SNEH MANJIRI RESIDENCY

by VIKAS LAXMAN CHAUDHARY · Chhatrapati Sambhajinagar (MH), Aurangabad

Possession date of SNEH MANJIRI RESIDENCY: 31 May 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51500033160, and currently active. Its completion date is now May 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SNEH MANJIRI RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SNEH MANJIRI RESIDENCY has moved

  1. 31 January 2027

    Completion date given when the project was registered

  2. 31 May 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SNEH MANJIRI RESIDENCY’s extension records on MahaRERA (P51500033160), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SNEH MANJIRI RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the May 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500033160
Status
Registered and active
Builder
VIKAS LAXMAN CHAUDHARY
Location
Chhatrapati Sambhajinagar (MH), Aurangabad · 431001
Project type
Residential / Group Housing
Registered on
9 Feb 2022
Completion date at registration
January 2027
Latest completion date
May 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
13

Construction progress of SNEH MANJIRI RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SNEH MANJIRI RESIDENCY100%100%65%50%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SNEH MANJIRI RESIDENCY every month.

SNEH MANJIRI RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: SNEH MANJIRI RESIDENCY (6 floors)
  • Land: 391 sq m (about 0.1 acres) · sanctioned built-up 1,240 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SNEH MANJIRI RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SNEH MANJIRI RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SNEH MANJIRI RESIDENCY

What is the possession date of SNEH MANJIRI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SNEH MANJIRI RESIDENCY in Chhatrapati Sambhajinagar (MH), Aurangabad is 31 May 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SNEH MANJIRI RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SNEH MANJIRI RESIDENCY's builder has filed on MahaRERA, the official one, is 31 May 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SNEH MANJIRI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SNEH MANJIRI RESIDENCY in Chhatrapati Sambhajinagar (MH), Aurangabad is P51500033160.

Is SNEH MANJIRI RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SNEH MANJIRI RESIDENCY is registered as P51500033160 and its status is "Registered and active".

What is the construction status of SNEH MANJIRI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SNEH MANJIRI RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SNEH MANJIRI RESIDENCY is 100% done and internal work 65%. GharKundli's full report compares construction progress with the deadline.

Does SNEH MANJIRI RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SNEH MANJIRI RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SNEH MANJIRI RESIDENCY is registered on MahaRERA as P51500033160, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SNEH MANJIRI RESIDENCY's possession date changes?

The latest dates are on SNEH MANJIRI RESIDENCY's MahaRERA page (P51500033160). GharKundli's Kundli Watch sends a free WhatsApp update on SNEH MANJIRI RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SNEH MANJIRI RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), SNEH MANJIRI RESIDENCY has one building filed: SNEH MANJIRI RESIDENCY with 6 floors.

How big is the land of SNEH MANJIRI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SNEH MANJIRI RESIDENCY stands on 391 sq m of land (about 0.1 acres), with 1,240 sq m of sanctioned built-up area.

Where can I read reviews of SNEH MANJIRI RESIDENCY?

Google Maps has reviews of SNEH MANJIRI RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SNEH MANJIRI RESIDENCY?

SNEH MANJIRI RESIDENCY by VIKAS LAXMAN CHAUDHARY is in Chhatrapati Sambhajinagar (MH), Aurangabad (pincode 431001), Maharashtra, and is registered on MahaRERA as P51500033160, per GharKundli's check of MahaRERA records.

How many homes are in SNEH MANJIRI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), SNEH MANJIRI RESIDENCY has 12 homes in 1 tower registered on MahaRERA.

When was SNEH MANJIRI RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SNEH MANJIRI RESIDENCY was registered on MahaRERA on 9 February 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SNEH MANJIRI RESIDENCY?

No court cases are listed for SNEH MANJIRI RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SNEH MANJIRI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VIKAS LAXMAN CHAUDHARY, which has 13 other projects registered on MahaRERA.

All projects with possession due in 2027 in Aurangabad →

Other projects in pincode 431001

All 189 projects in Chhatrapati Sambhajinagar (431001) →

Other projects by VIKAS LAXMAN CHAUDHARY

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.