SHUBH GRAM PHASE-I HRIDEYA NAGAR
by SHUBHGRAM HOMES · Ohargaon, Aurangabad, Aurangabad
Possession date of SHUBH GRAM PHASE-I HRIDEYA NAGAR: 1 October 2028, moved from 1 June 2025 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500033100, and currently active. Its completion date has moved from June 2025 to October 2028: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SHUBH GRAM PHASE-I HRIDEYA NAGAR?
How the possession date of SHUBH GRAM PHASE-I HRIDEYA NAGAR has moved
1 June 2025
Completion date given when the project was registered
1 June 2028
Extended at the builder's request (MahaRERA application EA06112518246)
Reason the builder gave MahaRERA:
“I respectfully request an extension of time for the completion of the project due to unforeseen delays. The slab work has been delayed owing to the migration of laborers during the festival season and poor coordination between contractors.…” Read the full reason
“I respectfully request an extension of time for the completion of the project due to unforeseen delays. The slab work has been delayed owing to the migration of laborers during the festival season and poor coordination between contractors. Additionally, the progress of the wall and brickwork has been affected by supply chain issues, particularly fluctuations in cement prices. Financial constraints, stemming from a lack of demand from the allottee, have also contributed to the delay. In view of these challenges, we seek the authority’s kind consideration for an extension of time to complete…”1 October 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHUBH GRAM PHASE-I HRIDEYA NAGAR’s extension records on MahaRERA (P51500033100), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHUBH GRAM PHASE-I HRIDEYA NAGAR
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500033100
- Status
- Registered and active
- Builder
- SHUBHGRAM HOMES
- Location
- Ohargaon, Aurangabad, Aurangabad · 431001
- Project type
- Residential / Group Housing
- Registered on
- 9 Feb 2022
- Completion date at registration
- June 2025
- Latest completion date
- October 2028
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 16
- Sold or booked
- 44%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHUBH GRAM PHASE-I HRIDEYA NAGAR, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RH 01 TO 08 | 100% | 100% | 100% | 0% |
| RH 35 TO 42 | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- RH 01 TO 08: covers 3 floors
- RH 35 TO 42: covers 3 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHUBH GRAM PHASE-I HRIDEYA NAGAR every month.
SHUBH GRAM PHASE-I HRIDEYA NAGAR: buildings, flats and land, as filed on MahaRERA
- Buildings: RH 01 TO 08 (3 floors, 8 units) · RH 35 TO 42 (3 floors, 8 units)
- Car parking: 8 covered
- Land: 940 sq m (about 0.2 acres) · sanctioned built-up 1,237 sq m
- Boundaries filed include: 12 MTR WIDE PROJECT ROAD
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHUBH GRAM PHASE-I HRIDEYA NAGAR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHUBH GRAM PHASE-I HRIDEYA NAGAR: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHUBH GRAM PHASE-I HRIDEYA NAGAR
What is the possession date of SHUBH GRAM PHASE-I HRIDEYA NAGAR?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHUBH GRAM PHASE-I HRIDEYA NAGAR in Ohargaon, Aurangabad, Aurangabad is 1 October 2028 — 36 months later than 1 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHUBH GRAM PHASE-I HRIDEYA NAGAR?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHUBH GRAM PHASE-I HRIDEYA NAGAR's builder has filed on MahaRERA, the official one, is 1 October 2028, already 36 months later than the 1 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHUBH GRAM PHASE-I HRIDEYA NAGAR extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBH GRAM PHASE-I HRIDEYA NAGAR's builder applied to MahaRERA to extend the completion date once: to 1 June 2028, giving the reason "I respectfully request an extension of time for the completion of the project due to unforeseen delays. The slab work has been delayed owing to the migration of laborers during the festival season and poor coordination between contractors. Additionally, the progress of the wall and brickwork has been affected by supply chain issues, particularly fluctuations in cement prices. Financial constraints, stemming from a lack of demand from the allottee, have also contributed to the delay. In view of these challenges, we seek the authority’s kind consideration for an extension of time to complete…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SHUBH GRAM PHASE-I HRIDEYA NAGAR?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHUBH GRAM PHASE-I HRIDEYA NAGAR in Ohargaon, Aurangabad, Aurangabad is P51500033100.
Is SHUBH GRAM PHASE-I HRIDEYA NAGAR registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBH GRAM PHASE-I HRIDEYA NAGAR is registered as P51500033100 and its status is "Registered and active".
What is the construction status of SHUBH GRAM PHASE-I HRIDEYA NAGAR?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBH GRAM PHASE-I HRIDEYA NAGAR's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does SHUBH GRAM PHASE-I HRIDEYA NAGAR have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SHUBH GRAM PHASE-I HRIDEYA NAGAR safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBH GRAM PHASE-I HRIDEYA NAGAR is registered on MahaRERA as P51500033100, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHUBH GRAM PHASE-I HRIDEYA NAGAR's possession date changes?
The latest dates are on SHUBH GRAM PHASE-I HRIDEYA NAGAR's MahaRERA page (P51500033100). GharKundli's Kundli Watch sends a free WhatsApp update on SHUBH GRAM PHASE-I HRIDEYA NAGAR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHUBH GRAM PHASE-I HRIDEYA NAGAR have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBH GRAM PHASE-I HRIDEYA NAGAR has 2 buildings filed: RH 01 TO 08 with 3 floors and 8 units; RH 35 TO 42 with 3 floors and 8 units.
How much parking does SHUBH GRAM PHASE-I HRIDEYA NAGAR have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 8 covered car parking spaces for SHUBH GRAM PHASE-I HRIDEYA NAGAR.
How big is the land of SHUBH GRAM PHASE-I HRIDEYA NAGAR?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBH GRAM PHASE-I HRIDEYA NAGAR stands on 940 sq m of land (about 0.2 acres), with 1,237 sq m of sanctioned built-up area.
Where can I read reviews of SHUBH GRAM PHASE-I HRIDEYA NAGAR?
Google Maps has reviews of SHUBH GRAM PHASE-I HRIDEYA NAGAR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHUBH GRAM PHASE-I HRIDEYA NAGAR?
SHUBH GRAM PHASE-I HRIDEYA NAGAR by SHUBHGRAM HOMES is in Ohargaon, Aurangabad, Aurangabad (pincode 431001), Maharashtra, and is registered on MahaRERA as P51500033100, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 MTR WIDE PROJECT ROAD.
How many homes are in SHUBH GRAM PHASE-I HRIDEYA NAGAR?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBH GRAM PHASE-I HRIDEYA NAGAR has 16 homes in 2 towers registered on MahaRERA, and 44% of them are sold or booked.
When was SHUBH GRAM PHASE-I HRIDEYA NAGAR registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHUBH GRAM PHASE-I HRIDEYA NAGAR was registered on MahaRERA on 9 February 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SHUBH GRAM PHASE-I HRIDEYA NAGAR?
No court cases are listed for SHUBH GRAM PHASE-I HRIDEYA NAGAR on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SHUBH GRAM PHASE-I HRIDEYA NAGAR?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHUBHGRAM HOMES.
Check it yourself on MahaRERA
- How to check the possession date of SHUBH GRAM PHASE-I HRIDEYA NAGAR
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Aurangabad →
Other projects in Aurangabad
- NABHRAJ TRILOK HEIGHTS MHADA
- PARAM SUVARNVASTU
- KHINVANSARA AURA
- BUSINESS TRIANGLE
- Siddhi Ellora Business Park
- PRASSANA HIGH CLASS CITY PHASE - I
- HORIZON
- Gaia Carnival Apartment Phase II
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.