Crystal Vue
by Nageshwar V Neela · Sion Koliwada, Mumbai 400037
What’s in the report? →Possession date of Crystal Vue (MahaRERA P51900006774): 30 December 2027, moved from 30 December 2025 (24 months later). It has 45 homes (3 BHK, 4 BHK and 5 BHK, 980–1893 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900006774, and currently active.
Source: MahaRERA website — records for P51900006774, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Crystal Vue?
6 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Crystal Vue has moved
30 December 2025
Completion date given when the project was registered
30 December 2027
Extended at the builder's request (MahaRERA application EXT51900012780)
Reason the builder gave MahaRERA:
“The Developer was in process of commencing the development of the said project, however, due to the worldwide lockdown caused due to the COVID-19 pandemic, the Developer could not implement the timeline as decided. Thus, the Project was nev…” Read the full reason
“The Developer was in process of commencing the development of the said project, however, due to the worldwide lockdown caused due to the COVID-19 pandemic, the Developer could not implement the timeline as decided. Thus, the Project was never started nor did the Developer sell any Units/ Apartment in the said Project. The Developer is in the process of starting the construction now, thus, the Developer is seeking extension of time for Project Completion till 30th December, 2027 from 30th December, 2025.”
Source: Crystal Vue’s extension records on MahaRERA (P51900006774), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Crystal Vue
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 court cases, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900006774
- Status
- Registered and active
- Builder
- Nageshwar V Neela
- Location
- Sion Koliwada, Mumbai · 400037
- Project type
- Residential / Group Housing
- Registered on
- 16 Aug 2017
- Completion date at registration
- December 2025
- Latest completion date
- December 2027
- Delay so far
- 24 months
- Homes
- 45
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 6
- Title report on file
- Not found
Construction progress of Crystal Vue, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Vue | 100% | 68% | 18% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Vue: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Crystal Vue every 1–2 months.
Crystal Vue: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 4 BHK | 1,463 | 19 |
| 3 BHK | 980 – 1,893 | 18 |
| 5 BHK | 1,893 | 8 |
- Buildings: Vue (37 floors, 45 units)
- Car parking: 72 covered
- Land: 1,861 sq m (about 0.5 acres) · sanctioned built-up 7,326 sq m · recreational space 420 sq m
- Boundaries filed include: Harbhansalal Marg
- Land, as filed: 2pt,89pt
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Crystal Vue →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Crystal Vue: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Crystal Vue
What is the possession date of Crystal Vue?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Crystal Vue in Sion Koliwada, Mumbai is 30 December 2027 — 24 months later than 30 December 2025, the date given at registration.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Crystal Vue?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Crystal Vue's builder has filed on MahaRERA, the official one, is 30 December 2027, already 24 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Crystal Vue extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Vue's builder applied to MahaRERA to extend the completion date once: to 30 December 2027, giving the reason "The Developer was in process of commencing the development of the said project, however, due to the worldwide lockdown caused due to the COVID-19 pandemic, the Developer could not implement the timeline as decided. Thus, the Project was never started nor did the Developer sell any Units/ Apartment in the said Project. The Developer is in the process of starting the construction now, thus, the Developer is seeking extension of time for Project Completion till 30th December, 2027 from 30th December, 2025.".
What is the RERA number of Crystal Vue?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Crystal Vue in Sion Koliwada, Mumbai is P51900006774.
Is Crystal Vue registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Vue is registered as P51900006774 and its status is "Registered and active".
What is the current construction status of Crystal Vue? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Vue's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Vue is 68% done and internal work 18%. GharKundli's full report compares construction progress with the deadline.
Does Crystal Vue have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Crystal Vue safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Vue is registered on MahaRERA as P51900006774, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Crystal Vue?
Crystal Vue is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Crystal Vue start at 980 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Crystal Vue?
For a flat in Crystal Vue (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Crystal Vue received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Vue is still under construction, with 30 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Crystal Vue uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Crystal Vue was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Crystal Vue's possession date changes?
The latest dates are on Crystal Vue's MahaRERA page (P51900006774). GharKundli's Kundli Watch sends a free WhatsApp update on Crystal Vue every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Crystal Vue have?
According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Vue has one building filed: Vue with 37 floors and 45 units.
What are the flat sizes (carpet area) in Crystal Vue?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Crystal Vue: 4 BHK: 1463 sq ft carpet (19 homes); 3 BHK: 980 to 1893 sq ft carpet (18 homes); 5 BHK: 1893 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Crystal Vue have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 72 covered car parking spaces for Crystal Vue.
How big is the land of Crystal Vue?
According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Vue stands on 1,861 sq m of land (about 0.5 acres), with 7,326 sq m of sanctioned built-up area and 420 sq m of recreational open space.
What are the reviews of Crystal Vue?
Google Maps has reviews of Crystal Vue written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Crystal Vue?
Crystal Vue by Nageshwar V Neela is in Sion Koliwada, Mumbai, pincode 400037, Maharashtra, and is registered on MahaRERA as P51900006774, per GharKundli's check of MahaRERA records. Its boundaries filed there include Harbhansalal Marg. Its land is filed as 2pt,89pt. GharKundli lists all 36 MahaRERA projects in Antop Hill (400037).
How many flats are in Crystal Vue, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Vue has 45 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Crystal Vue registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Crystal Vue was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.
Does Crystal Vue have any legal issues or court cases?
6 court cases are listed for Crystal Vue on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Crystal Vue?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Nageshwar V Neela.
Check it yourself on MahaRERA
- How to check the possession date of Crystal Vue
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Ward FNorth
- Siddha Sky Phase V
- Samar Heights
- Om Building Co-operative Housing Society Limited
- Paramount
- Maaria Annexe
- Som Niwas
- Dosti Mezzo 22
- DNS Anuutham
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.