Sayba Samriddhi
by Shanaya Star (Gagangiri) · Chembur East, MumbaiAlso near Chembur West, Govandi, Subhash Nagar
Possession date of Sayba Samriddhi: 30 October 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800078403, and currently active. Its completion date is now October 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Sayba Samriddhi?
How the possession date of Sayba Samriddhi has moved
30 June 2027
Completion date given when the project was registered
30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sayba Samriddhi’s extension records on MahaRERA (P51800078403), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sayba Samriddhi
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800078403
- Status
- Registered and active
- Builder
- Shanaya Star
- Location
- Chembur East, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 11 Dec 2024
- Completion date at registration
- June 2027
- Latest completion date
- October 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 125
- Sold or booked
- 90%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sayba Samriddhi, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sayba Samriddhi | 100% | 100% | 100% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- Sayba Samriddhi: covers up to top of 16th floor
Latest CC order on MahaRERA: dated 18/03/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sayba Samriddhi every month.
Sayba Samriddhi: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 584 – 679 | 108 |
| 1 BHK | 468 – 503 | 16 |
| Other | 668 | 1 |
- Buildings: Sayba Samriddhi (18 floors, 125 units)
- Car parking: 84 covered
- Land: 897 sq m (about 0.2 acres) · sanctioned built-up 7,795 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Gagangiri Construction (a group of 15 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 15 months); 14 still being built, none past the promised date yet; 1 lapsed. 7 complaints on MahaRERA across 3 projects.
Read Google reviews of Sayba Samriddhi →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sayba Samriddhi: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sayba Samriddhi
What is the possession date of Sayba Samriddhi?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sayba Samriddhi in Chembur East, Mumbai is 30 October 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Sayba Samriddhi?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sayba Samriddhi's builder has filed on MahaRERA, the official one, is 30 October 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Sayba Samriddhi?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sayba Samriddhi in Chembur East, Mumbai is P51800078403.
Is Sayba Samriddhi registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Samriddhi is registered as P51800078403 and its status is "Registered and active".
What is the construction status of Sayba Samriddhi?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Samriddhi's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sayba Samriddhi is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Sayba Samriddhi have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sayba Samriddhi safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Samriddhi is registered on MahaRERA as P51800078403, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Sayba Samriddhi's possession date changes?
The latest dates are on Sayba Samriddhi's MahaRERA page (P51800078403). GharKundli's Kundli Watch sends a free WhatsApp update on Sayba Samriddhi every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sayba Samriddhi have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Samriddhi has one building filed: Sayba Samriddhi with 18 floors and 125 units.
What are the flat sizes (carpet area) in Sayba Samriddhi?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sayba Samriddhi: 2 BHK: 584 to 679 sq ft carpet (108 homes); 1 BHK: 468 to 503 sq ft carpet (16 homes); Other: 668 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Sayba Samriddhi have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 84 covered car parking spaces for Sayba Samriddhi.
How big is the land of Sayba Samriddhi?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Samriddhi stands on 897 sq m of land (about 0.2 acres), with 7,795 sq m of sanctioned built-up area.
What is the track record of Sayba Samriddhi's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Gagangiri Construction (a group of 15 linked companies) has 23 projects on MahaRERA since 2017, this one included. Of the 23 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 15 months); 14 still being built, none past the promised date yet; 1 lapsed. 7 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Sayba Samriddhi?
Google Maps has reviews of Sayba Samriddhi written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sayba Samriddhi?
Sayba Samriddhi by Shanaya Star (Gagangiri) is in Chembur East, Mumbai (pincode 400071), near Chembur West, Govandi, Subhash Nagar, Maharashtra, and is registered on MahaRERA as P51800078403, per GharKundli's check of MahaRERA records.
How many homes are in Sayba Samriddhi?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Samriddhi has 125 homes in 1 tower registered on MahaRERA, and 90% of them are sold or booked.
When was Sayba Samriddhi registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sayba Samriddhi was registered on MahaRERA on 11 December 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on Sayba Samriddhi?
No court cases are listed for Sayba Samriddhi on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Sayba Samriddhi?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shanaya Star, the company Gagangiri files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Sayba Samriddhi
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400071
- SHREE SARASWATI CHS LTD PLOT 8B
- TULSI CHAMBER PHASE II
- SAMPOORNA
- QUEENS PARK
- ARHAM MOURYA
- 71 Pardis
- ICONS 71
- Viera Golf Greens
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.