Skip to content
GharKundli

UPTOWN PARK

by ASIF PATEL RASHEED PATEL · Chhatrapati Sambhajinagar (MH), Aurangabad

Possession date of UPTOWN PARK: 15 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51500051740, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about UPTOWN PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of UPTOWN PARK has moved

  1. 15 December 2028

    Completion date given when the project was registered

  2. 15 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: UPTOWN PARK’s extension records on MahaRERA (P51500051740), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on UPTOWN PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500051740
Status
Registered and active
Builder
ASIF PATEL RASHEED PATEL
Location
Chhatrapati Sambhajinagar (MH), Aurangabad · 431001
Project type
Residential / Group Housing
Registered on
27 Jun 2023
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
21
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of UPTOWN PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
UPTOWN PARK100%90%20%0%

Commencement certificate (CC), as filed on MahaRERA

  • UPTOWN PARK: covers 3 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on UPTOWN PARK every month.

UPTOWN PARK: buildings, flats and land, as filed on MahaRERA

  • Buildings: UPTOWN PARK (3 floors, 21 units)
  • Land: 2,000 sq m (about 0.5 acres) · sanctioned built-up 2,667 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of UPTOWN PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

UPTOWN PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about UPTOWN PARK

What is the possession date of UPTOWN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for UPTOWN PARK in Chhatrapati Sambhajinagar (MH), Aurangabad is 15 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for UPTOWN PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date UPTOWN PARK's builder has filed on MahaRERA, the official one, is 15 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of UPTOWN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of UPTOWN PARK in Chhatrapati Sambhajinagar (MH), Aurangabad is P51500051740.

Is UPTOWN PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), UPTOWN PARK is registered as P51500051740 and its status is "Registered and active".

What is the construction status of UPTOWN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), UPTOWN PARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work on UPTOWN PARK is 90% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.

Does UPTOWN PARK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is UPTOWN PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), UPTOWN PARK is registered on MahaRERA as P51500051740, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if UPTOWN PARK's possession date changes?

The latest dates are on UPTOWN PARK's MahaRERA page (P51500051740). GharKundli's Kundli Watch sends a free WhatsApp update on UPTOWN PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does UPTOWN PARK have?

According to GharKundli's check of MahaRERA records (updated November 2026), UPTOWN PARK has one building filed: UPTOWN PARK with 3 floors and 21 units.

How big is the land of UPTOWN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), UPTOWN PARK stands on 2,000 sq m of land (about 0.5 acres), with 2,667 sq m of sanctioned built-up area.

Where can I read reviews of UPTOWN PARK?

Google Maps has reviews of UPTOWN PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is UPTOWN PARK?

UPTOWN PARK by ASIF PATEL RASHEED PATEL is in Chhatrapati Sambhajinagar (MH), Aurangabad (pincode 431001), Maharashtra, and is registered on MahaRERA as P51500051740, per GharKundli's check of MahaRERA records.

How many homes are in UPTOWN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), UPTOWN PARK has 21 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was UPTOWN PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), UPTOWN PARK was registered on MahaRERA on 27 June 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on UPTOWN PARK?

No court cases are listed for UPTOWN PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of UPTOWN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ASIF PATEL RASHEED PATEL.

All projects with possession due in 2029 in Aurangabad →

Other projects in pincode 431001

All 137 projects in Chhatrapati Sambhajinagar (431001) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.