71 Pardis
by Pardis Construction LLP · Chembur, Mumbai 400071Also near Bhandup West, Sindhi Society, Fort
What’s in the report? →Possession date of 71 Pardis (MahaRERA PR1180002500164): 30 April 2028. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1180002500164, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PR1180002500164, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about 71 Pardis?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of 71 Pardis has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: 71 Pardis’s extension records on MahaRERA (PR1180002500164), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on 71 Pardis
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1180002500164
- Status
- Registered and active
- Builder
- Pardis Construction LLP
- Location
- Chembur, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 30 Jun 2025
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of 71 Pardis, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 71 pardis | 100% | 65% | 20% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- 71 pardis: covers 0 floors
Latest CC order on MahaRERA: dated 24/11/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 71 Pardis every 1–2 months.
71 Pardis: buildings, flats and land, as filed on MahaRERA
- Land: 425 sq m (about 0.1 acres)
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Pardis Construction (a group of 5 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 10 months); 6 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project.
Read Google reviews of 71 Pardis →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
71 Pardis: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about 71 Pardis
What is the possession date of 71 Pardis?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 71 Pardis in Chembur, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for 71 Pardis?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 71 Pardis's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of 71 Pardis?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 71 Pardis in Chembur, Mumbai is PR1180002500164.
Is 71 Pardis registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 71 Pardis is registered as PR1180002500164 and its status is "Registered and active".
What is the current construction status of 71 Pardis? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), 71 Pardis's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 71 pardis is 65% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.
Does 71 Pardis have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is 71 Pardis safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), 71 Pardis is registered on MahaRERA as PR1180002500164, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in 71 Pardis?
71 Pardis is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in 71 Pardis?
For a flat in 71 Pardis (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has 71 Pardis received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), 71 Pardis is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is 71 Pardis a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), 71 Pardis's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has 71 Pardis uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for 71 Pardis was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if 71 Pardis's possession date changes?
The latest dates are on 71 Pardis's MahaRERA page (PR1180002500164). GharKundli's Kundli Watch sends a free WhatsApp update on 71 Pardis every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of 71 Pardis?
According to GharKundli's check of MahaRERA records (updated October 2026), 71 Pardis stands on 425 sq m of land (about 0.1 acres).
What is the track record of 71 Pardis's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Pardis Construction (a group of 5 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 10 months); 6 still being built, none past the promised date yet. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of 71 Pardis?
Google Maps has reviews of 71 Pardis written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of 71 Pardis?
71 Pardis by Pardis Construction LLP is in Chembur, Mumbai, pincode 400071 (near Bhandup West, Sindhi Society, Fort), Maharashtra, and is registered on MahaRERA as PR1180002500164, per GharKundli's check of MahaRERA records. GharKundli lists all 318 MahaRERA projects in Chembur (400071).
When was 71 Pardis registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 71 Pardis was registered on MahaRERA on 30 June 2025. GharKundli did not find a title report on the land on file there.
Does 71 Pardis have any legal issues or court cases?
No court cases are listed for 71 Pardis on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of 71 Pardis?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pardis Construction LLP, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of 71 Pardis
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Chembur (400071)
- Shree Saraswati CHS LTD Plot 8B
- Icons 71
- Viera Golf Greens
- Arham Mourya
- Tulsi Chamber Phase II
- Queens Park
- Sampoorna
- Sayba Samriddhi
Other projects by Pardis Construction LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.