Skip to content
GharKundli

Bafna Anmol Nayantara Empire

by Bafna Builders and Land Developers · Sambhaji Chowk, Nashik 422002Registered on MahaRERA as “Anmol Nayantara Empire”

What’s in the report? →

Possession: Bafna Anmol Nayantara Empire (MahaRERA P51600001304) is marked completed on MahaRERA. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600001304. Status: Completed.

Source: MahaRERA website — records for P51600001304, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Bafna Anmol Nayantara Empire?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Bafna Anmol Nayantara Empire has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2019

    Extended at the builder's request (MahaRERA application EXT51600001028)

    Reason the builder gave MahaRERA:
    “• The Project Anmol Nayantara Empire comprising 4 buildings, Clubhouse and Multi-purpose Hall along with basic infrastructure is virtually completed. • Total Handover are 65 / 80 as of December 2018. • Total Occupants Residing 41 Nos as of…” Read the full reason“• The Project Anmol Nayantara Empire comprising 4 buildings, Clubhouse and Multi-purpose Hall along with basic infrastructure is virtually completed. • Total Handover are 65 / 80 as of December 2018. • Total Occupants Residing 41 Nos as of December 2018 • Nashik Municipal Corporation has granted appropriate water supply Connection based on occupied number of premises. • MSEDCL has also provided residential meter to common areas and individual. • All other basic infrastructure is in place and being augmented on the basis of physical occupation of the customer. • Bafna Builders and Land Devel…”

Source: Bafna Anmol Nayantara Empire’s extension records on MahaRERA (P51600001304), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Bafna Anmol Nayantara Empire

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600001304
Status
Completed
Builder
Bafna Builders and Land Developers
Location
Sambhaji Chowk, Nashik · 422002
Project type
Residential / Group Housing
Registered on
27 Jul 2017
Completion date at registration
December 2018
Latest completion date
December 2019
Delay so far
12 months
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Bafna Anmol Nayantara Empire, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A wing0%100%100%100%
B Wing0%100%100%100%
C Wing0%100%100%100%
D Wing0%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bafna Anmol Nayantara Empire every 1–2 months.

Bafna Anmol Nayantara Empire: buildings, flats and land, as filed on MahaRERA

  • Buildings: A wing (12 floors) · B Wing (12 floors) · C Wing (12 floors) · D Wing (12 floors)
  • Land: 8,166 sq m (about 2.0 acres) · sanctioned built-up 8,063 sq m · recreational space 958 sq m
  • Land, as filed: 747/1 2 748/a/ 1 2 749 p.no 40,111 to 115,116a,116b fpno.529
  • Map: Get directions

The builder’s record and reviews

Bafna Builders And Land Developers (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 finished, 1 within the promised date and 3 needed more time (typically 12 months). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Bafna Anmol Nayantara Empire →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Bafna Anmol Nayantara Empire: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Bafna Anmol Nayantara Empire

What is the possession date of Bafna Anmol Nayantara Empire?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Bafna Anmol Nayantara Empire in Sambhaji Chowk, Nashik is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Bafna Anmol Nayantara Empire?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Bafna Anmol Nayantara Empire's builder has filed on MahaRERA, the official one, is 31 December 2019, already 12 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Bafna Anmol Nayantara Empire extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Bafna Anmol Nayantara Empire's builder applied to MahaRERA to extend the completion date once: to 31 December 2019, giving the reason "• The Project Anmol Nayantara Empire comprising 4 buildings, Clubhouse and Multi-purpose Hall along with basic infrastructure is virtually completed. • Total Handover are 65 / 80 as of December 2018. • Total Occupants Residing 41 Nos as of December 2018 • Nashik Municipal Corporation has granted appropriate water supply Connection based on occupied number of premises. • MSEDCL has also provided residential meter to common areas and individual. • All other basic infrastructure is in place and being augmented on the basis of physical occupation of the customer. • Bafna Builders and Land Devel…".

What is the RERA number of Bafna Anmol Nayantara Empire?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Bafna Anmol Nayantara Empire in Sambhaji Chowk, Nashik is P51600001304.

Is Bafna Anmol Nayantara Empire registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Bafna Anmol Nayantara Empire is registered as P51600001304 and its status is "Completed".

What is the current construction status of Bafna Anmol Nayantara Empire? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Bafna Anmol Nayantara Empire's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Bafna Anmol Nayantara Empire have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Bafna Anmol Nayantara Empire safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Bafna Anmol Nayantara Empire is registered on MahaRERA as P51600001304, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Bafna Anmol Nayantara Empire?

According to GharKundli's check of MahaRERA records (updated November 2026), Bafna Anmol Nayantara Empire is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Bafna Anmol Nayantara Empire?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Bafna Anmol Nayantara Empire: gharkundli.com/tools/property-cost-calculator

Has Bafna Anmol Nayantara Empire received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Bafna Anmol Nayantara Empire is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Bafna Anmol Nayantara Empire completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Bafna Anmol Nayantara Empire is marked completed on MahaRERA, and the completion date filed there is 31 December 2019. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Bafna Anmol Nayantara Empire uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Bafna Anmol Nayantara Empire was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Bafna Anmol Nayantara Empire's possession date changes?

The latest dates are on Bafna Anmol Nayantara Empire's MahaRERA page (P51600001304). GharKundli's Kundli Watch sends a free WhatsApp update on Bafna Anmol Nayantara Empire every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Bafna Anmol Nayantara Empire have?

According to GharKundli's check of MahaRERA records (updated November 2026), Bafna Anmol Nayantara Empire has 4 buildings filed: A wing with 12 floors; B Wing with 12 floors; C Wing with 12 floors; D Wing with 12 floors.

How big is the land of Bafna Anmol Nayantara Empire?

According to GharKundli's check of MahaRERA records (updated November 2026), Bafna Anmol Nayantara Empire stands on 8,166 sq m of land (about 2.0 acres), with 8,063 sq m of sanctioned built-up area and 958 sq m of recreational open space.

What is the track record of Bafna Anmol Nayantara Empire's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Bafna Builders And Land Developers (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 4 finished, 1 within the promised date and 3 needed more time (typically 12 months). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Bafna Anmol Nayantara Empire?

Google Maps has reviews of Bafna Anmol Nayantara Empire written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Bafna Anmol Nayantara Empire?

Bafna Anmol Nayantara Empire by Bafna Builders and Land Developers is in Sambhaji Chowk, Nashik, pincode 422002, Maharashtra, and is registered on MahaRERA as P51600001304, per GharKundli's check of MahaRERA records. Its land is filed as 747/1 2 748/a/ 1 2 749 p.no 40,111 to 115,116a,116b fpno.529. GharKundli lists all 117 MahaRERA projects in Gole Colony (422002).

When was Bafna Anmol Nayantara Empire registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Bafna Anmol Nayantara Empire was registered on MahaRERA on 27 July 2017. GharKundli did not find a title report on the land on file there.

Does Bafna Anmol Nayantara Empire have any legal issues or court cases?

No court cases are listed for Bafna Anmol Nayantara Empire on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Bafna Anmol Nayantara Empire?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Bafna Builders and Land Developers, which has 1 other project registered on MahaRERA.

Other projects in Gole Colony (422002)

All 117 projects in Gole Colony (422002) →

Other projects by Bafna Builders and Land Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.