SHREE SANKET EMPIRE
by SHREE SANKET DEVELOPERS · Malegaon, Nashik
Possession: SHREE SANKET EMPIRE is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600007618. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SHREE SANKET EMPIRE?
How the possession date of SHREE SANKET EMPIRE has moved
31 December 2017
Completion date given when the project was registered
31 December 2018
Extended at the builder's request (MahaRERA application EXT51600000172)
Reason the builder gave MahaRERA: “Construction activity has not been completed due to non-availability of material issue.”
31 March 2024
Extended at the builder's request (MahaRERA application EXT51600016959)
Reason the builder gave MahaRERA: “WE HAVE APPLIED FOR OCCUPANCY CERTIFICATE TO LOCAL PLANNING AUTHORITY WITHIN DUE DATE. HOWEVER, WE DID NOT RECEIVE COPY OF COMPLETION CERTIFICATE FROM LOCAL PLANNING AUTHORITY IN DUE TIME. HENCE, WE ARE APPLYING FOR EXTENTION”
Source: SHREE SANKET EMPIRE’s extension records on MahaRERA (P51600007618), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHREE SANKET EMPIRE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the March 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600007618
- Status
- Completed
- Builder
- SHREE SANKET DEVELOPERS
- Location
- Malegaon, Nashik · 423203
- Project type
- Commercial
- Registered on
- 17 Aug 2017
- Completion date at registration
- December 2017
- Latest completion date
- March 2024
- Delay so far
- 75 months
- Homes
- 105
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of SHREE SANKET EMPIRE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHREE SANKET EMPIRE | 100% | 100% | 100% | 100% |
| SHREE SANKET EMPIRE | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE SANKET EMPIRE every month.
SHREE SANKET EMPIRE: buildings, flats and land, as filed on MahaRERA
- Buildings: SHREE SANKET EMPIRE (6 floors) · SHREE SANKET EMPIRE (6 floors)
- Land: 1,948 sq m (about 0.5 acres) · sanctioned built-up 1,946 sq m
The builder’s record and reviews
Shree Sanket Developers (a group of 2 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 6 finished, 1 within the promised date and 5 needed more time (typically 14 months); 1 still being built, 1 past the promised date (typically 2 months late). No complaints on MahaRERA.
Read Google reviews of SHREE SANKET EMPIRE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHREE SANKET EMPIRE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHREE SANKET EMPIRE
What is the possession date of SHREE SANKET EMPIRE?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHREE SANKET EMPIRE in Malegaon, Nashik is 31 March 2024 — 75 months later than 31 December 2017, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SHREE SANKET EMPIRE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE SANKET EMPIRE's builder has filed on MahaRERA, the official one, is 31 March 2024, already 75 months later than the 31 December 2017 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHREE SANKET EMPIRE extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SANKET EMPIRE's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2018, giving the reason "Construction activity has not been completed due to non-availability of material issue."; to 31 March 2024, giving the reason "WE HAVE APPLIED FOR OCCUPANCY CERTIFICATE TO LOCAL PLANNING AUTHORITY WITHIN DUE DATE. HOWEVER, WE DID NOT RECEIVE COPY OF COMPLETION CERTIFICATE FROM LOCAL PLANNING AUTHORITY IN DUE TIME. HENCE, WE ARE APPLYING FOR EXTENTION".
What is the RERA number of SHREE SANKET EMPIRE?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHREE SANKET EMPIRE in Malegaon, Nashik is P51600007618.
Is SHREE SANKET EMPIRE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SANKET EMPIRE is registered as P51600007618 and its status is "Completed".
What is the construction status of SHREE SANKET EMPIRE?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SANKET EMPIRE's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does SHREE SANKET EMPIRE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SHREE SANKET EMPIRE safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SANKET EMPIRE is registered on MahaRERA as P51600007618, its MahaRERA status is "Completed", its completion date has moved 75 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHREE SANKET EMPIRE's possession date changes?
The latest dates are on SHREE SANKET EMPIRE's MahaRERA page (P51600007618). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE SANKET EMPIRE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHREE SANKET EMPIRE have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SANKET EMPIRE has 2 buildings filed: SHREE SANKET EMPIRE with 6 floors; SHREE SANKET EMPIRE with 6 floors.
How big is the land of SHREE SANKET EMPIRE?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SANKET EMPIRE stands on 1,948 sq m of land (about 0.5 acres), with 1,946 sq m of sanctioned built-up area.
What is the track record of SHREE SANKET EMPIRE's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Sanket Developers (a group of 2 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 6 finished, 1 within the promised date and 5 needed more time (typically 14 months); 1 still being built, 1 past the promised date (typically 2 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHREE SANKET EMPIRE?
Google Maps has reviews of SHREE SANKET EMPIRE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHREE SANKET EMPIRE?
SHREE SANKET EMPIRE by SHREE SANKET DEVELOPERS is in Malegaon, Nashik (pincode 423203), Maharashtra, and is registered on MahaRERA as P51600007618, per GharKundli's check of MahaRERA records.
How many homes are in SHREE SANKET EMPIRE?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SANKET EMPIRE has 105 homes in 2 towers registered on MahaRERA.
When was SHREE SANKET EMPIRE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE SANKET EMPIRE was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SHREE SANKET EMPIRE?
1 court case is listed for SHREE SANKET EMPIRE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SHREE SANKET EMPIRE?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE SANKET DEVELOPERS, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHREE SANKET EMPIRE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 423203
All 7 projects in Malegaon (423203) →Other projects by SHREE SANKET DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.