LAKSHYA VINAYAK RESIDENCY

by EXPERT FOUNDATION AND STRUCTURE PVT LTD · Jatwada Road, Aurangabad

Possession date of LAKSHYA VINAYAK RESIDENCY: 31 December 2025, moved from 30 June 2021 (54 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51500007854. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about LAKSHYA VINAYAK RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of LAKSHYA VINAYAK RESIDENCY has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 29 June 2023

    Extended at the builder's request (MahaRERA application EXT51500010511)

    Reason the builder gave MahaRERA:
    “The construction of the project got delayed on account pandemic situation across country due to COVID-19. The construction work at site is completely stopped due to non-availability of labour, we have communicated the same to our customers…” Read the full reason“The construction of the project got delayed on account pandemic situation across country due to COVID-19. The construction work at site is completely stopped due to non-availability of labour, we have communicated the same to our customers and they are also understanding the difficulty. The customers have issued their consent for extension of the date of completion of the project. Hence, we request you to allow us extension by 24 months from original date of completion.”
  3. 29 December 2024

    Extended at the builder's request (MahaRERA application EXT51500018551)

    Reason the builder gave MahaRERA: “The registered project technically completed in all respect, waiting for occupancy certificate from respective authority.”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51500027447)

    Reason the builder gave MahaRERA:
    “The construction and development work of the project was fully completed in September 2024. However, we are unable to obtain the Completion Certificate from AMRDA due to a delay in their online process, which is currently on hold at the aut…” Read the full reason“The construction and development work of the project was fully completed in September 2024. However, we are unable to obtain the Completion Certificate from AMRDA due to a delay in their online process, which is currently on hold at the authority’s end.Since this delay is purely technical and beyond our control, we kindly request a 12-month extension for the project. The project is 100% complete, and possession has already been handed over to buyers. Therefore, there is no inconvenience or loss to the customers.We request you to grant the extension at the earliest.”

Source: LAKSHYA VINAYAK RESIDENCY’s extension records on MahaRERA (P51500007854), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on LAKSHYA VINAYAK RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500007854
Status
Lapsed (registration period ended)
Builder
EXPERT FOUNDATION AND STRUCTURE PVT LTD
Location
Jatwada Road, Aurangabad · 431007
Project type
Residential / Group Housing
Registered on
18 Aug 2017
Completion date at registration
June 2021
Latest completion date
December 2025
Delay so far
54 months
Homes
26
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of LAKSHYA VINAYAK RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING 1 TO 20100%100%100%100%
BUILDING 23 TO 28100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on LAKSHYA VINAYAK RESIDENCY every month.

LAKSHYA VINAYAK RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING 1 TO 20 (2 floors) · BUILDING 23 TO 28 (2 floors)
  • Land: 1,744 sq m (about 0.4 acres) · sanctioned built-up 1,497 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of LAKSHYA VINAYAK RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

LAKSHYA VINAYAK RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about LAKSHYA VINAYAK RESIDENCY

What is the possession date of LAKSHYA VINAYAK RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for LAKSHYA VINAYAK RESIDENCY in Jatwada Road, Aurangabad is 31 December 2025 — 54 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for LAKSHYA VINAYAK RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date LAKSHYA VINAYAK RESIDENCY's builder has filed on MahaRERA, the official one, is 31 December 2025, already 54 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of LAKSHYA VINAYAK RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKSHYA VINAYAK RESIDENCY's builder applied to MahaRERA to extend the completion date 3 times: to 29 June 2023, giving the reason "The construction of the project got delayed on account pandemic situation across country due to COVID-19. The construction work at site is completely stopped due to non-availability of labour, we have communicated the same to our customers and they are also understanding the difficulty. The customers have issued their consent for extension of the date of completion of the project. Hence, we request you to allow us extension by 24 months from original date of completion."; to 29 December 2024, giving the reason "The registered project technically completed in all respect, waiting for occupancy certificate from respective authority."; to 31 December 2025, giving the reason "The construction and development work of the project was fully completed in September 2024. However, we are unable to obtain the Completion Certificate from AMRDA due to a delay in their online process, which is currently on hold at the authority’s end.Since this delay is purely technical and beyond our control, we kindly request a 12-month extension for the project. The project is 100% complete, and possession has already been handed over to buyers. Therefore, there is no inconvenience or loss to the customers.We request you to grant the extension at the earliest.".

What is the RERA number of LAKSHYA VINAYAK RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of LAKSHYA VINAYAK RESIDENCY in Jatwada Road, Aurangabad is P51500007854.

Is LAKSHYA VINAYAK RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKSHYA VINAYAK RESIDENCY is registered as P51500007854 and its status is "Lapsed (registration period ended)".

What is the construction status of LAKSHYA VINAYAK RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKSHYA VINAYAK RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does LAKSHYA VINAYAK RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is LAKSHYA VINAYAK RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKSHYA VINAYAK RESIDENCY is registered on MahaRERA as P51500007854, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if LAKSHYA VINAYAK RESIDENCY's possession date changes?

The latest dates are on LAKSHYA VINAYAK RESIDENCY's MahaRERA page (P51500007854). GharKundli's Kundli Watch sends a free WhatsApp update on LAKSHYA VINAYAK RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does LAKSHYA VINAYAK RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKSHYA VINAYAK RESIDENCY has 2 buildings filed: BUILDING 1 TO 20 with 2 floors; BUILDING 23 TO 28 with 2 floors.

How big is the land of LAKSHYA VINAYAK RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKSHYA VINAYAK RESIDENCY stands on 1,744 sq m of land (about 0.4 acres), with 1,497 sq m of sanctioned built-up area.

Where can I read reviews of LAKSHYA VINAYAK RESIDENCY?

Google Maps has reviews of LAKSHYA VINAYAK RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is LAKSHYA VINAYAK RESIDENCY?

LAKSHYA VINAYAK RESIDENCY by EXPERT FOUNDATION AND STRUCTURE PVT LTD is in Jatwada Road, Aurangabad (pincode 431007), Maharashtra, and is registered on MahaRERA as P51500007854, per GharKundli's check of MahaRERA records.

How many homes are in LAKSHYA VINAYAK RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKSHYA VINAYAK RESIDENCY has 26 homes in 2 towers registered on MahaRERA.

When was LAKSHYA VINAYAK RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), LAKSHYA VINAYAK RESIDENCY was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on LAKSHYA VINAYAK RESIDENCY?

No court cases are listed for LAKSHYA VINAYAK RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of LAKSHYA VINAYAK RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is EXPERT FOUNDATION AND STRUCTURE PVT LTD.