Jaikumar Parksyde Homes Phase 5A

by Jaikumar Constructions LLP · Hanuman Nagar, Nashik 422002Also near Panchavati, Dwarka, IndiranagarRegistered on MahaRERA as “Parksyde Homes Phase 5A”

What’s in the report? →

Possession: Jaikumar Parksyde Homes Phase 5A (MahaRERA P51600004799) is marked completed on MahaRERA. It has 420 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600004799. Status: Completed.

Source: MahaRERA website — records for P51600004799, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Jaikumar Parksyde Homes Phase 5A?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Jaikumar Parksyde Homes Phase 5A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51600004799
Status
Completed
Builder
Jaikumar Constructions LLP
Location
Hanuman Nagar, Nashik · 422002
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
June 2025
Latest completion date
June 2025
Homes
420
Towers
7
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Jaikumar Parksyde Homes Phase 5A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
M1100%100%100%100%
M2100%100%100%100%
M3100%100%100%100%
M4100%100%100%100%
M5100%100%100%100%
M6100%100%100%100%
L100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Jaikumar Parksyde Homes Phase 5A every 1–2 months.

Jaikumar Parksyde Homes Phase 5A: buildings, flats and land, as filed on MahaRERA

  • Buildings: M1 (18 floors) · M2 (21 floors) · M3 (21 floors) · M4 (21 floors) · M5 (21 floors) · M6 (21 floors) · L (18 floors)
  • Land: 21,758 sq m (about 5.4 acres) · sanctioned built-up 35,169 sq m · recreational space 2,176 sq m
  • Land, as filed: S NO 256 PART AND 257 PART
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Jaikumar Constructions (a group of 4 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 11 finished, all within the promised date; 5 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Jaikumar Parksyde Homes Phase 5A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Jaikumar Parksyde Homes Phase 5A: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Jaikumar Parksyde Homes Phase 5A

What is the possession date of Jaikumar Parksyde Homes Phase 5A?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Jaikumar Parksyde Homes Phase 5A in Hanuman Nagar, Nashik is 30 June 2025.

Is the builder's possession date different from the MahaRERA date for Jaikumar Parksyde Homes Phase 5A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Jaikumar Parksyde Homes Phase 5A's builder has filed on MahaRERA, the official one, is 30 June 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Jaikumar Parksyde Homes Phase 5A?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Jaikumar Parksyde Homes Phase 5A in Hanuman Nagar, Nashik is P51600004799.

Is Jaikumar Parksyde Homes Phase 5A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaikumar Parksyde Homes Phase 5A is registered as P51600004799 and its status is "Completed".

What is the current construction status of Jaikumar Parksyde Homes Phase 5A? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaikumar Parksyde Homes Phase 5A's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 7 towers. GharKundli's full report compares construction progress with the deadline.

Does Jaikumar Parksyde Homes Phase 5A have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Jaikumar Parksyde Homes Phase 5A safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaikumar Parksyde Homes Phase 5A is registered on MahaRERA as P51600004799, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Jaikumar Parksyde Homes Phase 5A?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaikumar Parksyde Homes Phase 5A is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Jaikumar Parksyde Homes Phase 5A?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Jaikumar Parksyde Homes Phase 5A: gharkundli.com/tools/property-cost-calculator

Has Jaikumar Parksyde Homes Phase 5A received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaikumar Parksyde Homes Phase 5A is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Jaikumar Parksyde Homes Phase 5A completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaikumar Parksyde Homes Phase 5A is marked completed on MahaRERA, and the completion date filed there is 30 June 2025. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Jaikumar Parksyde Homes Phase 5A uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Jaikumar Parksyde Homes Phase 5A was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Jaikumar Parksyde Homes Phase 5A have other wings or phases?

Yes. MahaRERA lists 5 other registrations of the same project, each with its own possession date: Parksyde Homes Phase 1 (P51600002640, possession 30 Jun 2018); Parksyde Homes Phase 2A (P51600009429, possession 30 Jul 2020); Parksyde Homes Phase 2B (P51600002975, possession 30 Jul 2020); Parksyde Homes Phase 3 (P51600003548, possession 30 Jun 2022); Parksyde Homes Phase 4B (P51600004804, possession 31 Oct 2019). Check that your agreement names the registration of your own wing.

How can I get updates if Jaikumar Parksyde Homes Phase 5A's possession date changes?

The latest dates are on Jaikumar Parksyde Homes Phase 5A's MahaRERA page (P51600004799). GharKundli's Kundli Watch sends a free WhatsApp update on Jaikumar Parksyde Homes Phase 5A every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Jaikumar Parksyde Homes Phase 5A have?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaikumar Parksyde Homes Phase 5A has 7 buildings filed: M1 with 18 floors; M2 with 21 floors; M3 with 21 floors; M4 with 21 floors; M5 with 21 floors; M6 with 21 floors; and 1 more.

How big is the land of Jaikumar Parksyde Homes Phase 5A?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaikumar Parksyde Homes Phase 5A stands on 21,758 sq m of land (about 5.4 acres), with 35,169 sq m of sanctioned built-up area and 2,176 sq m of recreational open space.

What is the track record of Jaikumar Parksyde Homes Phase 5A's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaikumar Constructions (a group of 4 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 11 finished, all within the promised date; 5 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Jaikumar Parksyde Homes Phase 5A?

Google Maps has reviews of Jaikumar Parksyde Homes Phase 5A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Jaikumar Parksyde Homes Phase 5A?

Jaikumar Parksyde Homes Phase 5A by Jaikumar Constructions LLP is in Hanuman Nagar, Nashik, pincode 422002 (near Panchavati, Dwarka, Indiranagar), Maharashtra, and is registered on MahaRERA as P51600004799, per GharKundli's check of MahaRERA records. Its land is filed as S NO 256 PART AND 257 PART. GharKundli lists all 117 MahaRERA projects in Gole Colony (422002).

How many flats are in Jaikumar Parksyde Homes Phase 5A?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaikumar Parksyde Homes Phase 5A has 420 homes in 7 towers registered on MahaRERA.

When was Jaikumar Parksyde Homes Phase 5A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaikumar Parksyde Homes Phase 5A was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Does Jaikumar Parksyde Homes Phase 5A have any legal issues or court cases?

No court cases are listed for Jaikumar Parksyde Homes Phase 5A on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Jaikumar Parksyde Homes Phase 5A?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Jaikumar Constructions LLP, which has 6 other projects registered on MahaRERA.

Other projects in Gole Colony (422002)

All 117 projects in Gole Colony (422002) →

Other projects by Jaikumar Constructions LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.