340
- Sold or booked
- 67%
- Towers
- 12
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of KALYANI SAI VISHWA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A-WING A-1, A-2 | 100% | 100% | 100% | 100% |
| BUILIDNG -B, WING-B1,B2 | 100% | 100% | 100% | 100% |
| BUILDING C, WING C-1, C-2 | 100% | 100% | 100% | 100% |
| BUILDING D, WING D-1, D-2 | 0% | 0% | 0% | 0% |
| BUILDING -E, WING E-1,E-2 | 100% | 100% | 100% | 100% |
| BUILDING F, WING-F1,F-2 | 100% | 100% | 100% | 100% |
| BUILDING G, WING-G-1G-2 | 0% | 0% | 0% | 0% |
| BUILDING -H | 0% | 0% | 0% | 0% |
| BUILDING-I, WING I-1,I-2,I-2 | 100% | 100% | 100% | 100% |
| BUILDING-J, WING J-1,J-2,J-3 | 100% | 100% | 70% | 0% |
| BUILDING-K, WING-K1,K-2,K-3 | 100% | 100% | 100% | 100% |
| BUILDING L, WING-L-1,L-2,L-3 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING A-WING A-1, A-2: covers 5 floors
- BUILIDNG -B, WING-B1,B2: covers 5 floors
- BUILDING C, WING C-1, C-2: covers 5 floors
- BUILDING D, WING D-1, D-2: covers 8 floors
- BUILDING -E, WING E-1,E-2: covers 5 floors
- BUILDING F, WING-F1,F-2: covers 5 floors
- BUILDING G, WING-G-1G-2: covers 5 floors
- BUILDING -H: covers 5 floors
- BUILDING-I, WING I-1,I-2,I-2: covers 4 floors
- BUILDING-J, WING J-1,J-2,J-3: covers 5 floors
- BUILDING-K, WING-K1,K-2,K-3: covers 5 floors
- BUILDING L, WING-L-1,L-2,L-3: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KALYANI SAI VISHWA every month.
KALYANI SAI VISHWA: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING A-WING A-1, A-2 (5 floors, 24 units) · BUILIDNG -B, WING-B1,B2 (5 floors, 24 units) · BUILDING C, WING C-1, C-2 (5 floors, 24 units) · BUILDING D, WING D-1, D-2 (8 floors, 24 units) · BUILDING -E, WING E-1,E-2 (5 floors, 24 units) · BUILDING F, WING-F1,F-2 (5 floors, 24 units) · BUILDING G, WING-G-1G-2 (5 floors, 36 units) · BUILDING -H (5 floors, 16 units) · and 4 more
- Car parking: 11 open
- Land: 22,000 sq m (about 5.4 acres) · sanctioned built-up 14,821 sq m · recreational space 2,200 sq m
- Boundaries filed include: KHAM RIVER
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of KALYANI SAI VISHWA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KALYANI SAI VISHWA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KALYANI SAI VISHWA
What is the possession date of KALYANI SAI VISHWA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KALYANI SAI VISHWA in Sawangi, Aurangabad is 31 July 2028 — 60 months later than 30 March 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for KALYANI SAI VISHWA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KALYANI SAI VISHWA's builder has filed on MahaRERA, the official one, is 31 July 2028, already 60 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KALYANI SAI VISHWA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), KALYANI SAI VISHWA's builder applied to MahaRERA to extend the completion date once: to 31 March 2028, giving the reason "Lack of Demand from Customers and Shortage of Fund". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of KALYANI SAI VISHWA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KALYANI SAI VISHWA in Sawangi, Aurangabad is P51500006121.
Is KALYANI SAI VISHWA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KALYANI SAI VISHWA is registered as P51500006121 and its status is "Registered and active".
What is the construction status of KALYANI SAI VISHWA?
According to GharKundli's check of MahaRERA records (updated November 2026), KALYANI SAI VISHWA's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 12 towers. GharKundli's full report compares construction progress with the deadline.
Does KALYANI SAI VISHWA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is KALYANI SAI VISHWA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), KALYANI SAI VISHWA is registered on MahaRERA as P51500006121, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KALYANI SAI VISHWA's possession date changes?
The latest dates are on KALYANI SAI VISHWA's MahaRERA page (P51500006121). GharKundli's Kundli Watch sends a free WhatsApp update on KALYANI SAI VISHWA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KALYANI SAI VISHWA have?
According to GharKundli's check of MahaRERA records (updated November 2026), KALYANI SAI VISHWA has 12 buildings filed: BUILDING A-WING A-1, A-2 with 5 floors and 24 units; BUILIDNG -B, WING-B1,B2 with 5 floors and 24 units; BUILDING C, WING C-1, C-2 with 5 floors and 24 units; BUILDING D, WING D-1, D-2 with 8 floors and 24 units; BUILDING -E, WING E-1,E-2 with 5 floors and 24 units; BUILDING F, WING-F1,F-2 with 5 floors and 24 units; and 6 more.
How much parking does KALYANI SAI VISHWA have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 11 open car parking spaces for KALYANI SAI VISHWA.
How big is the land of KALYANI SAI VISHWA?
According to GharKundli's check of MahaRERA records (updated November 2026), KALYANI SAI VISHWA stands on 22,000 sq m of land (about 5.4 acres), with 14,821 sq m of sanctioned built-up area and 2,200 sq m of recreational open space.
Where can I read reviews of KALYANI SAI VISHWA?
Google Maps has reviews of KALYANI SAI VISHWA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KALYANI SAI VISHWA?
KALYANI SAI VISHWA by RAJASHREE UDYOG is in Sawangi, Aurangabad (pincode 431001), Maharashtra, and is registered on MahaRERA as P51500006121, per GharKundli's check of MahaRERA records. Its boundaries filed there include KHAM RIVER.
How many homes are in KALYANI SAI VISHWA?
According to GharKundli's check of MahaRERA records (updated November 2026), KALYANI SAI VISHWA has 340 homes in 12 towers registered on MahaRERA, and 67% of them are sold or booked.
When was KALYANI SAI VISHWA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KALYANI SAI VISHWA was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on KALYANI SAI VISHWA?
No court cases are listed for KALYANI SAI VISHWA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of KALYANI SAI VISHWA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAJASHREE UDYOG.
Check it yourself on MahaRERA
- How to check the possession date of KALYANI SAI VISHWA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Aurangabad →
Other projects in Sawangi
All 137 projects in Chhatrapati Sambhajinagar (431001) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.