Skip to content
GharKundli

RAJDEEP HEIGHTS

by RAJDEEP DEVELOPERS · Shahnoorwadi, AurangabadAlso near Chhatrapati Sambhajinagar (MH)

Possession date of RAJDEEP HEIGHTS: 30 October 2026. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51500051151. Status: Lapsed (registration period ended). Its completion date is now October 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about RAJDEEP HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of RAJDEEP HEIGHTS has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: RAJDEEP HEIGHTS’s extension records on MahaRERA (P51500051151), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on RAJDEEP HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500051151
Status
Lapsed (registration period ended)
Builder
RAJDEEP DEVELOPERS
Location
Shahnoorwadi, Aurangabad · 431001
Project type
Residential / Group Housing
Registered on
1 Jun 2023
Completion date at registration
June 2026
Latest completion date
October 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
14
Sold or booked
93%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of RAJDEEP HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RAJDEEP HEIGHTS100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • RAJDEEP HEIGHTS: covers 0 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on RAJDEEP HEIGHTS every month.

RAJDEEP HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: RAJDEEP HEIGHTS (8 floors, 14 units)
  • Car parking: 8 open
  • Land: 399 sq m (about 0.1 acres) · sanctioned built-up 1,496 sq m
  • Boundaries filed include: GOVT ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of RAJDEEP HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

RAJDEEP HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about RAJDEEP HEIGHTS

What is the possession date of RAJDEEP HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RAJDEEP HEIGHTS in Shahnoorwadi, Aurangabad is 30 October 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for RAJDEEP HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date RAJDEEP HEIGHTS's builder has filed on MahaRERA, the official one, is 30 October 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of RAJDEEP HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RAJDEEP HEIGHTS in Shahnoorwadi, Aurangabad is P51500051151.

Is RAJDEEP HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), RAJDEEP HEIGHTS is registered as P51500051151 and its status is "Lapsed (registration period ended)".

What is the construction status of RAJDEEP HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), RAJDEEP HEIGHTS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on RAJDEEP HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does RAJDEEP HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is RAJDEEP HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), RAJDEEP HEIGHTS is registered on MahaRERA as P51500051151, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if RAJDEEP HEIGHTS's possession date changes?

The latest dates are on RAJDEEP HEIGHTS's MahaRERA page (P51500051151). GharKundli's Kundli Watch sends a free WhatsApp update on RAJDEEP HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does RAJDEEP HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), RAJDEEP HEIGHTS has one building filed: RAJDEEP HEIGHTS with 8 floors and 14 units.

How much parking does RAJDEEP HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 8 open car parking spaces for RAJDEEP HEIGHTS.

How big is the land of RAJDEEP HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), RAJDEEP HEIGHTS stands on 399 sq m of land (about 0.1 acres), with 1,496 sq m of sanctioned built-up area.

Where can I read reviews of RAJDEEP HEIGHTS?

Google Maps has reviews of RAJDEEP HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is RAJDEEP HEIGHTS?

RAJDEEP HEIGHTS by RAJDEEP DEVELOPERS is in Shahnoorwadi, Aurangabad (pincode 431001), near Chhatrapati Sambhajinagar (MH), Maharashtra, and is registered on MahaRERA as P51500051151, per GharKundli's check of MahaRERA records. Its boundaries filed there include GOVT ROAD.

How many homes are in RAJDEEP HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), RAJDEEP HEIGHTS has 14 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.

When was RAJDEEP HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), RAJDEEP HEIGHTS was registered on MahaRERA on 1 June 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on RAJDEEP HEIGHTS?

No court cases are listed for RAJDEEP HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of RAJDEEP HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAJDEEP DEVELOPERS.

All projects with possession due in 2026 in Aurangabad →

Other projects in pincode 431001

All 140 projects in Chhatrapati Sambhajinagar (431001) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.