Lifescapes Mirage
by Rohan Developers Pvt. Ltd. · Prarthana Samaj, Mumbai
Possession: Lifescapes Mirage is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900001725. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Lifescapes Mirage?
How the possession date of Lifescapes Mirage has moved
31 December 2017
Completion date given when the project was registered
31 March 2018
Extended at the builder's request (MahaRERA application EXT51900000015)
Reason the builder gave MahaRERA:
“Project is complete in all regards with Occupation Certificate of entire building excluding 2 flats on the topmost floor of sale portion, due to compliance issues. However, the 2 flats mentioned have not been sold/allotted to anyone as on d…” Read the full reason
“Project is complete in all regards with Occupation Certificate of entire building excluding 2 flats on the topmost floor of sale portion, due to compliance issues. However, the 2 flats mentioned have not been sold/allotted to anyone as on date. The full O.C. for the building will be acquired at the earliest.”
Source: Lifescapes Mirage’s extension records on MahaRERA (P51900001725), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Lifescapes Mirage
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints and 3 court cases, and how it ended
- Construction pace against the March 2018 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900001725
- Status
- Completed
- Builder
- Rohan Developers Pvt. Ltd.
- Location
- Prarthana Samaj, Mumbai · 400016
- Project type
- Residential / Group Housing
- Registered on
- 29 Jul 2017
- Completion date at registration
- December 2017
- Latest completion date
- March 2018
- Delay so far
- 3 months
- Homes
- 37
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Lifescapes Mirage, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Lifescapes Mirage | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lifescapes Mirage every month.
Lifescapes Mirage: buildings, flats and land, as filed on MahaRERA
- Buildings: Lifescapes Mirage (26 floors)
- Land: 1,335 sq m (about 0.3 acres) · sanctioned built-up 5,153 sq m · recreational space 93 sq m
The builder’s record and reviews
Rohan Developers (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 18 months); 3 lapsed. 26 complaints on MahaRERA across 4 projects.
Read Google reviews of Lifescapes Mirage →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Lifescapes Mirage: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Lifescapes Mirage
What is the possession date of Lifescapes Mirage?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Lifescapes Mirage in Prarthana Samaj, Mumbai is 31 March 2018 — 3 months later than 31 December 2017, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Lifescapes Mirage?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Lifescapes Mirage's builder has filed on MahaRERA, the official one, is 31 March 2018, already 3 months later than the 31 December 2017 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Lifescapes Mirage extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Lifescapes Mirage's builder applied to MahaRERA to extend the completion date once: to 31 March 2018, giving the reason "Project is complete in all regards with Occupation Certificate of entire building excluding 2 flats on the topmost floor of sale portion, due to compliance issues. However, the 2 flats mentioned have not been sold/allotted to anyone as on date. The full O.C. for the building will be acquired at the earliest.".
What is the RERA number of Lifescapes Mirage?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Lifescapes Mirage in Prarthana Samaj, Mumbai is P51900001725.
Is Lifescapes Mirage registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Lifescapes Mirage is registered as P51900001725 and its status is "Completed".
What is the construction status of Lifescapes Mirage?
According to GharKundli's check of MahaRERA records (updated November 2026), Lifescapes Mirage's status on MahaRERA is "Completed". As filed by the builder, slab work on Lifescapes Mirage is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Lifescapes Mirage have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Lifescapes Mirage safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Lifescapes Mirage is registered on MahaRERA as P51900001725, its MahaRERA status is "Completed", its completion date has moved 3 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Lifescapes Mirage's possession date changes?
The latest dates are on Lifescapes Mirage's MahaRERA page (P51900001725). GharKundli's Kundli Watch sends a free WhatsApp update on Lifescapes Mirage every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Lifescapes Mirage have?
According to GharKundli's check of MahaRERA records (updated November 2026), Lifescapes Mirage has one building filed: Lifescapes Mirage with 26 floors.
How big is the land of Lifescapes Mirage?
According to GharKundli's check of MahaRERA records (updated November 2026), Lifescapes Mirage stands on 1,335 sq m of land (about 0.3 acres), with 5,153 sq m of sanctioned built-up area and 93 sq m of recreational open space.
What is the track record of Lifescapes Mirage's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Rohan Developers (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 18 months); 3 lapsed. 26 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Lifescapes Mirage?
Google Maps has reviews of Lifescapes Mirage written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Lifescapes Mirage?
Lifescapes Mirage by Rohan Developers Pvt. Ltd. is in Prarthana Samaj, Mumbai (pincode 400016), Maharashtra, and is registered on MahaRERA as P51900001725, per GharKundli's check of MahaRERA records.
How many homes are in Lifescapes Mirage?
According to GharKundli's check of MahaRERA records (updated November 2026), Lifescapes Mirage has 37 homes in 1 tower registered on MahaRERA.
When was Lifescapes Mirage registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Lifescapes Mirage was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Lifescapes Mirage?
3 court cases are listed for Lifescapes Mirage on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Lifescapes Mirage?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Rohan Developers Pvt. Ltd., which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Lifescapes Mirage
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ward GNorth
All 83 projects in Mahim (400016) →Other projects by Rohan Developers Pvt. Ltd.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.