AL MEHDI HEIGHTS
by AL HAADI DEVELOPERS · Dongri, MumbaiAlso near Bhuleshwar, Masjid Bunder, Nagpada
Possession date of AL MEHDI HEIGHTS: 31 December 2027, moved from 20 April 2020 (92 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900011681, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about AL MEHDI HEIGHTS?
How the possession date of AL MEHDI HEIGHTS has moved
20 April 2020
Completion date given when the project was registered
20 April 2021
Extended at the builder's request (MahaRERA application EXT51900005700)
Reason the builder gave MahaRERA: “As per attached the application for extension of the mentioned project.”
31 December 2023
Extended at the builder's request (MahaRERA application EXT51900012900)
Reason the builder gave MahaRERA:
“Govt. of Maharashtra (GOM) has increased FSI to compensate real estate loss due to Covid 19. Due to this we have received additional FSI for additional 6 floors approved by Municipal Commissioner. Currently we are under process of getting o…” Read the full reason
“Govt. of Maharashtra (GOM) has increased FSI to compensate real estate loss due to Covid 19. Due to this we have received additional FSI for additional 6 floors approved by Municipal Commissioner. Currently we are under process of getting other statutory approval from the GOM for MOEF and High Rise. However we are under process of getting Part OC.”31 December 2027
Extended at the builder's request (MahaRERA application EA15092638922)
Reason the builder gave MahaRERA: “Project is almost completed will be handed over within a year for this we required 1 more year extension upto 31 Dec 2027 for internal work and infra part.”
Source: AL MEHDI HEIGHTS’s extension records on MahaRERA (P51900011681), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AL MEHDI HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900011681
- Status
- Registered and active
- Builder
- AL HAADI DEVELOPERS
- Location
- Dongri, Mumbai · 400009
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- April 2020
- Latest completion date
- December 2027
- Delay so far
- 92 months
- Homes
- 150
- Sold or booked
- 81%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of AL MEHDI HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AL MEHDI HEIGHTS | 100% | 90% | 80% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- AL MEHDI HEIGHTS: covers 45 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AL MEHDI HEIGHTS every month.
AL MEHDI HEIGHTS: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 409 – 453 | 144 |
| 2 BHK | 586 – 636 | 6 |
- Buildings: AL MEHDI HEIGHTS (48 floors, 150 units)
- Land: 1,370 sq m (about 0.3 acres) · sanctioned built-up 10,906 sq m · recreational space 407 sq m
- Boundaries filed include: SVP ROAD, 2ND FLANK ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of AL MEHDI HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AL MEHDI HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AL MEHDI HEIGHTS
What is the possession date of AL MEHDI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AL MEHDI HEIGHTS in Dongri, Mumbai is 31 December 2027 — 92 months later than 20 April 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for AL MEHDI HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AL MEHDI HEIGHTS's builder has filed on MahaRERA, the official one, is 31 December 2027, already 92 months later than the 20 April 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AL MEHDI HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), AL MEHDI HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 20 April 2021, giving the reason "As per attached the application for extension of the mentioned project."; to 31 December 2023, giving the reason "Govt. of Maharashtra (GOM) has increased FSI to compensate real estate loss due to Covid 19. Due to this we have received additional FSI for additional 6 floors approved by Municipal Commissioner. Currently we are under process of getting other statutory approval from the GOM for MOEF and High Rise. However we are under process of getting Part OC."; to 31 December 2027, giving the reason "Project is almost completed will be handed over within a year for this we required 1 more year extension upto 31 Dec 2027 for internal work and infra part.".
What is the RERA number of AL MEHDI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AL MEHDI HEIGHTS in Dongri, Mumbai is P51900011681.
Is AL MEHDI HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AL MEHDI HEIGHTS is registered as P51900011681 and its status is "Registered and active".
What is the construction status of AL MEHDI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), AL MEHDI HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AL MEHDI HEIGHTS is 90% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does AL MEHDI HEIGHTS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is AL MEHDI HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), AL MEHDI HEIGHTS is registered on MahaRERA as P51900011681, its completion date has moved 92 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AL MEHDI HEIGHTS's possession date changes?
The latest dates are on AL MEHDI HEIGHTS's MahaRERA page (P51900011681). GharKundli's Kundli Watch sends a free WhatsApp update on AL MEHDI HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AL MEHDI HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), AL MEHDI HEIGHTS has one building filed: AL MEHDI HEIGHTS with 48 floors and 150 units.
What are the flat sizes (carpet area) in AL MEHDI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for AL MEHDI HEIGHTS: 1 BHK: 409 to 453 sq ft carpet (144 homes); 2 BHK: 586 to 636 sq ft carpet (6 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of AL MEHDI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), AL MEHDI HEIGHTS stands on 1,370 sq m of land (about 0.3 acres), with 10,906 sq m of sanctioned built-up area and 407 sq m of recreational open space.
Where can I read reviews of AL MEHDI HEIGHTS?
Google Maps has reviews of AL MEHDI HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AL MEHDI HEIGHTS?
AL MEHDI HEIGHTS by AL HAADI DEVELOPERS is in Dongri, Mumbai (pincode 400009), near Bhuleshwar, Masjid Bunder, Nagpada, Maharashtra, and is registered on MahaRERA as P51900011681, per GharKundli's check of MahaRERA records. Its boundaries filed there include SVP ROAD, 2ND FLANK ROAD.
How many homes are in AL MEHDI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), AL MEHDI HEIGHTS has 150 homes in 1 tower registered on MahaRERA, and 81% of them are sold or booked.
When was AL MEHDI HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AL MEHDI HEIGHTS was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on AL MEHDI HEIGHTS?
No court cases are listed for AL MEHDI HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AL MEHDI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AL HAADI DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of AL MEHDI HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Ward ABCD
- AADITYA LUXURIA
- BURJ ASHRAFI
- Shakuntala Sadan
- Meadows
- MEHTA SUNSHINE HEIGHTS B WING
- Shapoorji Pallonji The Odyssey 1
- ONYX
- DREAM RESIDENCY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.