SAHYADRI PARK PHASE 1
by SAHYADRI BUILDERS & DEVELOPERS · Pisadevi, Aurangabad
Possession date of SAHYADRI PARK PHASE 1: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51500053593, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SAHYADRI PARK PHASE 1?
How the possession date of SAHYADRI PARK PHASE 1 has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SAHYADRI PARK PHASE 1’s extension records on MahaRERA (P51500053593), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAHYADRI PARK PHASE 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- SAHYADRI PARK PHASE 2P51500053809 · possession 31 Jul 2028
- MahaRERA registration
- P51500053593
- Status
- Registered and active
- Builder
- SAHYADRI BUILDERS & DEVELOPERS
- Location
- Pisadevi, Aurangabad · 431008
- Project type
- Others
- Registered on
- 10 Nov 2023
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 104
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of SAHYADRI PARK PHASE 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A - TYPE | 0% | 0% | 0% | 0% |
| B - TYPE | 0% | 0% | 0% | 0% |
| C - TYPE | 0% | 0% | 0% | 0% |
| D - TYPE | 0% | 0% | 0% | 0% |
| EF - TYPE | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAHYADRI PARK PHASE 1 every month.
SAHYADRI PARK PHASE 1: buildings, flats and land, as filed on MahaRERA
- Buildings: A - TYPE (2 floors) · B - TYPE (1 floors) · C - TYPE (1 floors) · D - TYPE (1 floors) · EF - TYPE (5 floors)
- Land: 6,700 sq m (about 1.7 acres) · sanctioned built-up 7,325 sq m · recreational space 670 sq m
- Boundaries filed include: CAMBRIDGE -SAWANGI JALGAON BYPASS ROAD
The builder’s record and reviews
Sahyadri Builders & Developers has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of SAHYADRI PARK PHASE 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAHYADRI PARK PHASE 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAHYADRI PARK PHASE 1
What is the possession date of SAHYADRI PARK PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAHYADRI PARK PHASE 1 in Pisadevi, Aurangabad is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SAHYADRI PARK PHASE 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAHYADRI PARK PHASE 1's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SAHYADRI PARK PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAHYADRI PARK PHASE 1 in Pisadevi, Aurangabad is P51500053593.
Is SAHYADRI PARK PHASE 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAHYADRI PARK PHASE 1 is registered as P51500053593 and its status is "Registered and active".
What is the construction status of SAHYADRI PARK PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), SAHYADRI PARK PHASE 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does SAHYADRI PARK PHASE 1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SAHYADRI PARK PHASE 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SAHYADRI PARK PHASE 1 is registered on MahaRERA as P51500053593, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does SAHYADRI PARK PHASE 1 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SAHYADRI PARK PHASE 2 (P51500053809, possession 31 Jul 2028). Check that your agreement names the registration of your own wing.
How can I get updates if SAHYADRI PARK PHASE 1's possession date changes?
The latest dates are on SAHYADRI PARK PHASE 1's MahaRERA page (P51500053593). GharKundli's Kundli Watch sends a free WhatsApp update on SAHYADRI PARK PHASE 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAHYADRI PARK PHASE 1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), SAHYADRI PARK PHASE 1 has 5 buildings filed: A - TYPE with 2 floors; B - TYPE with 1 floors; C - TYPE with 1 floors; D - TYPE with 1 floors; EF - TYPE with 5 floors.
How big is the land of SAHYADRI PARK PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), SAHYADRI PARK PHASE 1 stands on 6,700 sq m of land (about 1.7 acres), with 7,325 sq m of sanctioned built-up area and 670 sq m of recreational open space.
What is the track record of SAHYADRI PARK PHASE 1's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Sahyadri Builders & Developers has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SAHYADRI PARK PHASE 1?
Google Maps has reviews of SAHYADRI PARK PHASE 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAHYADRI PARK PHASE 1?
SAHYADRI PARK PHASE 1 by SAHYADRI BUILDERS & DEVELOPERS is in Pisadevi, Aurangabad (pincode 431008), Maharashtra, and is registered on MahaRERA as P51500053593, per GharKundli's check of MahaRERA records. Its boundaries filed there include CAMBRIDGE -SAWANGI JALGAON BYPASS ROAD.
How many homes are in SAHYADRI PARK PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), SAHYADRI PARK PHASE 1 has 104 homes in 5 towers registered on MahaRERA.
When was SAHYADRI PARK PHASE 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAHYADRI PARK PHASE 1 was registered on MahaRERA on 10 November 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SAHYADRI PARK PHASE 1?
No court cases are listed for SAHYADRI PARK PHASE 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SAHYADRI PARK PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAHYADRI BUILDERS & DEVELOPERS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAHYADRI PARK PHASE 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Aurangabad →
Other projects in Pisadevi
- MADHURA ANGAN PHASE 2
- MADHURA ANGAN
- KISAN PARK
- VITHAI RESIDENCY PHASE I
- SHANTAI RESIDENCY
- GOKULDHAM RESIDENCY
- SAHYADRI PARK PHASE 2
- LAXMI PARK
Other projects by SAHYADRI BUILDERS & DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.