SARA PARIVARTAN SECTOR B - PH 2
by SARA PROPERTIES (Jagrutsara) · Sawangi, Aurangabad
Possession: SARA PARIVARTAN SECTOR B - PH 2 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500016122. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SARA PARIVARTAN SECTOR B - PH 2?
How the possession date of SARA PARIVARTAN SECTOR B - PH 2 has moved
21 April 2022
Completion date given when the project was registered
20 April 2023
Extended at the builder's request (MahaRERA application EXT51500012418)
Reason the builder gave MahaRERA: “We have completed the said project , and also applied for completion certificate to Authority but there are local issues about authority so we required some more time for completion certificate till 20/04/2023... please grant the extension”
Source: SARA PARIVARTAN SECTOR B - PH 2’s extension records on MahaRERA (P51500016122), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SARA PARIVARTAN SECTOR B - PH 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- SARA PARIVARTAN - SECTOR B - PHASE 1P51500001468
- SARA PARIVARTAN - SECTOR EP51500001935
- MahaRERA registration
- P51500016122
- Status
- Completed
- Builder
- SARA PROPERTIES
- Location
- Sawangi, Aurangabad · 431007
- Project type
- Residential / Group Housing
- Registered on
- 17 Apr 2018
- Completion date at registration
- April 2022
- Latest completion date
- April 2023
- Delay so far
- 12 months
- Homes
- 163
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of SARA PARIVARTAN SECTOR B - PH 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| H TYPE BUILDING WING 17-18-19-20-21 | 100% | 100% | 100% | 100% |
| I TYPE BUILDING WING 22-23 | 100% | 100% | 100% | 100% |
| I TYPE BUILDING WING 24-25 | 100% | 100% | 100% | 100% |
| I TYPE BUILDING WING 26-27 | 100% | 100% | 100% | 75% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SARA PARIVARTAN SECTOR B - PH 2 every month.
SARA PARIVARTAN SECTOR B - PH 2: buildings, flats and land, as filed on MahaRERA
- Buildings: H TYPE BUILDING WING 17-18-19-20-21 (9 floors) · I TYPE BUILDING WING 22-23 (9 floors) · I TYPE BUILDING WING 24-25 (9 floors) · I TYPE BUILDING WING 26-27 (9 floors)
- Land: 3,135 sq m (about 0.8 acres) · sanctioned built-up 6,660 sq m · recreational space 1,437 sq m
The builder’s record and reviews
Sara Properties (a group of 9 linked companies) has 50 projects on MahaRERA since 2019, this one included. Of the 22 GharKundli has checked: 5 finished, 4 within the promised date and 1 needed more time (typically 6 months); 16 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of SARA PARIVARTAN SECTOR B - PH 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SARA PARIVARTAN SECTOR B - PH 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SARA PARIVARTAN SECTOR B - PH 2
What is the possession date of SARA PARIVARTAN SECTOR B - PH 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SARA PARIVARTAN SECTOR B - PH 2 in Sawangi, Aurangabad is 20 April 2023 — 12 months later than 21 April 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SARA PARIVARTAN SECTOR B - PH 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SARA PARIVARTAN SECTOR B - PH 2's builder has filed on MahaRERA, the official one, is 20 April 2023, already 12 months later than the 21 April 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SARA PARIVARTAN SECTOR B - PH 2 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SARA PARIVARTAN SECTOR B - PH 2's builder applied to MahaRERA to extend the completion date once: to 20 April 2023, giving the reason "We have completed the said project , and also applied for completion certificate to Authority but there are local issues about authority so we required some more time for completion certificate till 20/04/2023... please grant the extension".
What is the RERA number of SARA PARIVARTAN SECTOR B - PH 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SARA PARIVARTAN SECTOR B - PH 2 in Sawangi, Aurangabad is P51500016122.
Is SARA PARIVARTAN SECTOR B - PH 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SARA PARIVARTAN SECTOR B - PH 2 is registered as P51500016122 and its status is "Completed".
What is the construction status of SARA PARIVARTAN SECTOR B - PH 2?
According to GharKundli's check of MahaRERA records (updated November 2026), SARA PARIVARTAN SECTOR B - PH 2's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does SARA PARIVARTAN SECTOR B - PH 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SARA PARIVARTAN SECTOR B - PH 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SARA PARIVARTAN SECTOR B - PH 2 is registered on MahaRERA as P51500016122, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does SARA PARIVARTAN SECTOR B - PH 2 have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: SARA PARIVARTAN - SECTOR B - PHASE 1 (P51500001468); SARA PARIVARTAN - SECTOR E (P51500001935). Check that your agreement names the registration of your own wing.
How can I get updates if SARA PARIVARTAN SECTOR B - PH 2's possession date changes?
The latest dates are on SARA PARIVARTAN SECTOR B - PH 2's MahaRERA page (P51500016122). GharKundli's Kundli Watch sends a free WhatsApp update on SARA PARIVARTAN SECTOR B - PH 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SARA PARIVARTAN SECTOR B - PH 2 have?
According to GharKundli's check of MahaRERA records (updated November 2026), SARA PARIVARTAN SECTOR B - PH 2 has 4 buildings filed: H TYPE BUILDING WING 17-18-19-20-21 with 9 floors; I TYPE BUILDING WING 22-23 with 9 floors; I TYPE BUILDING WING 24-25 with 9 floors; I TYPE BUILDING WING 26-27 with 9 floors.
How big is the land of SARA PARIVARTAN SECTOR B - PH 2?
According to GharKundli's check of MahaRERA records (updated November 2026), SARA PARIVARTAN SECTOR B - PH 2 stands on 3,135 sq m of land (about 0.8 acres), with 6,660 sq m of sanctioned built-up area and 1,437 sq m of recreational open space.
What is the track record of SARA PARIVARTAN SECTOR B - PH 2's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Sara Properties (a group of 9 linked companies) has 50 projects on MahaRERA since 2019, this one included. Of the 22 GharKundli has checked: 5 finished, 4 within the promised date and 1 needed more time (typically 6 months); 16 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SARA PARIVARTAN SECTOR B - PH 2?
Google Maps has reviews of SARA PARIVARTAN SECTOR B - PH 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SARA PARIVARTAN SECTOR B - PH 2?
SARA PARIVARTAN SECTOR B - PH 2 by SARA PROPERTIES (Jagrutsara) is in Sawangi, Aurangabad (pincode 431007), Maharashtra, and is registered on MahaRERA as P51500016122, per GharKundli's check of MahaRERA records.
How many homes are in SARA PARIVARTAN SECTOR B - PH 2?
According to GharKundli's check of MahaRERA records (updated November 2026), SARA PARIVARTAN SECTOR B - PH 2 has 163 homes in 4 towers registered on MahaRERA.
When was SARA PARIVARTAN SECTOR B - PH 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SARA PARIVARTAN SECTOR B - PH 2 was registered on MahaRERA on 17 April 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on SARA PARIVARTAN SECTOR B - PH 2?
No court cases are listed for SARA PARIVARTAN SECTOR B - PH 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SARA PARIVARTAN SECTOR B - PH 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SARA PROPERTIES, the company Jagrutsara files this project under, which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SARA PARIVARTAN SECTOR B - PH 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Sawangi
All 28 projects in Chikalthana (431007) →Other projects by SARA PROPERTIES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.