Skip to content
GharKundli

RMG PLAZA

by Bhagyoday Builders & Developers · Isadvi Road, Aurangabad

Possession date of RMG PLAZA: 28 February 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51500047675, and currently active. Its completion date is now February 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about RMG PLAZA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of RMG PLAZA has moved

  1. 31 October 2028

    Completion date given when the project was registered

  2. 28 February 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: RMG PLAZA’s extension records on MahaRERA (P51500047675), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on RMG PLAZA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the February 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500047675
Status
Registered and active
Builder
Bhagyoday Builders & Developers
Location
Isadvi Road, Aurangabad · 431001
Project type
Others
Registered on
17 Nov 2022
Completion date at registration
October 2028
Latest completion date
February 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
166
Towers
5
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of RMG PLAZA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
C WING FOR ROW HOUSES100%80%0%0%
D WING FOR ROW HOUSES100%0%0%0%
E WING FOR ROW HOSES100%100%55%0%
A BUILDING0%0%0%0%
B BUILDING25%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on RMG PLAZA every month.

RMG PLAZA: buildings, flats and land, as filed on MahaRERA

  • Buildings: C WING FOR ROW HOUSES (2 floors) · D WING FOR ROW HOUSES (2 floors) · E WING FOR ROW HOSES (2 floors) · A BUILDING (9 floors) · B BUILDING (9 floors)
  • Land: 6,000 sq m (about 1.5 acres) · sanctioned built-up 9,535 sq m · recreational space 673 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of RMG PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

RMG PLAZA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about RMG PLAZA

What is the possession date of RMG PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RMG PLAZA in Isadvi Road, Aurangabad is 28 February 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for RMG PLAZA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date RMG PLAZA's builder has filed on MahaRERA, the official one, is 28 February 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of RMG PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RMG PLAZA in Isadvi Road, Aurangabad is P51500047675.

Is RMG PLAZA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), RMG PLAZA is registered as P51500047675 and its status is "Registered and active".

What is the construction status of RMG PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), RMG PLAZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does RMG PLAZA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is RMG PLAZA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), RMG PLAZA is registered on MahaRERA as P51500047675, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if RMG PLAZA's possession date changes?

The latest dates are on RMG PLAZA's MahaRERA page (P51500047675). GharKundli's Kundli Watch sends a free WhatsApp update on RMG PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does RMG PLAZA have?

According to GharKundli's check of MahaRERA records (updated November 2026), RMG PLAZA has 5 buildings filed: C WING FOR ROW HOUSES with 2 floors; D WING FOR ROW HOUSES with 2 floors; E WING FOR ROW HOSES with 2 floors; A BUILDING with 9 floors; B BUILDING with 9 floors.

How big is the land of RMG PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), RMG PLAZA stands on 6,000 sq m of land (about 1.5 acres), with 9,535 sq m of sanctioned built-up area and 673 sq m of recreational open space.

Where can I read reviews of RMG PLAZA?

Google Maps has reviews of RMG PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is RMG PLAZA?

RMG PLAZA by Bhagyoday Builders & Developers is in Isadvi Road, Aurangabad (pincode 431001), Maharashtra, and is registered on MahaRERA as P51500047675, per GharKundli's check of MahaRERA records.

How many homes are in RMG PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), RMG PLAZA has 166 homes in 5 towers registered on MahaRERA.

When was RMG PLAZA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), RMG PLAZA was registered on MahaRERA on 17 November 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on RMG PLAZA?

No court cases are listed for RMG PLAZA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of RMG PLAZA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Bhagyoday Builders & Developers.

All projects with possession due in 2029 in Aurangabad →

Other projects in Aurangabad

All 150 projects in Chhatrapati Sambhajinagar (431001) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.