YUVRAJ RESIDENCY
by YESHWANT VITHALRAO TIDKE · Gopalpur road Pisadevi, Aurangabad
Possession date of YUVRAJ RESIDENCY: 31 January 2024, moved from 31 January 2023 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51500026163. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (January 2024) has passed.
What do you want to know about YUVRAJ RESIDENCY?
How the possession date of YUVRAJ RESIDENCY has moved
31 January 2023
Completion date given when the project was registered
31 January 2024
Extended at the builder's request (MahaRERA application EXT51500012961)
Reason the builder gave MahaRERA: “Due To Covid Issues and Lockdown the Project started late & due to COVID impact material & labour were not available in required volume therefore project work begins very slow & is Not Completed within time 31/01/2023.”
Source: YUVRAJ RESIDENCY’s extension records on MahaRERA (P51500026163), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on YUVRAJ RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500026163
- Status
- Lapsed (registration period ended)
- Builder
- YESHWANT VITHALRAO TIDKE
- Location
- Gopalpur road Pisadevi, Aurangabad · 431008
- Project type
- Residential / Group Housing
- Registered on
- 25 Aug 2020
- Completion date at registration
- January 2023
- Latest completion date
- January 2024
- Delay so far
- 12 months
- Homes
- 80
- Towers
- 8
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of YUVRAJ RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A | 100% | 100% | 100% | 0% |
| BUILDING B | 100% | 100% | 100% | 0% |
| BUILDING C | 100% | 100% | 100% | 0% |
| BUILDING D | 100% | 70% | 0% | 0% |
| BUILDING E | 100% | 100% | 100% | 0% |
| BUIDING F | 100% | 100% | 70% | 0% |
| BUILDING G | 100% | 100% | 70% | 0% |
| BUILDING H | 100% | 100% | 70% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on YUVRAJ RESIDENCY every month.
YUVRAJ RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING A (2 floors) · BUILDING B (2 floors) · BUILDING C (2 floors) · BUILDING D (6 floors) · BUILDING E (2 floors) · BUIDING F (6 floors) · BUILDING G (3 floors) · BUILDING H (3 floors)
- Land: 5,755 sq m (about 1.4 acres) · sanctioned built-up 4,939 sq m · recreational space 621 sq m
- Boundaries filed include: Gopalpur-pisadevi govt road
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of YUVRAJ RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
YUVRAJ RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about YUVRAJ RESIDENCY
What is the possession date of YUVRAJ RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for YUVRAJ RESIDENCY in Gopalpur road Pisadevi, Aurangabad is 31 January 2024 — 12 months later than 31 January 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for YUVRAJ RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date YUVRAJ RESIDENCY's builder has filed on MahaRERA, the official one, is 31 January 2024, already 12 months later than the 31 January 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of YUVRAJ RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated November 2026), YUVRAJ RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 31 January 2024, giving the reason "Due To Covid Issues and Lockdown the Project started late & due to COVID impact material & labour were not available in required volume therefore project work begins very slow & is Not Completed within time 31/01/2023.".
What is the RERA number of YUVRAJ RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of YUVRAJ RESIDENCY in Gopalpur road Pisadevi, Aurangabad is P51500026163.
Is YUVRAJ RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), YUVRAJ RESIDENCY is registered as P51500026163 and its status is "Lapsed (registration period ended)".
What is the construction status of YUVRAJ RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), YUVRAJ RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 70% to 100% across 8 towers. GharKundli's full report compares construction progress with the deadline.
Does YUVRAJ RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is YUVRAJ RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), YUVRAJ RESIDENCY is registered on MahaRERA as P51500026163, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if YUVRAJ RESIDENCY's possession date changes?
The latest dates are on YUVRAJ RESIDENCY's MahaRERA page (P51500026163). GharKundli's Kundli Watch sends a free WhatsApp update on YUVRAJ RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does YUVRAJ RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), YUVRAJ RESIDENCY has 8 buildings filed: BUILDING A with 2 floors; BUILDING B with 2 floors; BUILDING C with 2 floors; BUILDING D with 6 floors; BUILDING E with 2 floors; BUIDING F with 6 floors; and 2 more.
How big is the land of YUVRAJ RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), YUVRAJ RESIDENCY stands on 5,755 sq m of land (about 1.4 acres), with 4,939 sq m of sanctioned built-up area and 621 sq m of recreational open space.
Where can I read reviews of YUVRAJ RESIDENCY?
Google Maps has reviews of YUVRAJ RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is YUVRAJ RESIDENCY?
YUVRAJ RESIDENCY by YESHWANT VITHALRAO TIDKE is in Gopalpur road Pisadevi, Aurangabad (pincode 431008), Maharashtra, and is registered on MahaRERA as P51500026163, per GharKundli's check of MahaRERA records. Its boundaries filed there include Gopalpur-pisadevi govt road.
How many homes are in YUVRAJ RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), YUVRAJ RESIDENCY has 80 homes in 8 towers registered on MahaRERA.
When was YUVRAJ RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), YUVRAJ RESIDENCY was registered on MahaRERA on 25 August 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on YUVRAJ RESIDENCY?
No court cases are listed for YUVRAJ RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of YUVRAJ RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is YESHWANT VITHALRAO TIDKE.
Check it yourself on MahaRERA
- How to check the possession date of YUVRAJ RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Aurangabad
- NABHRAJ TRILOK HEIGHTS MHADA
- PARAM SUVARNVASTU
- KHINVANSARA AURA
- BUSINESS TRIANGLE
- PRASSANA HIGH CLASS CITY PHASE - I
- Siddhi Ellora Business Park
- HORIZON
- Gaia Carnival Apartment Phase II
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.