A. H. Heights
by A.H. Constructions · Jogeshwari West, MumbaiAlso near Andheri West, Oshiwara, Jogeshwari East
Possession date of A. H. Heights: 30 April 2028, moved from 16 August 2022 (64 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800012784, and currently active. Its completion date has moved from August 2022 to April 2028: 64 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about A. H. Heights?
How the possession date of A. H. Heights has moved
16 August 2022
Completion date given when the project was registered
30 December 2024
Extended at the builder's request (MahaRERA application EXT51800012542)
Reason the builder gave MahaRERA:
“We have a total of 86 apartments, out of that 24 apartments are sold and 62 apartments are unsold which needs to be sold but without the Extension Number we are unable to sell those apartments. Hence we are making this application for Proje…” Read the full reason
“We have a total of 86 apartments, out of that 24 apartments are sold and 62 apartments are unsold which needs to be sold but without the Extension Number we are unable to sell those apartments. Hence we are making this application for Project Extension. We request you to give extension for our project till 30th December 2024.”29 December 2025
Extended at the builder's request (MahaRERA application EXT51800027108)
Reason the builder gave MahaRERA:
“3. Obstruction Due to Government Construction Activities: Furthermore, during the course of the construction project, an additional external factor beyond the control of the Contractor has contributed to the delay. Specifically, the Governm…” Read the full reason
“3. Obstruction Due to Government Construction Activities: Furthermore, during the course of the construction project, an additional external factor beyond the control of the Contractor has contributed to the delay. Specifically, the Government undertook a significant infrastructure project involving the construction of Road. The execution of this public works project has resulted in an obstruction to the transportation of construction materials to the project site. The primary access road to the construction site is now blocked and it is inaccessible due to the ongoing government road const…”31 December 2027
Extended at the builder's request (MahaRERA application EA02052620806)
Reason the builder gave MahaRERA:
“1. The project stands at 90% completion. 2. The consent of 55.32% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The…” Read the full reason
“1. The project stands at 90% completion. 2. The consent of 55.32% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons: a) Metro Construction Impact: Nearby metro station work caused access restrictions and logistical issues, delaying movement of materials, labour, and equipment. b) Government Road Work Obstruction: Ongoing road construction blocked site access, affecting material supply and project progress. c) Pandemic & Cost…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: A. H. Heights’s extension records on MahaRERA (P51800012784), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on A. H. Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800012784
- Status
- Registered and active
- Builder
- A.H. Constructions
- Location
- Jogeshwari West, Mumbai · 400102
- Project type
- Residential / Group Housing
- Registered on
- 7 Sep 2017
- Completion date at registration
- August 2022
- Latest completion date
- April 2028
- Delay so far
- 64 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 88
- Sold or booked
- 66%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of A. H. Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A H Heights | 100% | 92% | 91% | 97% |
Commencement certificate (CC), as filed on MahaRERA
- A H Heights: covers 20 Floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on A. H. Heights every month.
A. H. Heights: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 734 – 1,207 | 65 |
| 3 BHK | 1,207 | 23 |
- Buildings: A H Heights (34 floors, 88 units)
- Land: 3,000 sq m (about 0.7 acres) · sanctioned built-up 6,340 sq m · recreational space 1,424 sq m
- Boundaries filed include: Millat High School
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
A H Constructions has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 26 months late). 2 complaints on MahaRERA across 2 projects.
Read Google reviews of A. H. Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
A. H. Heights: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about A. H. Heights
What is the possession date of A. H. Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for A. H. Heights in Jogeshwari West, Mumbai is 30 April 2028 — 64 months later than 16 August 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for A. H. Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date A. H. Heights's builder has filed on MahaRERA, the official one, is 30 April 2028, already 64 months later than the 16 August 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of A. H. Heights extended?
According to GharKundli's check of MahaRERA records (updated October 2026), A. H. Heights's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2024, giving the reason "We have a total of 86 apartments, out of that 24 apartments are sold and 62 apartments are unsold which needs to be sold but without the Extension Number we are unable to sell those apartments. Hence we are making this application for Project Extension. We request you to give extension for our project till 30th December 2024."; to 29 December 2025, giving the reason "3. Obstruction Due to Government Construction Activities: Furthermore, during the course of the construction project, an additional external factor beyond the control of the Contractor has contributed to the delay. Specifically, the Government undertook a significant infrastructure project involving the construction of Road. The execution of this public works project has resulted in an obstruction to the transportation of construction materials to the project site. The primary access road to the construction site is now blocked and it is inaccessible due to the ongoing government road const…"; to 31 December 2027, giving the reason "1. The project stands at 90% completion. 2. The consent of 55.32% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons: a) Metro Construction Impact: Nearby metro station work caused access restrictions and logistical issues, delaying movement of materials, labour, and equipment. b) Government Road Work Obstruction: Ongoing road construction blocked site access, affecting material supply and project progress. c) Pandemic & Cost…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of A. H. Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of A. H. Heights in Jogeshwari West, Mumbai is P51800012784.
Is A. H. Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), A. H. Heights is registered as P51800012784 and its status is "Registered and active".
What is the construction status of A. H. Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), A. H. Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A H Heights is 92% done and internal work 91%. GharKundli's full report compares construction progress with the deadline.
Does A. H. Heights have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is A. H. Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), A. H. Heights is registered on MahaRERA as P51800012784, its completion date has moved 64 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if A. H. Heights's possession date changes?
The latest dates are on A. H. Heights's MahaRERA page (P51800012784). GharKundli's Kundli Watch sends a free WhatsApp update on A. H. Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does A. H. Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), A. H. Heights has one building filed: A H Heights with 34 floors and 88 units.
What are the flat sizes (carpet area) in A. H. Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for A. H. Heights: 2 BHK: 734 to 1207 sq ft carpet (65 homes); 3 BHK: 1207 sq ft carpet (23 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of A. H. Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), A. H. Heights stands on 3,000 sq m of land (about 0.7 acres), with 6,340 sq m of sanctioned built-up area and 1,424 sq m of recreational open space.
What is the track record of A. H. Heights's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), A H Constructions has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 26 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of A. H. Heights?
Google Maps has reviews of A. H. Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is A. H. Heights?
A. H. Heights by A.H. Constructions is in Jogeshwari West, Mumbai (pincode 400102), near Andheri West, Oshiwara, Jogeshwari East, Maharashtra, and is registered on MahaRERA as P51800012784, per GharKundli's check of MahaRERA records. Its boundaries filed there include Millat High School.
How many homes are in A. H. Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), A. H. Heights has 88 homes in 1 tower registered on MahaRERA, and 66% of them are sold or booked.
When was A. H. Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), A. H. Heights was registered on MahaRERA on 7 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on A. H. Heights?
No court cases are listed for A. H. Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of A. H. Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is A.H. Constructions, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of A. H. Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400102
- Arkan
- 24 Karat
- ESQUINA PRIVATE RESIDENCE
- Live Well Chs Ltd
- Infra - Azura Height
- Gurukrupa Ekam
- Ozone Avenue
- Lotus Sky Plaza
Other projects by A.H. Constructions
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.