ONYX
by Naminath Erector and Developers LLP · Prarthana Samaj, Mumbai
Possession date of ONYX: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900046851, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ONYX?
How the possession date of ONYX has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ONYX’s extension records on MahaRERA (P51900046851), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ONYX
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900046851
- Status
- Registered and active
- Builder
- Naminath Erector and Developers LLP
- Location
- Prarthana Samaj, Mumbai · 400004
- Project type
- Residential / Group Housing
- Registered on
- 14 Sep 2022
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 56
- Sold or booked
- 58%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ONYX, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ONYX | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- ONYX: covers 23 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ONYX every month.
ONYX: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 276 – 564 | 56 |
| Shops | 217 | 1 |
- Buildings: ONYX (24 floors, 57 units)
- Land: 689 sq m (about 0.2 acres) · sanctioned built-up 6,055 sq m
- Boundaries filed include: 60ft Vithalbhai Patel Road, Rajaram Mohan Roy Road 90ft
The builder’s record and reviews
Naminath Erector And Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 39 months late). No complaints on MahaRERA.
Read Google reviews of ONYX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ONYX: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ONYX
What is the possession date of ONYX?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ONYX in Prarthana Samaj, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ONYX?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ONYX's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of ONYX?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ONYX in Prarthana Samaj, Mumbai is P51900046851.
Is ONYX registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ONYX is registered as P51900046851 and its status is "Registered and active".
What is the construction status of ONYX?
According to GharKundli's check of MahaRERA records (updated October 2026), ONYX's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ONYX is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does ONYX have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ONYX safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ONYX is registered on MahaRERA as P51900046851, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ONYX's possession date changes?
The latest dates are on ONYX's MahaRERA page (P51900046851). GharKundli's Kundli Watch sends a free WhatsApp update on ONYX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ONYX have?
According to GharKundli's check of MahaRERA records (updated October 2026), ONYX has one building filed: ONYX with 24 floors and 57 units.
What are the flat sizes (carpet area) in ONYX?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ONYX: 1 BHK: 276 to 564 sq ft carpet (56 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of ONYX?
According to GharKundli's check of MahaRERA records (updated October 2026), ONYX stands on 689 sq m of land (about 0.2 acres), with 6,055 sq m of sanctioned built-up area.
What is the track record of ONYX's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Naminath Erector And Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 39 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ONYX?
Google Maps has reviews of ONYX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ONYX?
ONYX by Naminath Erector and Developers LLP is in Prarthana Samaj, Mumbai (pincode 400004), Maharashtra, and is registered on MahaRERA as P51900046851, per GharKundli's check of MahaRERA records. Its boundaries filed there include 60ft Vithalbhai Patel Road, Rajaram Mohan Roy Road 90ft.
How many homes are in ONYX?
According to GharKundli's check of MahaRERA records (updated October 2026), ONYX has 56 homes in 1 tower registered on MahaRERA, and 58% of them are sold or booked.
When was ONYX registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ONYX was registered on MahaRERA on 14 September 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on ONYX?
No court cases are listed for ONYX on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ONYX?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Naminath Erector and Developers LLP.
Check it yourself on MahaRERA
- How to check the possession date of ONYX
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Ward ABCD
- Lifescapes Mirage
- AADITYA LUXURIA
- BURJ ASHRAFI
- Shakuntala Sadan
- AL MEHDI HEIGHTS
- Meadows
- MEHTA SUNSHINE HEIGHTS B WING
- Shapoorji Pallonji The Odyssey 1
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.