SHREE SARASWATI CHS LTD PLOT 8B

by NAV DURGA CONSTRUCTION COMPANY · Chembur, Mumbai

Possession date of SHREE SARASWATI CHS LTD PLOT 8B: 30 November 2026, moved from 30 December 2023 (31 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800017436, and currently active. Its completion date has moved from December 2023 to November 2026: 31 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 10 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHREE SARASWATI CHS LTD PLOT 8B?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHREE SARASWATI CHS LTD PLOT 8B has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 31 August 2024

    Extended at the builder's request (MahaRERA application EXT51800018300)

    Reason the builder gave MahaRERA:
    “THE LOCKDOWNS LED TO CONSTRUCTIN ACTIVITIES COMING TO A STANDSTILL DUE TO NON AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY AFFECTED, EVEN WE…” Read the full reason“THE LOCKDOWNS LED TO CONSTRUCTIN ACTIVITIES COMING TO A STANDSTILL DUE TO NON AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY AFFECTED, EVEN WE ARE UNABLE TO RECOVER FUNDS EXISTING BUYERS AS FINANCIAL CRISIS ARE FACED BY ALMOST EVERYONE DUE TO FUND ISSUE, NOW DEVELOPER HAVE TAKEN CONSTRUCTION FINANCE, CONSTRUCTION WORK IS IN PROGRESS.”
  3. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51800024698)

    Reason the builder gave MahaRERA: “DUE TO FINANCIAL CONSTRAINTS FACED CONSTRUCTION WORK IS STILL NOT COMPLETED THEREFORE REQUEST TO GIVE EXTENSION UTPTO 31ST MARCH 2025.”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800028325)

    Reason the builder gave MahaRERA: “DUE TO UNRESOLVED FINANCIAL ISSUES THAT HAVE IMPACTED PROGRESS OF THE PROJECT.DESPITE OF OUR BEST EFFORTS THE REQUIRED FIANANCIAL RESORCES ARE NO YET FULL SECURED.WE THEREFORE REQUEST EXTENSION UPTO 31ST DECEMBER 2025”
  5. 31 March 2026

    Extended at the builder's request (MahaRERA application EA23012619561)

    Reason the builder gave MahaRERA:
    “Due to financial constraints faced by us, the progress of the project was temporarily affected. We wish to inform you that all financial issues have now been resolved, and construction work has recommenced in full swing with adequate resour…” Read the full reason“Due to financial constraints faced by us, the progress of the project was temporarily affected. We wish to inform you that all financial issues have now been resolved, and construction work has recommenced in full swing with adequate resources deployed at site. We assure you that the interests of the allottees / customers are fully secured, and the project shall be completed within the extended period.”
  6. 31 July 2026

    Extended at the builder's request

  7. 30 November 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHREE SARASWATI CHS LTD PLOT 8B’s extension records on MahaRERA (P51800017436), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHREE SARASWATI CHS LTD PLOT 8B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 10 complaints, and how it ended
  • Construction pace against the November 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800017436
Status
Registered and active
Builder
NAV DURGA CONSTRUCTION COMPANY
Location
Chembur, Mumbai · 400071
Project type
Residential / Group Housing
Registered on
13 Aug 2018
Completion date at registration
December 2023
Latest completion date
November 2026
Delay so far
31 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
79
Sold or booked
92%
Towers
1
Complaints on MahaRERA
10
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SHREE SARASWATI CHS LTD PLOT 8B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREE SARASWATI CHS LTD BLDG B6 AND A1100%100%100%90%

Commencement certificate (CC), as filed on MahaRERA

  • SHREE SARASWATI CHS LTD BLDG B6 AND A1: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE SARASWATI CHS LTD PLOT 8B every month.

SHREE SARASWATI CHS LTD PLOT 8B: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK635 – 87779
  • Buildings: SHREE SARASWATI CHS LTD BLDG B6 AND A1 (16 floors, 79 units)
  • Land: 11,541 sq m (about 2.9 acres) · sanctioned built-up 5,799 sq m · recreational space 3,230 sq m

The builder’s record and reviews

NAV Durga Construction (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 3 months); 6 still being built, 6 past the promised date (typically 18 months late); 1 lapsed. 59 complaints on MahaRERA across 6 projects.

