Skip to content
GharKundli

BHAVANA RESIDENCY PHASE II

by NEW TRIMURTI DEVELOPERS · Near Z P School, Aurangabad

Possession date of BHAVANA RESIDENCY PHASE II: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51500053426, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about BHAVANA RESIDENCY PHASE II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of BHAVANA RESIDENCY PHASE II has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: BHAVANA RESIDENCY PHASE II’s extension records on MahaRERA (P51500053426), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on BHAVANA RESIDENCY PHASE II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51500053426
Status
Registered and active
Builder
NEW TRIMURTI DEVELOPERS
Location
Near Z P School, Aurangabad · 431008
Project type
Residential / Group Housing
Registered on
31 Oct 2023
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
35
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of BHAVANA RESIDENCY PHASE II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A BUILDING100%0%0%0%
B BUILDING100%0%0%0%
C BUILDING0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on BHAVANA RESIDENCY PHASE II every month.

BHAVANA RESIDENCY PHASE II: buildings, flats and land, as filed on MahaRERA

  • Buildings: A BUILDING (4 floors) · B BUILDING (3 floors) · C BUILDING (3 floors)
  • Land: 4,000 sq m (about 1.0 acres) · sanctioned built-up 3,193 sq m · recreational space 404 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of BHAVANA RESIDENCY PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

BHAVANA RESIDENCY PHASE II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about BHAVANA RESIDENCY PHASE II

What is the possession date of BHAVANA RESIDENCY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BHAVANA RESIDENCY PHASE II in Near Z P School, Aurangabad is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for BHAVANA RESIDENCY PHASE II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date BHAVANA RESIDENCY PHASE II's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of BHAVANA RESIDENCY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BHAVANA RESIDENCY PHASE II in Near Z P School, Aurangabad is P51500053426.

Is BHAVANA RESIDENCY PHASE II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANA RESIDENCY PHASE II is registered as P51500053426 and its status is "Registered and active".

What is the construction status of BHAVANA RESIDENCY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANA RESIDENCY PHASE II's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does BHAVANA RESIDENCY PHASE II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is BHAVANA RESIDENCY PHASE II safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANA RESIDENCY PHASE II is registered on MahaRERA as P51500053426, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if BHAVANA RESIDENCY PHASE II's possession date changes?

The latest dates are on BHAVANA RESIDENCY PHASE II's MahaRERA page (P51500053426). GharKundli's Kundli Watch sends a free WhatsApp update on BHAVANA RESIDENCY PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does BHAVANA RESIDENCY PHASE II have?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANA RESIDENCY PHASE II has 3 buildings filed: A BUILDING with 4 floors; B BUILDING with 3 floors; C BUILDING with 3 floors.

How big is the land of BHAVANA RESIDENCY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANA RESIDENCY PHASE II stands on 4,000 sq m of land (about 1.0 acres), with 3,193 sq m of sanctioned built-up area and 404 sq m of recreational open space.

Where can I read reviews of BHAVANA RESIDENCY PHASE II?

Google Maps has reviews of BHAVANA RESIDENCY PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is BHAVANA RESIDENCY PHASE II?

BHAVANA RESIDENCY PHASE II by NEW TRIMURTI DEVELOPERS is in Near Z P School, Aurangabad (pincode 431008), Maharashtra, and is registered on MahaRERA as P51500053426, per GharKundli's check of MahaRERA records.

How many homes are in BHAVANA RESIDENCY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANA RESIDENCY PHASE II has 35 homes in 3 towers registered on MahaRERA.

When was BHAVANA RESIDENCY PHASE II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAVANA RESIDENCY PHASE II was registered on MahaRERA on 31 October 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on BHAVANA RESIDENCY PHASE II?

No court cases are listed for BHAVANA RESIDENCY PHASE II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of BHAVANA RESIDENCY PHASE II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NEW TRIMURTI DEVELOPERS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2029 in Aurangabad →

Other projects in Aurangabad

All 43 projects in Pisadevi (431008) →

Other projects by NEW TRIMURTI DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.