Meridian Court 1
by Vijaykamal Properties Pvt Ltd (Ravi) · New Link Road, MumbaiAlso near Kandivali West, Bandra, Iraniwadi
Possession date of Meridian Court 1: 31 December 2027, moved from 30 December 2024 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800007441, and currently active. 26 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about Meridian Court 1?
How the possession date of Meridian Court 1 has moved
30 December 2024
Completion date given when the project was registered
30 December 2025
Extended at the builder's request (MahaRERA application EXT51800027263)
Reason the builder gave MahaRERA: “delay in approvals and construction”
31 December 2027
Extended at the builder's request (MahaRERA application EA30012619644)
Reason the builder gave MahaRERA:
“Respected Sir/Madam, I. Grounds for Seeking Extension The Promoter respectfully submits that the delay in completion of the project has occurred due to circumstances beyond the reasonable control of the Promoter, despite continuous efforts…” Read the full reason
“Respected Sir/Madam, I. Grounds for Seeking Extension The Promoter respectfully submits that the delay in completion of the project has occurred due to circumstances beyond the reasonable control of the Promoter, despite continuous efforts to maintain construction progress. Labour Shortages due to Elections and Festivals: A significant portion of the project’s workforce originates from Bihar. During the Bihar Legislative Assembly Elections, large-scale labour migration occurred due to mandatory voting and community obligations, causing acute manpower shortages. This was followed by Chhath P…”
Source: Meridian Court 1’s extension records on MahaRERA (P51800007441), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Meridian Court 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 26 complaints, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007441
- Status
- Registered and active
- Builder
- Vijaykamal Properties Pvt Ltd
- Location
- New Link Road, Mumbai · 400067
- Project type
- Others
- Registered on
- 17 Aug 2017
- Completion date at registration
- December 2024
- Latest completion date
- December 2027
- Delay so far
- 36 months
- Homes
- 351
- Sold or booked
- 59%
- Towers
- 1
- Complaints on MahaRERA
- 26
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Meridian Court 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Meridian Court | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Meridian Court: covers 27 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Meridian Court 1 every month.
Meridian Court 1: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 448 – 685 | 176 |
| 1 BHK | 448 – 685 | 175 |
| Shops | 110 – 300 | 22 |
- Buildings: Meridian Court (27 floors, 373 units)
- Land: 764 sq m (about 0.2 acres) · sanctioned built-up 16,472 sq m · recreational space 600 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 4 finished, all within the promised date; 15 still being built, 8 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects.
Read Google reviews of Meridian Court 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Meridian Court 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Meridian Court 1
What is the possession date of Meridian Court 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Meridian Court 1 in New Link Road, Mumbai is 31 December 2027 — 36 months later than 30 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Meridian Court 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Meridian Court 1's builder has filed on MahaRERA, the official one, is 31 December 2027, already 36 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Meridian Court 1 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Meridian Court 1's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "delay in approvals and construction"; to 31 December 2027, giving the reason "Respected Sir/Madam, I. Grounds for Seeking Extension The Promoter respectfully submits that the delay in completion of the project has occurred due to circumstances beyond the reasonable control of the Promoter, despite continuous efforts to maintain construction progress. Labour Shortages due to Elections and Festivals: A significant portion of the project’s workforce originates from Bihar. During the Bihar Legislative Assembly Elections, large-scale labour migration occurred due to mandatory voting and community obligations, causing acute manpower shortages. This was followed by Chhath P…".
What is the RERA number of Meridian Court 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Meridian Court 1 in New Link Road, Mumbai is P51800007441.
Is Meridian Court 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Meridian Court 1 is registered as P51800007441 and its status is "Registered and active". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of Meridian Court 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Meridian Court 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Meridian Court is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Meridian Court 1 have complaints on MahaRERA?
26 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Meridian Court 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Meridian Court 1 is registered on MahaRERA as P51800007441, its completion date has moved 36 months since registration, 26 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Meridian Court 1's possession date changes?
The latest dates are on Meridian Court 1's MahaRERA page (P51800007441). GharKundli's Kundli Watch sends a free WhatsApp update on Meridian Court 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Meridian Court 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Meridian Court 1 has one building filed: Meridian Court with 27 floors and 373 units.
What are the flat sizes (carpet area) in Meridian Court 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Meridian Court 1: 2 BHK: 448 to 685 sq ft carpet (176 homes); 1 BHK: 448 to 685 sq ft carpet (175 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Meridian Court 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Meridian Court 1 stands on 764 sq m of land (about 0.2 acres), with 16,472 sq m of sanctioned built-up area and 600 sq m of recreational open space.
What is the track record of Meridian Court 1's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 4 finished, all within the promised date; 15 still being built, 8 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Meridian Court 1?
Google Maps has reviews of Meridian Court 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 26 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Meridian Court 1?
Meridian Court 1 by Vijaykamal Properties Pvt Ltd (Ravi) is in New Link Road, Mumbai (pincode 400067), near Kandivali West, Bandra, Iraniwadi, Maharashtra, and is registered on MahaRERA as P51800007441, per GharKundli's check of MahaRERA records.
How many homes are in Meridian Court 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Meridian Court 1 has 351 homes in 1 tower registered on MahaRERA, and 59% of them are sold or booked.
When was Meridian Court 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Meridian Court 1 was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Meridian Court 1?
No court cases are listed for Meridian Court 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Meridian Court 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Vijaykamal Properties Pvt Ltd, the company Ravi files this project under, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Meridian Court 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Borivali
- SAFFRONWOODS CHSL
- L&T Realty Ahana Tower B
- L&T Realty Ahana Tower A
- PARSHURAM HEIGHTS
- AVIRAHI ELEGANCE
- MARU MANSION
- SHRADDHA SKYLINE
- RASHMI ICON
Other projects by Vijaykamal Properties Pvt Ltd
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.