Possession date of Aaditya Luxuria (MahaRERA P51900003845): 29 December 2026, moved from 30 December 2024 (24 months later). It has 48 homes (1 BHK, 2 BHK and 3 BHK, 435–4618 sq ft carpet), 65% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900003845, and currently active.

Source: MahaRERA website — records for P51900003845, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Aaditya Luxuria?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Aaditya Luxuria has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT51900024793)

    Reason the builder gave MahaRERA:
    “Due to amendments in development control regulations, the project had to undergo a transition from DCPR 1991 to DCPR 2034. This migration necessitated several planning changes, which were time consuming and impacted our ability to complete…” Read the full reason“Due to amendments in development control regulations, the project had to undergo a transition from DCPR 1991 to DCPR 2034. This migration necessitated several planning changes, which were time consuming and impacted our ability to complete the project within stipulated time.”
  3. 29 December 2026

    Extended at the builder's request (MahaRERA application EA01092622436)

    Reason the builder gave MahaRERA: “The project has already received Full Occupation Certificate (OC). However, an extension is required only for the purpose of carrying out necessary corrections/updates on the MahaRERA portal”

Source: Aaditya Luxuria’s extension records on MahaRERA (P51900003845), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Aaditya Luxuria

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900003845
Status
Registered and active
Builder
M/S. A.K. DEVELOPERS
Location
Charni road, Mumbai · 400004
Project type
Residential / Group Housing
Registered on
6 Aug 2017
Completion date at registration
December 2024
Latest completion date
December 2026
Delay so far
24 months
Homes
48
Sold or booked
65%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Aaditya Luxuria, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AADITYA LUXURIA100%90%20%0%

Commencement certificate (CC), as filed on MahaRERA

  • AADITYA LUXURIA: covers 27 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aaditya Luxuria every 1–2 months.

Aaditya Luxuria: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK435 – 1,84123
2 BHK806 – 96813
4 BHK1,394 – 1,5019
5 BHK4,6182
1 BHK5291

The builder’s record and reviews

Sanghvi Realty Pivate (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Aaditya Luxuria →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aaditya Luxuria: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aaditya Luxuria

What is the possession date of Aaditya Luxuria?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aaditya Luxuria in Charni road, Mumbai is 29 December 2026 — 24 months later than 30 December 2024, the date given at registration.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Aaditya Luxuria?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aaditya Luxuria's builder has filed on MahaRERA, the official one, is 29 December 2026, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Aaditya Luxuria extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Aaditya Luxuria's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "Due to amendments in development control regulations, the project had to undergo a transition from DCPR 1991 to DCPR 2034. This migration necessitated several planning changes, which were time consuming and impacted our ability to complete the project within stipulated time."; to 29 December 2026, giving the reason "The project has already received Full Occupation Certificate (OC). However, an extension is required only for the purpose of carrying out necessary corrections/updates on the MahaRERA portal".

What is the RERA number of Aaditya Luxuria?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aaditya Luxuria in Charni road, Mumbai is P51900003845.

Is Aaditya Luxuria registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aaditya Luxuria is registered as P51900003845 and its status is "Registered and active".

What is the current construction status of Aaditya Luxuria? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Aaditya Luxuria's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AADITYA LUXURIA is 90% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.

Does Aaditya Luxuria have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Aaditya Luxuria safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Aaditya Luxuria is registered on MahaRERA as P51900003845, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aaditya Luxuria?

Aaditya Luxuria is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Aaditya Luxuria are 435 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Aaditya Luxuria?

For a flat in Aaditya Luxuria (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Aaditya Luxuria received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Aaditya Luxuria is still under construction, with 29 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Aaditya Luxuria uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Aaditya Luxuria was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Aaditya Luxuria's possession date changes?

The latest dates are on Aaditya Luxuria's MahaRERA page (P51900003845). GharKundli's Kundli Watch sends a free WhatsApp update on Aaditya Luxuria every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aaditya Luxuria have?

According to GharKundli's check of MahaRERA records (updated October 2026), Aaditya Luxuria has one building filed: AADITYA LUXURIA with 27 floors and 48 units.

What are the flat sizes (carpet area) in Aaditya Luxuria?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Aaditya Luxuria: 3 BHK: 435 to 1841 sq ft carpet (23 homes); 2 BHK: 806 to 968 sq ft carpet (13 homes); 4 BHK: 1394 to 1501 sq ft carpet (9 homes); 5 BHK: 4618 sq ft carpet (2 homes); 1 BHK: 529 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Aaditya Luxuria?

According to GharKundli's check of MahaRERA records (updated October 2026), Aaditya Luxuria stands on 1,024 sq m of land (about 0.3 acres), with 11,720 sq m of sanctioned built-up area and 374 sq m of recreational open space.

What is the track record of Aaditya Luxuria's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sanghvi Realty Pivate (a group of 2 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Aaditya Luxuria?

Google Maps has reviews of Aaditya Luxuria written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aaditya Luxuria?

Aaditya Luxuria by M/S. A.K. DEVELOPERS is in Charni road, Mumbai, pincode 400004 (near Girgaon, Khetwadi, Grant Road), Maharashtra, and is registered on MahaRERA as P51900003845, per GharKundli's check of MahaRERA records. Its land is filed as 638 &1638. GharKundli lists all 79 MahaRERA projects in Girgaon (400004).

How many flats are in Aaditya Luxuria, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Aaditya Luxuria has 48 homes in 1 tower registered on MahaRERA, and 65% of them are sold or booked.

When was Aaditya Luxuria registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aaditya Luxuria was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.

Does Aaditya Luxuria have any legal issues or court cases?

No court cases are listed for Aaditya Luxuria on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Aaditya Luxuria?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S. A.K. DEVELOPERS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Mumbai City →

Other projects in Girgaon (400004)

All 79 projects in Girgaon (400004) →

Other projects by M/S. A.K. DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.