MADHURA ANGAN
by MADHURA ESTATE · Pisadevi, Aurangabad
Possession date of MADHURA ANGAN: 30 April 2032. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1040002500545, and currently active. Its completion date is now April 2032, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MADHURA ANGAN?
How the possession date of MADHURA ANGAN has moved
31 December 2031
Completion date given when the project was registered
30 April 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: MADHURA ANGAN’s extension records on MahaRERA (PR1040002500545), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MADHURA ANGAN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- MADHURA ANGAN PHASE 2PM1040002601068 · possession 30 Apr 2033
- MahaRERA registration
- PR1040002500545
- Status
- Registered and active
- Builder
- MADHURA ESTATE
- Location
- Pisadevi, Aurangabad · 431008
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2025
- Completion date at registration
- December 2031
- Latest completion date
- April 2032
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 88
- Sold or booked
- 0%
- Towers
- 6
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of MADHURA ANGAN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AB Type Building / A type | 100% | 80% | 45% | 25% |
| AB Type Building / B Type | 100% | 80% | 45% | 25% |
| C Type Building | 100% | 100% | 100% | 80% |
| D type Building | 100% | 100% | 100% | 75% |
| E Type Building | 100% | 100% | 100% | 85% |
| F Type | 100% | 100% | 100% | 65% |
Commencement certificate (CC), as filed on MahaRERA
- AB Type Building: covers 8 floors
- AB Type Building: covers 8 floors
- C Type Building: covers 2 floors
- D type Building: covers 2 floors
- E Type Building: covers 2 floors
- F Type: covers 7 floors
Latest CC order on MahaRERA: dated 18/08/2023.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MADHURA ANGAN every month.
MADHURA ANGAN: buildings, flats and land, as filed on MahaRERA
- Buildings: AB Type Building (8 floors, 34 units) · AB Type Building (8 floors, 24 units) · C Type Building (2 floors, 5 units) · D type Building (2 floors, 5 units) · E Type Building (2 floors, 7 units) · F Type (7 floors, 23 units)
- Car parking: 29 covered, 4 open
- Land: 4,412 sq m (about 1.1 acres) · sanctioned built-up 7,535 sq m · recreational space 442 sq m
- Boundaries filed include: POKHARI ROAD
The builder’s record and reviews
Madhura Estate (a group of 2 linked companies) has 2 projects on MahaRERA since 2025, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of MADHURA ANGAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MADHURA ANGAN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MADHURA ANGAN
What is the possession date of MADHURA ANGAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MADHURA ANGAN in Pisadevi, Aurangabad is 30 April 2032, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MADHURA ANGAN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MADHURA ANGAN's builder has filed on MahaRERA, the official one, is 30 April 2032, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of MADHURA ANGAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MADHURA ANGAN in Pisadevi, Aurangabad is PR1040002500545.
Is MADHURA ANGAN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MADHURA ANGAN is registered as PR1040002500545 and its status is "Registered and active".
What is the construction status of MADHURA ANGAN?
According to GharKundli's check of MahaRERA records (updated October 2026), MADHURA ANGAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 80% to 100% across 6 towers. GharKundli's full report compares construction progress with the deadline.
Does MADHURA ANGAN have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is MADHURA ANGAN safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MADHURA ANGAN is registered on MahaRERA as PR1040002500545, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does MADHURA ANGAN have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: MADHURA ANGAN PHASE 2 (PM1040002601068, possession 30 Apr 2033). Check that your agreement names the registration of your own wing.
How can I get updates if MADHURA ANGAN's possession date changes?
The latest dates are on MADHURA ANGAN's MahaRERA page (PR1040002500545). GharKundli's Kundli Watch sends a free WhatsApp update on MADHURA ANGAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MADHURA ANGAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), MADHURA ANGAN has 6 buildings filed: AB Type Building with 8 floors and 34 units; AB Type Building with 8 floors and 24 units; C Type Building with 2 floors and 5 units; D type Building with 2 floors and 5 units; E Type Building with 2 floors and 7 units; F Type with 7 floors and 23 units.
How much parking does MADHURA ANGAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 29 covered and 4 open car parking spaces for MADHURA ANGAN.
How big is the land of MADHURA ANGAN?
According to GharKundli's check of MahaRERA records (updated October 2026), MADHURA ANGAN stands on 4,412 sq m of land (about 1.1 acres), with 7,535 sq m of sanctioned built-up area and 442 sq m of recreational open space.
What is the track record of MADHURA ANGAN's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Madhura Estate (a group of 2 linked companies) has 2 projects on MahaRERA since 2025, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MADHURA ANGAN?
Google Maps has reviews of MADHURA ANGAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MADHURA ANGAN?
MADHURA ANGAN by MADHURA ESTATE is in Pisadevi, Aurangabad (pincode 431008), Maharashtra, and is registered on MahaRERA as PR1040002500545, per GharKundli's check of MahaRERA records. Its boundaries filed there include POKHARI ROAD.
How many homes are in MADHURA ANGAN?
According to GharKundli's check of MahaRERA records (updated October 2026), MADHURA ANGAN has 88 homes in 6 towers registered on MahaRERA, and 0% of them are sold or booked.
When was MADHURA ANGAN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MADHURA ANGAN was registered on MahaRERA on 11 August 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on MADHURA ANGAN?
No court cases are listed for MADHURA ANGAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of MADHURA ANGAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MADHURA ESTATE.
Check it yourself on MahaRERA
- How to check the possession date of MADHURA ANGAN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Pisadevi
- MADHURA ANGAN PHASE 2
- KISAN PARK
- VITHAI RESIDENCY PHASE I
- SHANTAI RESIDENCY
- GOKULDHAM RESIDENCY
- SAHYADRI PARK PHASE 2
- LAXMI PARK
- SAHYADRI PARK PHASE 1
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.