Millenia Heights
by Laxminarayan Shriramji Attal · Bhagyanagar, Aurangabad
Possession: Millenia Heights is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500014763. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Millenia Heights?
How the possession date of Millenia Heights has moved
15 December 2019
Completion date given when the project was registered
15 December 2020
Extended at the builder's request (MahaRERA application EXT51500003905)
Reason the builder gave MahaRERA: “The building is 90% ready with internal work going on. Due to the poor demand conditions, we wish to extend the completion of the project by an year.”
9 September 2022
Extended at the builder's request (MahaRERA application EXT51500012524)
Reason the builder gave MahaRERA: “Lockdown due to Covid-19 pandemic in Maharashtra. Unable to complete work due to the same.”
Source: Millenia Heights’s extension records on MahaRERA (P51500014763), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Millenia Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500014763
- Status
- Completed
- Builder
- Laxminarayan Shriramji Attal
- Location
- Bhagyanagar, Aurangabad · 431001
- Project type
- Others
- Registered on
- 2 Jan 2018
- Completion date at registration
- December 2019
- Latest completion date
- September 2022
- Delay so far
- 33 months
- Homes
- 15
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Millenia Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Millenia Heights | 100% | 100% | 100% | 80% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Millenia Heights every month.
Millenia Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: Millenia Heights (7 floors)
- Land: 579 sq m (about 0.1 acres) · sanctioned built-up 792 sq m
- Boundaries filed include: Layout Road 12m, Layout road 9m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Millenia Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Millenia Heights: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Millenia Heights
What is the possession date of Millenia Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Millenia Heights in Bhagyanagar, Aurangabad is 9 September 2022 — 33 months later than 15 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Millenia Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Millenia Heights's builder has filed on MahaRERA, the official one, is 9 September 2022, already 33 months later than the 15 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Millenia Heights extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Millenia Heights's builder applied to MahaRERA to extend the completion date 2 times: to 15 December 2020, giving the reason "The building is 90% ready with internal work going on. Due to the poor demand conditions, we wish to extend the completion of the project by an year."; to 9 September 2022, giving the reason "Lockdown due to Covid-19 pandemic in Maharashtra. Unable to complete work due to the same.".
What is the RERA number of Millenia Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Millenia Heights in Bhagyanagar, Aurangabad is P51500014763.
Is Millenia Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Millenia Heights is registered as P51500014763 and its status is "Completed".
What is the construction status of Millenia Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), Millenia Heights's status on MahaRERA is "Completed". As filed by the builder, slab work on Millenia Heights is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Millenia Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Millenia Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Millenia Heights is registered on MahaRERA as P51500014763, its MahaRERA status is "Completed", its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Millenia Heights's possession date changes?
The latest dates are on Millenia Heights's MahaRERA page (P51500014763). GharKundli's Kundli Watch sends a free WhatsApp update on Millenia Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Millenia Heights have?
According to GharKundli's check of MahaRERA records (updated November 2026), Millenia Heights has one building filed: Millenia Heights with 7 floors.
How big is the land of Millenia Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), Millenia Heights stands on 579 sq m of land (about 0.1 acres), with 792 sq m of sanctioned built-up area.
Where can I read reviews of Millenia Heights?
Google Maps has reviews of Millenia Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Millenia Heights?
Millenia Heights by Laxminarayan Shriramji Attal is in Bhagyanagar, Aurangabad (pincode 431001), Maharashtra, and is registered on MahaRERA as P51500014763, per GharKundli's check of MahaRERA records. Its boundaries filed there include Layout Road 12m, Layout road 9m.
How many homes are in Millenia Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), Millenia Heights has 15 homes in 1 tower registered on MahaRERA.
When was Millenia Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Millenia Heights was registered on MahaRERA on 2 January 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on Millenia Heights?
No court cases are listed for Millenia Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Millenia Heights?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Laxminarayan Shriramji Attal.
Check it yourself on MahaRERA
- How to check the possession date of Millenia Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Aurangabad
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.