NAVKAR RESIDENCY
by NAVKAR BUILDCON · Satara Parisar, Aurangabad
Possession date of NAVKAR RESIDENCY: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500051052, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about NAVKAR RESIDENCY?
How the possession date of NAVKAR RESIDENCY has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: NAVKAR RESIDENCY’s extension records on MahaRERA (P51500051052), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NAVKAR RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51500051052
- Status
- Registered and active
- Builder
- NAVKAR BUILDCON
- Location
- Satara Parisar, Aurangabad · 431001
- Project type
- Residential / Group Housing
- Registered on
- 22 May 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 22
- Sold or booked
- 45%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of NAVKAR RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NAVKAR RESIDENCY | 100% | 100% | 96% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- NAVKAR RESIDENCY: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NAVKAR RESIDENCY every month.
NAVKAR RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: NAVKAR RESIDENCY (7 floors, 22 units)
- Land: 532 sq m (about 0.1 acres) · sanctioned built-up 1,702 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of NAVKAR RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NAVKAR RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NAVKAR RESIDENCY
What is the possession date of NAVKAR RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NAVKAR RESIDENCY in Satara Parisar, Aurangabad is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for NAVKAR RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NAVKAR RESIDENCY's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of NAVKAR RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NAVKAR RESIDENCY in Satara Parisar, Aurangabad is P51500051052.
Is NAVKAR RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NAVKAR RESIDENCY is registered as P51500051052 and its status is "Registered and active".
What is the construction status of NAVKAR RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), NAVKAR RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NAVKAR RESIDENCY is 100% done and internal work 96%. GharKundli's full report compares construction progress with the deadline.
Does NAVKAR RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is NAVKAR RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), NAVKAR RESIDENCY is registered on MahaRERA as P51500051052, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NAVKAR RESIDENCY's possession date changes?
The latest dates are on NAVKAR RESIDENCY's MahaRERA page (P51500051052). GharKundli's Kundli Watch sends a free WhatsApp update on NAVKAR RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NAVKAR RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), NAVKAR RESIDENCY has one building filed: NAVKAR RESIDENCY with 7 floors and 22 units.
How big is the land of NAVKAR RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), NAVKAR RESIDENCY stands on 532 sq m of land (about 0.1 acres), with 1,702 sq m of sanctioned built-up area.
Where can I read reviews of NAVKAR RESIDENCY?
Google Maps has reviews of NAVKAR RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NAVKAR RESIDENCY?
NAVKAR RESIDENCY by NAVKAR BUILDCON is in Satara Parisar, Aurangabad (pincode 431001), Maharashtra, and is registered on MahaRERA as P51500051052, per GharKundli's check of MahaRERA records.
How many homes are in NAVKAR RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), NAVKAR RESIDENCY has 22 homes in 1 tower registered on MahaRERA, and 45% of them are sold or booked.
When was NAVKAR RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NAVKAR RESIDENCY was registered on MahaRERA on 22 May 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on NAVKAR RESIDENCY?
No court cases are listed for NAVKAR RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of NAVKAR RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NAVKAR BUILDCON, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of NAVKAR RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Aurangabad →
Other projects in Satara Parisar
- PARSHWA HEIGHTS
- Hrim Ssky City Phase IV
- SARA SAPHIRE PH - I
- SARA SAPHIRE PH - II
- BRAHMA PARK
- P-9 VILLAS
- 18 LAXMI ELITES
- SIGNATURE 27
Other projects by NAVKAR BUILDCON
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.