Read Google reviews of SHREE SARASWATI CHS LTD PLOT 8B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHREE SARASWATI CHS LTD PLOT 8B: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHREE SARASWATI CHS LTD PLOT 8B

What is the possession date of SHREE SARASWATI CHS LTD PLOT 8B?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE SARASWATI CHS LTD PLOT 8B in Chembur, Mumbai is 30 November 2026 — 31 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHREE SARASWATI CHS LTD PLOT 8B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE SARASWATI CHS LTD PLOT 8B's builder has filed on MahaRERA, the official one, is 30 November 2026, already 31 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHREE SARASWATI CHS LTD PLOT 8B extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SARASWATI CHS LTD PLOT 8B's builder applied to MahaRERA to extend the completion date 5 times: to 31 August 2024, giving the reason "THE LOCKDOWNS LED TO CONSTRUCTIN ACTIVITIES COMING TO A STANDSTILL DUE TO NON AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY AFFECTED, EVEN WE ARE UNABLE TO RECOVER FUNDS EXISTING BUYERS AS FINANCIAL CRISIS ARE FACED BY ALMOST EVERYONE DUE TO FUND ISSUE, NOW DEVELOPER HAVE TAKEN CONSTRUCTION FINANCE, CONSTRUCTION WORK IS IN PROGRESS."; to 31 March 2025, giving the reason "DUE TO FINANCIAL CONSTRAINTS FACED CONSTRUCTION WORK IS STILL NOT COMPLETED THEREFORE REQUEST TO GIVE EXTENSION UTPTO 31ST MARCH 2025."; to 31 December 2025, giving the reason "DUE TO UNRESOLVED FINANCIAL ISSUES THAT HAVE IMPACTED PROGRESS OF THE PROJECT.DESPITE OF OUR BEST EFFORTS THE REQUIRED FIANANCIAL RESORCES ARE NO YET FULL SECURED.WE THEREFORE REQUEST EXTENSION UPTO 31ST DECEMBER 2025"; to 31 March 2026, giving the reason "Due to financial constraints faced by us, the progress of the project was temporarily affected. We wish to inform you that all financial issues have now been resolved, and construction work has recommenced in full swing with adequate resources deployed at site. We assure you that the interests of the allottees / customers are fully secured, and the project shall be completed within the extended period."; to 31 July 2026. MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SHREE SARASWATI CHS LTD PLOT 8B?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHREE SARASWATI CHS LTD PLOT 8B in Chembur, Mumbai is P51800017436.

Is SHREE SARASWATI CHS LTD PLOT 8B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SARASWATI CHS LTD PLOT 8B is registered as P51800017436 and its status is "Registered and active".

What is the construction status of SHREE SARASWATI CHS LTD PLOT 8B?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SARASWATI CHS LTD PLOT 8B's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHREE SARASWATI CHS LTD BLDG B6 AND A1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SHREE SARASWATI CHS LTD PLOT 8B have complaints on MahaRERA?

10 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SHREE SARASWATI CHS LTD PLOT 8B safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SARASWATI CHS LTD PLOT 8B is registered on MahaRERA as P51800017436, its completion date has moved 31 months since registration and 10 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHREE SARASWATI CHS LTD PLOT 8B's possession date changes?

The latest dates are on SHREE SARASWATI CHS LTD PLOT 8B's MahaRERA page (P51800017436). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE SARASWATI CHS LTD PLOT 8B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHREE SARASWATI CHS LTD PLOT 8B have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SARASWATI CHS LTD PLOT 8B has one building filed: SHREE SARASWATI CHS LTD BLDG B6 AND A1 with 16 floors and 79 units.

What are the flat sizes (carpet area) in SHREE SARASWATI CHS LTD PLOT 8B?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SHREE SARASWATI CHS LTD PLOT 8B: 2 BHK: 635 to 877 sq ft carpet (79 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of SHREE SARASWATI CHS LTD PLOT 8B?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SARASWATI CHS LTD PLOT 8B stands on 11,541 sq m of land (about 2.9 acres), with 5,799 sq m of sanctioned built-up area and 3,230 sq m of recreational open space.

What is the track record of SHREE SARASWATI CHS LTD PLOT 8B's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), NAV Durga Construction (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 3 months); 6 still being built, 6 past the promised date (typically 18 months late); 1 lapsed. 59 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SHREE SARASWATI CHS LTD PLOT 8B?

Google Maps has reviews of SHREE SARASWATI CHS LTD PLOT 8B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 10 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHREE SARASWATI CHS LTD PLOT 8B?

SHREE SARASWATI CHS LTD PLOT 8B by NAV DURGA CONSTRUCTION COMPANY is in Chembur, Mumbai (pincode 400071), Maharashtra, and is registered on MahaRERA as P51800017436, per GharKundli's check of MahaRERA records.

How many homes are in SHREE SARASWATI CHS LTD PLOT 8B?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SARASWATI CHS LTD PLOT 8B has 79 homes in 1 tower registered on MahaRERA, and 92% of them are sold or booked.

When was SHREE SARASWATI CHS LTD PLOT 8B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE SARASWATI CHS LTD PLOT 8B was registered on MahaRERA on 13 August 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on SHREE SARASWATI CHS LTD PLOT 8B?

No court cases are listed for SHREE SARASWATI CHS LTD PLOT 8B on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SHREE SARASWATI CHS LTD PLOT 8B?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NAV DURGA CONSTRUCTION COMPANY, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400071

All 318 projects in Chembur (400071) →

Other projects by NAV DURGA CONSTRUCTION COMPANY

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.