by Ojasvi Ramesh Kankariya · Birsingh Place, Aurangabad 431001

What’s in the report? →

Possession date of Aashiyana (MahaRERA P51500015581): 30 September 2020, and it has already passed. It has 12 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51500015581. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51500015581, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (September 2020) has passed.

What do you want to know about Aashiyana?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Aashiyana

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500015581
Status
Lapsed (registration period ended)
Builder
Ojasvi Ramesh Kankariya
Location
Birsingh Place, Aurangabad · 431001
Project type
Residential / Group Housing
Registered on
8 Mar 2018
Completion date at registration
September 2020
Latest completion date
September 2020
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Aashiyana, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Aashiyana11%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aashiyana every 1–2 months.

Aashiyana: buildings, flats and land, as filed on MahaRERA

  • Buildings: Aashiyana (8 floors)
  • Land: 396 sq m (about 0.1 acres) · sanctioned built-up 539 sq m
  • Land, as filed: plot no 41
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Aashiyana →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aashiyana: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aashiyana

What is the possession date of Aashiyana?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aashiyana in Birsingh Place, Aurangabad is 30 September 2020. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Aashiyana?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aashiyana's builder has filed on MahaRERA, the official one, is 30 September 2020, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Aashiyana?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aashiyana in Birsingh Place, Aurangabad is P51500015581.

Is Aashiyana registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashiyana is registered as P51500015581 and its status is "Lapsed (registration period ended)".

What is the current construction status of Aashiyana? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashiyana's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Aashiyana is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Aashiyana have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Aashiyana safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashiyana is registered on MahaRERA as P51500015581, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aashiyana?

Aashiyana isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Aashiyana?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Aashiyana: gharkundli.com/tools/property-cost-calculator

Has Aashiyana received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Aashiyana isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2020 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Aashiyana?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashiyana's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2020) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Aashiyana uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Aashiyana was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Aashiyana's possession date changes?

The latest dates are on Aashiyana's MahaRERA page (P51500015581). GharKundli's Kundli Watch sends a free WhatsApp update on Aashiyana every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aashiyana have?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashiyana has one building filed: Aashiyana with 8 floors.

How big is the land of Aashiyana?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashiyana stands on 396 sq m of land (about 0.1 acres), with 539 sq m of sanctioned built-up area.

What are the reviews of Aashiyana?

Google Maps has reviews of Aashiyana written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aashiyana?

Aashiyana by Ojasvi Ramesh Kankariya is in Birsingh Place, Aurangabad, pincode 431001, Maharashtra, and is registered on MahaRERA as P51500015581, per GharKundli's check of MahaRERA records. Its land is filed as plot no 41. GharKundli lists all 396 MahaRERA projects in Chhatrapati Sambhajinagar (431001).

How many flats are in Aashiyana?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashiyana has 12 homes in 1 tower registered on MahaRERA.

When was Aashiyana registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashiyana was registered on MahaRERA on 8 March 2018. GharKundli did not find a title report on the land on file there.

Does Aashiyana have any legal issues or court cases?

No court cases are listed for Aashiyana on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Aashiyana?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Ojasvi Ramesh Kankariya.