by DHOOT DEVELOPERS PVT. LTD. · Chembur East, MumbaiAlso near Chembur, Fci, Nehru Nagar

Possession: Dhoot Adi Residency-Shree Adi House CHSL is marked completed on MahaRERA.

Registered on MahaRERA under P51800008557. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on Dhoot Adi Residency-Shree Adi House CHSL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800008557
Status
Completed
Builder
DHOOT DEVELOPERS PVT. LTD.
Location
Chembur East, Mumbai · 400071
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
December 2018
Latest completion date
December 2019
Delay so far
12 months
Homes
23
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Kundli Watch

Dhoot Adi Residency-Shree Adi House CHSL: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Dhoot Adi Residency-Shree Adi House CHSL

What is the possession date of Dhoot Adi Residency-Shree Adi House CHSL?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Dhoot Adi Residency-Shree Adi House CHSL in Chembur East, Mumbai is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Dhoot Adi Residency-Shree Adi House CHSL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Dhoot Adi Residency-Shree Adi House CHSL's builder has filed on MahaRERA, the official one, is 31 December 2019, already 12 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Dhoot Adi Residency-Shree Adi House CHSL?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Dhoot Adi Residency-Shree Adi House CHSL in Chembur East, Mumbai is P51800008557.

Is Dhoot Adi Residency-Shree Adi House CHSL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Dhoot Adi Residency-Shree Adi House CHSL is registered as P51800008557 and its status is "Completed".

What is the construction status of Dhoot Adi Residency-Shree Adi House CHSL?

According to GharKundli's check of MahaRERA records (updated November 2026), Dhoot Adi Residency-Shree Adi House CHSL's status on MahaRERA is "Completed". GharKundli's full report compares construction progress with the deadline.

Does Dhoot Adi Residency-Shree Adi House CHSL have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Dhoot Adi Residency-Shree Adi House CHSL safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Dhoot Adi Residency-Shree Adi House CHSL is registered on MahaRERA as P51800008557, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Dhoot Adi Residency-Shree Adi House CHSL's possession date changes?

The latest dates are on Dhoot Adi Residency-Shree Adi House CHSL's MahaRERA page (P51800008557). GharKundli's Kundli Watch sends a free WhatsApp update on Dhoot Adi Residency-Shree Adi House CHSL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

Where is Dhoot Adi Residency-Shree Adi House CHSL?

Dhoot Adi Residency-Shree Adi House CHSL by DHOOT DEVELOPERS PVT. LTD. is in Chembur East, Mumbai (pincode 400071), near Chembur, Fci, Nehru Nagar, Maharashtra, and is registered on MahaRERA as P51800008557, per GharKundli's check of MahaRERA records.

How many homes are in Dhoot Adi Residency-Shree Adi House CHSL?

According to GharKundli's check of MahaRERA records (updated November 2026), Dhoot Adi Residency-Shree Adi House CHSL has 23 homes in 1 tower registered on MahaRERA.

When was Dhoot Adi Residency-Shree Adi House CHSL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Dhoot Adi Residency-Shree Adi House CHSL was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Dhoot Adi Residency-Shree Adi House CHSL?

No court cases are listed for Dhoot Adi Residency-Shree Adi House CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Dhoot Adi Residency-Shree Adi House CHSL?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DHOOT DEVELOPERS PVT. LTD., which has 4 other projects registered on MahaRERA.

Other projects in pincode 400071

All 284 projects in Chembur (400071) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.